Sec. 302-45. Process for approval ofland disturbance permit.
Sobre este texto
- As published by Municode, current through 2026-01-27
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Procedures.
(1) Application requirements. An application for a land disturbance permit shall be submitted to the department and shall include:
a. Application on the form furnished by the department.
b. The applicable civil design and construction drawings prepared in conformance with the specifications and standards of article IV of this chapter.
c. Preliminary plat or site plan requesting or reflecting project approval by the department, if applicable.
d. The erosion and sedimentation control plan and supporting documentation required in chapter 306.
e. Stormwater management concept plan, permit application, and stormwater management plan as provided in chapter 310.
f. Payment of all land disturbance permit fees established by the board of comm1ss1oners.
(2) Other agency approval. The applicant may be required by the department to secure development approval from other agencies if they are affected by the development. Development approval may be required from but not limited to:
a. Fire department.
b. Rockdale Water Resources.
c. Rockdale County Health Department.
d. Georgia Department of Transportation.
e. Georgia Department of Natural Resources.
f. U. S. Army Corps of Engineers.
g. U. S. Environmental Protection Agency.
(3) Comments on applications. Upon receipt of comments from other county departments, the department shall indicate on a copy of the construction drawings, or in
writing, all comments related to compliance with this chapter, conditions of zoning approval, and other regulations under the purview of the county, as appropriate.
( 4) Forwarding of comments. The department shall forward to the applicant the county's review comments.
(5) Compliance. The applicant shall be responsible for compliance with all codes, regulations and zoning requirements and for the satisfaction of all of the comments of
the department. The owner also shall be responsible for obtaining necessary approvals and permits from all other agencies affected by the project prior to issuance of the permit.
(6) Disapproval.
a. If a land disturbance permit is disapproved, the director shall notify the applicant within 15 days of the date the application was submitted and provide notes or comments to indicate deficiencies.
b. No development activity may take place on the subject parcel until the permit application is resubmitted to address deficiencies and approved by the department.
c. Resubmission of the land disturbance permit shall require payment of a resubmission fee.
(7) Conditions of approval. Minor changes, revision notes or additions to the plans may be made by the department; if required for approval, notes shall be conditions of permit approval.
Historia
(Ord. No. 0-2006-32, §§ 1-3, 11-28-2006)