Groundwater recharge areas shall adhere to the following development standards:

1. Secondary Containment for New Above-Ground Storage Tanks

All new above-ground chemical or petroleum storage tanks shall have secondary containment for 110% of the volume of such tanks or 110% of the volume of the largest tank in a cluster of tanks.

2. Liners for New Agricultural Waste Impoundment Sites

New agricultural waste impoundment sites shall be lined if they are within:

1. A high pollution susceptibility area;

2. A medium pollution susceptibility area and exceed 15 acre-feet in size; or

3. A low pollution susceptibility area and exceed 50 acre-feet in size.

At a minimum, the liner shall be constructed of compacted clay having a thickness of one (1) foot and a vertical hydraulic conductivity of less than 5x10-7cm/sec or other criteria established by the Natural Resource Conservation Service. Applications for a building permit for a new agricultural waste impoundment site that requires a liner under the provisions of this subsection shall include a site development plan that shows the location and design of the liner.

3. On-Site Sewage Management System Tanks and Drain Fields 1. No construction may proceed on any building or manufactured home to be serviced by an on-site sewage management system tank and drain field without applying for and obtaining an On-Site Sewage Management System Construction Permit from the Chatham County Health Department as stated in Chapter 290-5-26 *On-Site Sewage Management Systems* of the Georgia Department of Public Health. 2. As provided in Chapter 290.5.26.7 *Absorption Fields of the On-Site Management Systems* of the Georgia Department of Public Health, no absorption field shall be installed in areas where groundwater, soil characteristics or adverse geological formation may interfere with the absorption or effective treatment of sewage effluent. 3. New lots shall meet the minimum lot sizes as identified in the rules of the Georgia Department of Natural Resources Chapter 391-1-16 Rules for Environmental Planning Criteria. In no case shall the minimum lot size be less than that allowed by the base zoning district.

4. Impervious Surfaces for Hazardous Materials Handling Operations

Within all pollution susceptibility areas, new facilities that handle hazardous constituents in amounts of 10,000 pounds or more on any one day shall perform their operations on impervious surfaces and in conformance with any applicable Federal spill prevention requirements and the City of Savannah Fire and Life Safety Code requirements. This provision shall not apply to underground storage tanks. Applications for a building permit for hazardous materials handling operations as defined in this subsection shall include a site plan that shows the location and design of any required spill and leak collection systems.

5. Permanent Stormwater Infiltration Basins

Permanent stormwater infiltration basins shall not be constructed in areas having high pollution susceptibility.

Leer este código donde se publica (enCodePlus) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:savannah/zoning/10.3.4@2026-11-14-be4b050140

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Savannah Zoning Ordinance, 10.3.4. Development Standards | Georgia Commons