2.5.1. Responsibility.

Sobre este texto

  • As published by Municode, current through 2026-01-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

a. No person shall conduct any pre-construction, land-disturbing and/or development activity involving more than 0.4 acres

without first obtaining a development permit from the Chief Building Official to perform such activity, unless exempted

under other sections of this code. (See Article 6.13.)

b. Any person proposing development shall first submit to the Building Inspection Department an application for a development permit, including all civil design and construction drawings required by

this Development Code.

c. The Building Inspection Department is responsible for administering and coordinating the review process for issuance of development permits. The Building Inspection Department shall forward a copy of the development permit application, including the civil design and constructions drawings for the project, to the Planning

Department, Public Works Department and other departments, the Soil and Water Conservation District, the Georgia Department of Transportation or others as appropriate, for their review and comment. The Building Inspection Department shall provide all comments to the applicant for resolution, and shall issue

the development permit when all requirements of this Development Code are met.

d. Approval of plans by the City or County shall not imply or transfer acceptance of responsibility for the application of the principles of engineering, architecture, landscape architecture or any other profession, from the professional, corporation or individual under whose hand or supervision the plans were prepared.

e. The completion of inspections and authorization for work continuation shall not transfer responsibility for the quality of

the work performed or materials used from the owner, nor imply or transfer acceptance of responsibility for project design or engineering from the professional, corporation or individual under whose hand or supervision the plans were

prepared.

f. No development permit shall be interpreted to relieve any owner of the responsibility of maintaining full compliance with all applicable codes, ordinances and other

regulations. Any development permit issued in error or in contradiction to the provisions of this Development Code shall

be considered to have been null and void upon its issuance.

g. Liability.

(1) The approval of an erosion and sediment control plan or other plans under the provisions of this Development Code, the issuance of a development permit, or the compliance with the any other provisions of this

Development Code shall not relieve any person from the responsibility for damage to any person or property otherwise imposed by law nor impose any liability upon the governing body or the Coosa River Soil and Water Conservation Commission District for damage to any person or

property.

(2) The fact that any activity for which a development permit has been issued results in injury to the property of another shall neither constitute proof of nor create a presumption of a violation of the standards provided for in this Development Code or the terms of the development permit.

2.5.2. Development activities authorized. A development permit shall be issued to authorize all activities associated with development activity

regulated by this Code, including, but not limited to, clearing and grubbing, grading and the construction of such improvements as streets, surface parking areas and drives, storm water drainage facilities, sidewalks, or other structures permanently placed on or in the property except

for buildings, signs, or other structures requiring the issuance of a building permit.

2.5.3. Process for approval of development permit. An application for a development permit may proceed simultaneously with an application for

site plan, but may not be issued prior to project approval of such plan by the Building Inspection Department.

a. The application for a development permit shall be submitted to the Building Inspection Department and must include the following:

(1) Application on the form furnished by the Building Inspection Department, requesting review for issuance of a development permit.

(2) Six copies of:

(a) The civil design and construction drawings prepared in conformance with the specifications and standards in this Development Code.

(b) Site plan requesting or reflecting project approval by the Building Inspection Department.

(3) Payment of any development permit fee, as established from time to time by the Governing Body.

b. The application will be checked for completeness within five business days of its submission. Incomplete applications will

be returned to the applicant.

c. Upon receipt of a complete development permit application, the Building Inspection Department shall refer the soil erosion and sediment control plan to the Coosa River Soil and Water Conservation

District for its review and approval or disapproval concerning the adequacy of the erosion and sediment control plan. No development permit will be issued unless the plan has been approved by the district, and any variances and bonding, if required, have been obtained.

d. The applicant may be required by the Building Inspection Department to secure development approval from other agencies if they are affected by the development. Development approval may be required from but not limited to:

(1) The Planning Department.

(2) The Public Works Department.

(3) The Public Utilities Department.

(4) Fire Department.

(5) County Health Department.

(6) Coosa River Soil and Water Conservation Commission District.

(7) Georgia Department of Transportation.

(8) Georgia Department of Natural Resources.

(9) U.S. Army Corps of Engineers.

(10) U.S. Environmental Protection Agency.

e. Upon receipt of comments from other departments, the Building Inspection Department shall forward all comments related to compliance with this Development Code, conditions of zoning approval, and

other regulations or ordinances, as appropriate.

f. The applicant shall be responsible for compliance with all codes, regulations and zoning requirements and for the satisfaction of all of the comments received from the various departments and agencies.

g. Reserved.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:rome/zoning/2.5.1@2026-01-26-5f2b0df216

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Rome Zoning Ordinance, 2.5.1. Responsibility | Georgia Commons