Substations for electrical transformers, gas regulators, and telephone subscriber carrier sites (excluding telecommunication/transmission towers/antennas) shall be permitted in any zoning district, if essential to the service of the district, provided that the following restrictions shall apply:
a) When located in a residential district, the use is permitted if it occupies a parcel that is one‐ quarter (0.25) acre or less and does not exceed the height limits of the district in which it is located, but shall be conditional if it occupies a parcel greater than one quarter (0.25+) acre or exceeds the height limits of the district in which it is located.
b) The minimum lot area and width requirements for the zoning district shall not apply, but the utility substation shall comply with all yard setback requirements for the district in which it is located, which shall be in addition to the required buffers.
c) The substation shall be screened in a manner to hide it from view from the adjacent property. Required buffers/screening shall be installed and maintained as specified in the Specific Provisions Section of this Development Ordinance.
d) Such use shall be secured within a building, or completely surrounded by a security fence or wall with locked gate(s), said fence/wall having a minimum height of eight (8) feet;
e) Such use shall not involve the storage of vehicles or service equipment;
f) All open areas shall be maintained and kept free of weeds and debris.
g) Any lighting on the property shall be of such type or installation that prevents direct view of the light source from adjacent residences and does not cause any glare to occur on adjacent properties or streets.
h) Where utility substations are a permitted use, a site development sketch shall be submitted to the Planning and Zoning Official(s) for approval to insure compatibility of the facilities with the surrounding property and compliance with this Ordinance. Where utility substations are a conditional use, a comprehensive site development plan shall be required as specified in the Amendments Section of this Development Ordinance.
Leer este código donde se publica (county website (oglethorpecountyga.gov)) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.