Screven County · Ordenanza de zonificación
Appendix A - ZONING / Article 17 - TELECOMMUNICATIONS TOWERS AND ANTENNAS
Sec. 1706. Administrative approvals.
Sobre este texto
- As published by Municode, current through 2021-06-08
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
A. General.
1. The department may administratively approve the uses set forth in section 1706.E of this article. All such uses shall comply with requirements set forth in this article and all other applicable codes and ordinances.
2. Except as provided in section 1706.D, the department shall respond to each application within 45 days of its receipt by either approving or denying the application. One 45-day extension of this review period may be exercised by the department if such additional time is deemed necessary to adequately assess the request. If the department fails to respond to the applicant within a maximum of 90 days, the application shall be deemed to be approved.
3. As part of any administrative approval, the department may administratively reduce setback requirements by up to ten percent to compensate for irregularly shaped lots or parcels; provided, however, that setback requirements shall not be reduced in conflict with engineering requirements for safety or structural failure containment [see section 1705.A.5.(e)].
4. Any decision by the department that results in the denial of a request to place, construct, or modify wireless telecommunications facilities shall be in writing and supported by substantial evidence. In addition to the requirements set forth in section 1706.E for uses allowed by administrative approval, the department shall consider the applicable factors set forth in section 1707.F in acting upon an application for administrative approval.
B. Application contents fee. All applications for administrative approval of a permit shall be submitted to the Screven County zoning administrator. Each application shall contain as a part thereof detailed plans and specifications as set forth in section 1705. An application for administrative approval for [a] permit shall not be accepted for processing without the information required in section 1705 of this article. An application fee shall be charged by the department in an amount stated in section 1709 of this article.
C. Collocation of antennas required. Applicants for the erection of a tower of placement of an antenna shall be required to collocate upon an existing tower or alternative tower structure.
An exception to collocation shall only be made if the applicant adequately demonstrates that an existing tower suitable for collocation does not exist in the geographic antenna placement area, and that no suitable alternative tower structure is available as set forth in section 1704.D.
D. Independent expert review. If, in the opinion of the office, an independent expert review of an application is warranted, the office may engage a licensed professional engineer or other appropriate professional, as an independent expert to review any of the materials submitted by an applicant and render an opinion on any issue relevant to the application, the adequacy of the supporting data, structural integrity and the feasibility of alternative sites or collocation. Upon the review by an independent expert, the department shall convey its concerns to the applicant in writing and shall allow the applicant a reasonable opportunity to address those concerns. If the applicant is unable to satisfactorily address those concerns, the applicant shall be allowed a reasonable amount of time, not to exceed 30 days, in which to modify the application to alleviate the department's concerns or withdraw the application altogether. The expert's opinion shall be considered determinative, unless the applicant agrees to pay the expenses of submitting both opinions for a peer review, which review shall then be considered final. If the independent third party expert supports the applicant's expert, then the department shall pay the expenses of said third-party expert. If the independent third-party expert supports the position of the department, then the applicant shall respond within 30 days following the final review as herein provided. No permit shall be issued until the applicant has paid all expenses incurred under this section.
E. Uses allowed by administrative approval. The following uses may be approved by the department after conducting an administrative review:
1. If it is adequately demonstrated that antenna collocation, as required by section 1706.C above, is not possible for a given geographic antenna placement area, construction of a new tower up to a height of 150 feet, including the placement of additional buildings or other supporting equipment used in connection with said tower or antenna, may be permitted in the following zoning districts:
a. General commercial (GC).
b. Light industrial (LI).
c. Heavy industrial (HI).
d. Agricultural and residential (AG-3).
provided, however, that all structures shall meet the setback, screening and buffer requirements contained herein.
2. So long as the addition of said antenna adds no more that ten feet to the height of the existing alternative tower structure:
a. Installation of an antenna on an existing alternative tower structure in any nonresidential district; or
b. Installation of an antenna on an existing county owned alternative tower structure in any nonresidential district, provided a lease authorizing the antenna has been approved by the governing authority.
3. So long as the addition of said antenna adds no more than ten feet to the height of the existing tower:
a. Installation of an antenna on an existing tower of any height in any nonresidential district, and further including the placement of additional buildings or other supporting equipment used in connection with said antenna; or
b. Installation of an antenna on an existing tower locate on property owned, leased, or otherwise controlled by the county in any nonresidential district, and further including the placement of additional buildings or other supporting equipment used in connection with said antenna, provided a lease authorizing the tower has been approved by the governing authority.
4. Construction of a new tower up to a height of 150 feet, including the placement of additional buildings or other supporting equipment used in connection with said tower or antenna, if placed upon property owned, leased or otherwise controlled by the county in any nonresidential district, providing a lease authorizing the tower has been approved by the governing authority.
5. Agricultural GPS towers meeting the requirements of this article.
F. Public notice; appeal. At lease 15 days prior to the issuance of a permit for the construction of a tower or antenna as an administratively approved use except for collocation permits, the department shall cause a sign to be posted on the property and the publication of a public notice in the newspaper in which sheriff's advertisements appear. Said public notice shall state the nature of the application, height of the proposed structure, street address of the proposed location, or other identifying information necessary to inform the public of the proposed location. The expense of the public notice shall be borne by the applicant. If, during the public notice period, a written objection to the permit application is filed, the validity of the application and all pertinent documentation shall be determined by the planning and zoning commission. Said objection must make reference to the specific section of the article which the objector contends is not met and provide supporting documentation therefor. The objection shall be placed on the first available agenda of a regularly scheduled meeting following the expiration of the 15-day appeal period. The planning and zoning commission shall dispense with the objection by either:
1. A determination that the application is valid and meets all applicable criteria of this article, which shall result in the issuance of a building permit.
2. A determination that the application does not satisfy all applicable criteria of this article. Applications so found must, as a result, be processed through the conditional use permit process set forth in section 1707 contained herein.
3. Review of the decision of the planning and zoning commission shall be by writ of certiorari to the Superior Court of Screven County.
G. Appeal of administrative determination. If a permit application for a tower as an administratively permitted use is determined by the department to not meet all applicable criteria of this article, the applicant may appeal the determination to the planning and zoning commission in accordance with the Zoning Ordinance of Screven County, Georgia.
The planning and zoning commission shall dispose with the objection by either:
1. A determination that the application is valid and meets all applicable criteria of this article, which shall result in the issuance of a building permit.
2. A determination that the application does not satisfy all applicable criteria of this article. Applications which do not satisfy all applicable criteria must, as a result, be processed through the conditional use permit process set forth in section 1707 contained herein.
3. Review of the decision of the planning and zoning commission shall be by writ of certiorari to the Superior Court of Screven County.
Historia
(Ord. of 9-9-2009, § 5)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.