Ir al contenido
Georgia Commons
Menú

Snellville · Ordenanza de zonificación

Snellville Zoning Ordinance

Este documento se muestra completo, como un solo texto: su fuente no lo divide en secciones.

Sobre este texto

  • As published by Municode, current through 2026-07-13
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
  • Read by OCR from a scanned page: a character, a name, or a number may be misread.

Este texto se leyó por OCR de una página escaneada: una letra, un nombre o un número pueden estar mal leídos.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Parte 2 de 7. Este texto es largo, así que su página lo muestra en partes, en el orden de la fuente. Un enlace a uno de sus párrafos lleva a la parte que lo contiene.

1. The applicant for a discretionary development proposal may voluntarily agree to pay for the cost of providing the system improvements, or a pro-rated share of the cost of said system improvements that are reasonably attributed to the subject development, as determined by the City.

2. When an application is for a discretionary development proposal before the City Council, the City may find that the proposed development will provide substantial adverse impacts on the transportation system. The City may find further that the existing transportation system is insufficient to serve the proposed development and the City is unable to provide adequate transportation facilities within a reasonable amount of time after the impacts of said development would occur. Given such findings, the City Council may reduce the development density or intensity to the degree that the impacts of the development proposal do not degrade transportation facilities below adopted level of service standards, require a phasing of the development in a manner that adequate public facilities will be provided publicly or privately, or in cases where such other alternatives do not address the adverse impacts, deny an application for a discretionary development proposal.

103-5.3. Subdivision Review

A. Pre-application Conference When any subdivision of a tract of land is proposed, whether for residential or nonresidential development, the subdivider is encouraged to present to the Department preliminary documents and graphic exhibits to allow early evaluation of the subdivider's intentions and coordination with the Comprehensive Plan and UDO regulations, and to inform and provide the subdivider with the necessary regulations in order to properly accomplish the proposed project.

B. Concept Plan Approval

1. Application for concept plan approval must be submitted to the Department using an application form and in a number of copies to be determined by the Director. The concept plan must include the entire property proposed for development but need not include the applicant's entire contiguous ownership.

2. If the subdivider chooses not to submit a concept plan, then the subdivider may proceed directly with the submittal of development plans (called a preliminary plat) if they show the entire property proposed for development. In so doing, however, the subdivider assumes the risk of premature design and engineering expenses if the City requires subsequent design and engineering changes.

3. Copies of the approved concept plan must be provided to the Department for permanent record, in a number as determined by the Director.

C. Development Plans Approval for Subdivisions

1. An application for development plans (called a preliminary plat) approval and issuance of a development permit must be submitted to the Department using an application form and in a number of copies as determined by the Director. The development plans may encompass a portion of a property included within an approved concept plan. However, if no concept plan has been approved, the development plans must include the entire property being developed and having the same zoning district. The application must include the preliminary plat, and construction drawings. All construction drawings and other engineering data shall be prepared and sealed by a professional engineer currently registered in the State of Georgia, in accordance with provisions of Georgia Law.

2. The Director must indicate on a review copy of the drawings or in a written memorandum all comments related to compliance of the development plans with this section, principles of good design, this UDO, conditions of zoning approval, and the regulations of other City and County departments and State agencies as appropriate.

The Director has final authority to determine the applicability of any and all comments under this UDO or conditions of zoning approval.

3. A preliminary plat may not be approved when it shows a lot that would present particularly unusual difficulties for construction of a building, which would clearly require a variance to be reasonably usable, or which is otherwise "unbuildable" because of its unusability, whether due to the presence of floodplain, unusual configuration, lack of public utilities or for any other reason. A House Location Plan (HLP) may be required to be filed as a part of the preliminary plat approval to substantiate the buildability of any such difficult or unusual lot. This provision does not apply to lots used exclusively for subdivision identification signage, entrance or landscape features, common areas, open spaces, private alleys, or stormwater facilities.

4. The subdivider is responsible for compliance with all codes, regulations, and zoning requirements and for the satisfaction of all of the noted and written comments of the Director.

5. If an applicant disagrees with the findings or final review comments of the Director or of any other City department, concluding that factual or interpretive errors have been made, the appeal procedure of Sec. 103-7.3 (Administrative Decision Appeals) must be followed to resolve the issues.

6. When the Director has determined that the plat and other development plans are in compliance with all applicable City regulations and approval has been received from all affected City and County departments, the Director must sign and date a CERTIFICATE OF DEVELOPMENT PLANS APPROVAL stamped or printed on a reproducible copy of the plat. Copies of approved plat and development plans must be transmitted to the applicant and retained by the Department for its records.

7. After the above approval by all affected City and County departments, a development permit will be issued at the developer's request to begin construction activities based on the approved development plans.

D. Final Plat Approval

1. When the provisions of this subsection have been complied with, the subdivider may submit to the Department an application for final plat approval, using an application form and a number of copies as determined by the Director.

2. The Director must indicate on a review copy of the plat or in a written memorandum all comments related to compliance of the final plat with this UDO, conditions of zoning approval, and the regulations of other City and County departments and State agencies as appropriate. The Director will have final staff authority to determine the applicability of any and all comments under this UDO or conditions of zoning approval.

3. A final plat may not be approved when it shows or otherwise creates a lot that would present particularly severe and unusual difficulties for construction of a building, which would clearly require a variance to be reasonably usable, or which is otherwise "unbuildable" due to the presence of floodplain, unusual configuration, lack of Gwinnett County Health Department approval, or for any other justified reason.

This provision does not apply to lots used exclusively for subdivision identification signage, entrance or landscape features, common areas, open spaces, private alleys, or stormwater facilities.

4. Lots which would appear to be buildable under certain circumstances and would require further study or additional information before a building permit could be issued, but which present problems or unusual difficulties which can reasonably be addressed or overcome by the lot owner, may be included in the plat with the appropriate notation of the steps necessary to allow issuance of a building permit.

5. The subdivider is responsible for compliance with all codes, UDO requirements, and for the satisfaction of all of the comments of the Director.

6. Final approval by the Director may not be shown on the final plat until all requirements of these and other applicable regulations have been met, and the Director has received a completed request for approval of development conformance and an executed development performance and maintenance agreement. The agreement must be accompanied by a bond, letter of credit or other acceptable surety providing for the maintenance of all installations and improvements required by these regulations in the subdivision for a period not to exceed 12 months following the date of approval of development conformance for subdivisions for which the final topping of a "two-pass" street has not been applied or for a period not to exceed 24 months. The maintenance bond period of application may be extended by the Director at the request of the developer, provided it is in the best interest of the health, safety, and welfare of the public.

7. The Director must further determine that either:

a. All improvements and installation to the subdivision required for approval of the final plat under the rules and regulations of the City of Snellville have been completed in accordance with the appropriate specifications; or

b. All of the stormwater drainage and detention facilities, water and sewer utilities, street base and curbing construction required for approval of the final plat have been properly installed and completed and, for those required improvements not yet completed (grassing, pavement topping, required landscaping, sidewalks, etc.) a performance bond will have been filed by the subdivider with the development performance and maintenance agreement, which performance bond must:

i. Be conditioned upon the faithful performance by the subdivider or developer of all work required to complete all improvements and installations for the subdivision, or approved portion thereof, in compliance with these rules and regulations within a specified time, not to exceed 3 months;

ii. Be payable to, and for the indemnification of, the City;

iii. Be in an amount equal to the cost of construction of the required improvements not yet completed plus an additional 10% of said costs, as calculated by the Director on the basis of yearly contract prices or City contracts, where available;

iv. Be with surety by a company entered and licensed to do business in the State of Georgia; and

v. Be in a form acceptable to the Director or the City Attorney.

8. Payment for materials and installation of traffic control and street name signs must be made to the Department in accordance with the traffic engineering regulations before approval of the final plat. Payment of the cost of striping major thoroughfares or required signalization if required and not completed by the developer must also be received by the Department before approval of the final plat.

9. Payment of the required plat recording fee must be made to the Department before approval of the final plat.

10. Once the Department has approved the final plat and all other affected departments and agencies of government as required have certified compliance and signed the route sheet, the Director will certify by their signature on the original of the plat that all of the requirements of this UDO, and the conditions of zoning approval have been met, and that all other affected departments have approved the plat. The final plat may not be deemed approved until it has been signed by the Director and where the use of septic tanks is proposed, by a duly authorized representative of the Gwinnett County Health Department. The final plat when approved must be submitted to the Planning Commission for information purposes.

11. Once the final plat has been so certified, the Director must authorize it to be recorded by the developer with the Clerk of the Superior Court of Gwinnett County. The developer must record the final plat within 30 days after final approval. Any plat not submitted within 30 days for recordation will be considered invalid and have to be resubmitted for review. The subdivider must provide the Department with an appropriate number of copies of the recorded plat, as determined by the Director.

Deeds to lands dedicated to the City in fee simple, or to property owner associations for park or recreational use, must be recorded simultaneously with the final plat.

12. Periodically, but no less often than once each month, the Director must submit a listing of all approved final plats to the City Council for ratification of acceptance of all dedications.

103-5.4. Non-Subdivision Review

A. Pre-application conference When any development of a single site (other than a subdivision or a single-family detached or two-family dwelling) is proposed, the developer is encouraged to present to the Department preliminary documents and graphic exhibits to permit early evaluation of the developer's intentions and coordination with the Comprehensive Plan and this UDO, and to inform and provide the developer with the necessary regulations in order to properly accomplish the proposed project.

B. Concept Plan Approval

1. Application for concept plan approval must be submitted to the Department of Planning and Development using an application form and in a number of copies to be determined by the Director.

2. The concept plan must include the entire property being developed. Properties that adjoin the subject property and are under the same ownership or control as the subject property must be indicated as such. If the developer elects not to submit a concept plan, then the developer may proceed directly with the submittal of development plans, provided they show the entire site being developed. In so doing, however, the developer assumes the risk of premature design and engineering expenses in the event that the City requires subsequent design.

3. Copies of the approved concept plan must be provided to the Department for permanent record, in a number as determined by the Director.

C. Site Development Plan Approval

1. An application for development plan approval and issuance of a development permit must be submitted to the Department using an application form and in a number of copies as determined by the Director. The development plans may encompass a portion of a property included within an approved concept plan. However, if no concept plan has been approved, the development plans must include the entire property being developed and having similar zoning. As required by Sec. 103-6.7 (Site Development Plans), the application must include the site plan and construction drawings, as appropriate to the project. All construction drawings and other engineering data must be prepared and sealed by a professional engineer currently registered in the State of Georgia, in accordance with the provisions of Georgia law.

2. The Director must indicate on a review copy of the drawings or in a written memorandum all comments related to compliance of the development plans with this UDO, principles of good design, conditions of zoning approval, and the regulations of other City and County departments and State agencies as appropriate. The Director will have final staff authority to determine the applicability of any and all comments under these this UDO or conditions of zoning approval.

3. The developer is responsible for compliance with all codes, this UDO, and for the satisfaction of all of the noted and written comments of the Director.

4. Deeds to lands dedicated to the City in fee simple must be submitted to the Director for recording.

5. If an applicant disagrees with the findings or final review comments of the Director or of any other City department, concluding that factual or interpretive errors have been made, the appeal procedure of Sec. 103-7.3 (Administrative Decision Appeals) must be followed to resolve the issues.

6. When the Director has determined that the site plan and other development plans are in compliance with all applicable City regulations and this UDO, and approval has been received from all affected City and County departments, they will sign and date a certificate of development plans approval on a reproducible copy of the plan.

Approved copies of the approved development plans must be transmitted to the applicant and retained by the Department for its record.

7. Following the above approval by all affected City and County departments, a development permit will be issued at the developer's request to begin construction activities based on the approved development plans. Said permit may include clearing, grubbing, and grading as appropriate and approved as part of the project. A building permit may also be issued on the basis of the approved development permit under the provisions of Sec. 103-4 (Building Permits). A certificate of occupancy may not be issued, however, until a certificate of development conformance for the project has been executed by the owner and an executed development performance and maintenance agreement has been received in accordance with these regulations.

D. Certificate of Development Conformance Approval Process

1. Final approval by the Director may not be shown on the certificate of development conformance until all requirements of these and other applicable regulations have been met, and the Director has received a completed request for approval of development conformance and an executed development performance and maintenance agreement. The agreement must be accompanied by a bond, letter of credit or other acceptable surety providing for the maintenance of all installation and public improvements required by these regulations in the development for a period not to exceed 12 months following the date of approval of development conformance for developments for which the final topping of a "two-pass" street has not been applied or for a period not to exceed 24 months. The maintenance bond period of application may be extended by the Director at the request of the developer, provided it is in the best interest of the health, safety, and welfare of the public.

2. The Director must further determine that either:

a. All public improvements and installations to the development required to be dedicated and for approval of the certificate of development conformance under the rules and regulations of the City have been completed in accordance with the appropriate specifications; or

b. All of the stormwater drainage and detention facilities, water and sewer utilities, street base and curbing construction required for approval of the certificate of development conformance have been properly installed and completed, and, for those required public improvements not yet completed within areas to be dedicated (grassing, pavement topping, required landscaping, sidewalks, etc.), a performance bond will have been filed by the developer with the development performance and maintenance agreement, which performance bond will:

i. Be conditioned upon the faithful performance by the developer of all work required to complete all public improvements and installation required to be dedicated for the development, or approved portion thereof, in compliance with these rules and regulations within a specified time, not to exceed 3 months;

ii. Be payable to, and for the indemnification of, the City;

iii. Be in an amount equal to the cost of construction of the required public improvements required to be dedicated not yet completed plus an additional 10% of said costs, as calculated by the Director on the basis of yearly contract prices or City contracts, where available;

iv. Be with surety by a company entered and licensed to do business in the State of Georgia; and

v. Be in a form acceptable to the Director or the City Attorney.

3. Payment for materials and installation of traffic control must be made to the Department in accordance with the traffic engineering regulations before approval of the certificate of development conformance. Payment of the cost of striping major thoroughfares or required signalization if required and not completed by the developer must also be received by the Department before approval of the certificate of development conformance.

4. Payment of the required plat recording fee must be made to the Department before approval of the final plat.

5. Once the Department has approved the certificate of development conformance and all other affected departments and agencies of government as required have certified compliance and signed the route sheet, the Director must certify by their signature on the original of the certificate of development conformance that all of the requirements of this UDO, and the conditions of zoning approval have been met, and that all other affected departments have approved the plat. The certificate of development conformance is not deemed approved until it has been signed by the Director and, where the use of septic tanks is proposed, by a duly authorized representative of the Gwinnett County Health Department.

103-5.5. Assignment of Names, Addresses

A. Subdivision or Development Names

1. Proposed subdivision or development names must be reviewed and approved before the issuance of a development permit. Names must be reviewed by the Gwinnett County Department of Planning and Development upon submittal of the preliminary plat or site plan. This submittal must be made directly by the developer to that County department.

2. Proposed names may not duplicate or too closely approximate, phonetically, the name of any other subdivision or development in Gwinnett County or its municipalities except for extensions of existing subdivisions or developments.

3. Subdivision and development names may be reserved if submitted and approved along with the concept plan for the project.

B. Street Names

1. Proposed street names must be reviewed and approved before the approval of a final plat for recording. Street names may be reserved through approval as shown on an approved concept plan or preliminary plat for the subdivision. Proposed names for private streets must follow the same rules as for public streets.

2. Street names must consist of a root name of the developer's choosing and a suffix designation (such as "street," "avenue," "drive," etc.), and shall be followed by a quadrant suffix. Directional prefixes (i.e., "north," "south") and the prefixes "old" or "new" may not be used.

3. All streets shall bear the proper quadrant suffix appropriate to its location within the County (i.e., NE, NW, SE, and SW), as determined by the Gwinnett County Department of Planning and Development.

4. A proposed street that is obviously in alignment with another already existing and named street must bear the name of such existing street, unless this requirement is waived by the Gwinnett County Departments of Public Safety and Engineering.

5. Except within the same development, no proposed street name may duplicate (be spelled the same or be phonetically the same) as an existing street name within Gwinnett County regardless of the use of such suffix designations as "street," "avenue," "boulevard," "drive," "place," "way," "court," or however otherwise designated.

In the same subdivision, a root name may not occur more than twice.

6. All street root names and suffix designations are subject to the approval of the Gwinnett County Department of Planning and Development. Obscene or otherwise unacceptable language, abbreviations, contractions, or initials may not be used.

7. Root names may not exceed 13 characters including space, hyphens, etc. Letters not occurring in the English alphabet, and numerals, may not be used.

C. Street Address Assignments

1. A street address number must be assigned before issuance of a building permit. For any new structure proposed on a property that has not been assigned an address, a street number must be assigned upon confirmation or establishment of the property as a buildable lot of record under the requirements of these regulations.

2. Subdivisions. House numbers must be assigned after an exemption plat or preliminary plat is approved for the property. Submit two copies of the approved plat to the Gwinnett County Department of Planning and Development. Block number assignments must also be designated for abutting major street name signs at this time.

3. Commercial/industrial projects or buildings. Projects must be numbered after the developer submits the site plan to the City for development review. The developer must submit a copy of the site plan to the Gwinnett County Department of Planning and Development for this purpose.

4. Multifamily rental projects. Projects must be numbered after the developer submits copies of the site plan for development review. The overall development must be issued a single street address. The developer must number/letter individual buildings and units and must also submit a copy of the site plan to the Gwinnett County Department of Planning and Development for this purpose.

5. Multifamily and other condominium projects. Projects must be numbered after the developer submits the site plan for development review. Individual units must be numbered consecutively if located along public or private streets. Units in the "stacked-flat" configuration must use the same numbering approach as applies to an apartment project. The developer must submit a copy of the site plan to the Gwinnett County Department of Planning and Development for this purpose.

6. Numbering system. The following numbering systems must be followed, per postal regulations:

a. Individual mailbox for each dwelling unit: Each street in the project must be named.

b. Cluster box system—Centralized mailbox for the entire project: One street name will serve to assign all house numbers for main delivery.

103-5.6. Initiation of Development

A. Initial Activities Required After the issuance of any permit authorizing clearing and grading of a site:

1. Required erosion control measures must be installed, where practical, by the developer and inspected and approved by the Director before actual grading or removal of vegetation. All control measures must be in place as soon after the commencement of activities as possible and in coordination with the progress of the project.

2. Soil sedimentation facilities must be installed and operational before major grading operations.

3. Areas required to be undisturbed by this UDO, conditions of zoning approval, or other ordinance or regulation must be designated by survey stakes, flags, or other appropriate markings and must be inspected and approved by the Director before starting any clearing or grading activities.

B. Tree Protection Areas Before starting land disturbance activities, and throughout the clearing and grading process, the following must occur for any designated tree protection area in accordance with any approved buffer and landscape plan or tree preservation/replacement plan:

1. For those trees that are not to be removed, all temporary protection fencing, staking, and any tree protection area signs must be in-place. These barriers must be maintained throughout the land disturbance process and should not be removed until landscaping is begun.

2. The tree protection areas may not be used for the storage of earth and other materials resulting from or used during the development process.

3. Construction site activities, such as parking, materials storage, concrete washout, burning, etc., must be arranged to prevent disturbances in the tree protection areas.

C. Development Inspections The developer or contractor must verbally notify the Director at least 24 hours before starting each of the following phases, as authorized by any permit for site work or development. Inspections must be made by the Director and passed before the continuation of further activity or proceeding into new phases. A similar notification must be made to the Gwinnett County Inspection Department for any activity involving the water or sanitary sewer system.

1. Clearing or clearing and grubbing of the site or any portion included under the permit.

2. Grading. Installation of slope stakes is required. Upon completion of roadway grading, the water certificate shall be submitted to the Gwinnett County Department of Planning and Development certifying that the centerline of the road and the offset centerline of the water line is within 6 inches of that shown on the approved plans or relined plan submittal. Inspection and approval will be required before trenching or continuation with subbase preparation.

3. Installation of storm drainage pipe, detention, or other stormwater facilities.

4. Installation of sanitary sewer and appurtenances. This notification must be made simultaneously with official notification by the developer or contractor to the Gwinnett County Water Pollution Control Division, and if for informational purposes only, to the Department.

5. Curbing of roadways. Inspection should be requested before the forms have been set (if used). Roadway width will be spot checked by string line between curb stakes.

6. Subbase or subgrade of streets. After compaction, the subgrade must be string-lined for depth and crown. The subgrade must be roll tested and must pass with no movement, to the satisfaction of the inspection department.

7. Street base. The base must be string-lined for depth and crown and must pass a roll test with no movement to the satisfaction of the Director.

8. Paving. The Director must be on-site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be spot-checked, and the roadways will be cored after completion to check thickness.

D. Responsibility for Quality and Design The completion of inspections by City officials or employees and authorization for work continuation will not transfer responsibility for the quality of the work performed or materials used from the contractor or developer, nor imply or transfer acceptance of responsibility for project design or engineering from the professional corporation or individual under whose hand or supervision the plans were prepared.

E. Stop Work Orders Work which is not authorized by an approved permit, or which is not in conformance to the approved plans for the project, or which is not in compliance with the provisions of this UDO or any other adopted code, regulation or ordinance of the City, will be subject to immediate stop work order by the Director. Work which proceeds without having received the necessary inspections of the Director must be halted until all inspections of intervening work are completed.

F. Stabilization for Erosion Control If, for any reason, a clearing and grubbing, grading, or development permit expires after land disturbance activities have started, the developer must stabilize the site for erosion control, under the direction of the Director.

G. Silt Fence Removal Upon completion of a site development project, silt fences and other temporary erosion control measures must be removed before the issuance of a certificate of occupancy or within 30 days of permanent stabilization or submission of a notice of termination to the State of Georgia, whichever occurs first.

103-5.7. Approval of Development

A. Prerequisite to Final Plat or Certificate of Occupancy This approval is a prerequisite to the approval of a final plat or issuance of a certificate of occupancy for any part of a project or issuance of a certificate of occupancy for any part of a project included in a development permit, except for single-family detached dwellings and two-family dwellings. The approval must reflect the owner's certification that all site work and construction has been accomplished according to the terms of approved plans and permits, and that all facilities intended for maintenance, supervision and/or dedication to the public are in compliance with appropriate standards, regulations, codes and ordinances. Such approval will be revoked in cases of fraud or whenever unauthorized changes are made to the site without the benefit of required permits.

B. Submission Requirements Upon completion of the project authorized for construction by the development permit, the owner must file a certificate of development conformance with the Director, along with as-built surveys of all stormwater detention facilities and modifications to the limits of the 100-year floodplain (if any). An "as-built" hydrology study for the project with the actual parameters from the record drawing of the detention facilities must be prepared. A record drawing of the sanitary sewer facilities must also be prepared, separately or included with the above, and submitted to the Public Utilities Department of Gwinnett County as well as the Department in accordance with their regulations. The certificate of development conformance must be in a form as required by the Director and must be accompanied by a development performance and maintenance agreement completed in draft form. If the owner is a corporation, the documents must be signed by the president or vice president, be affixed by the corporate seal, and either the corporate secretary must attest to the signature and affix the corporate seal, or a certificate of corporate resolution must also be submitted.

C. Approval Following final inspection and approval of all record drawings, the Director must approve the certificate of development conformance.

103-5.8. Closeout and Maintenance

A. Development Performance and Maintenance Agreement Based on the approved certificate of development conformance, the owner must file a final development performance and maintenance agreement with the Director, along with any required certificate of corporate resolution and performance or maintenance surety, as a prerequisite to the approval of a final plat or issuance of a certificate of occupancy for any part of a project included in the development permit, except for single-family detached dwellings and two-family dwellings. The development performance and maintenance agreement must be in a form as required by the Director, and must include the following:

1. Final required improvements yet to be completed (e.g., grassing, topping, sidewalks, required landscaping) and performance bonding. Final landscaping shall be provided in accordance with a schedule acceptable to the Department. The developer may take up to 3 months after the date of approval of the certificate of development conformance to finish other designated improvements.

2. Maintenance of the public streets and drainage facilities within public streets or easements for the bonding period after the date of approval of the certificate of development conformance. Repairs must be made for any deficiencies identified within the bonding period or the bonds must be called to complete the same. The final street topping will not be applied until 90% of the lots have been issued a certificate of occupancy or until 36 months have passed from the date of final plat approval, whichever comes first. The Director has the ability to approve an alternate date for said topping based on the schedule of construction. The developer must post a 36-month performance surety in the amount of 110% of the cost of applying the final topping. If the final topping is not completed within 36 months of the date of final plat approval, the surety must be extended appropriately, as approved by the Director.

3. Indemnification of the City against all liability for damages arising as a result of errors or omissions in the design or construction of the development for a period of 10 years. If liability is subsequently assigned or transferred to a successor in title or other person, a copy of such legal instrument must be filed with the clerk to superior court.

B. Maintenance and Performance Surety

1. The maintenance surety and the performance surety, required from the owner/ developer or the contractor employed by the owner/developer, must be in the form of cash deposited with the City, or letter of escrow or letter of credit from a bank, or other financial institution in a form acceptable to the Director and City Attorney.

2. Performance surety and maintenance surety must, in all cases, be provided in an amount as provided in Sec. 103-5.3.D (Final Plat Approval) or Sec. 103-5.4.D (Certificate of Development Conformance Approval Process), as applicable. The maintenance bond period of application may not be less than 24 months from installation of the wearing course or final topping for a one-pass street and not less than 12 months from the installation of the binder for a two-pass street and which time will be extended equal to any extension of time for the performance bond granted by the Director but not more than 24 months. The performance bond period of application may not exceed 3 months unless an extension of an additional 3 months has been granted by the Director. All cost estimates must be as prepared by or acceptable to the Department.

3. A maintenance bond for the sanitary sewer facilities is required separately by the Water Pollution Control Division of Gwinnett County in accordance with their regulations. For the water system improvements, the contractor employed by the developer must maintain all water mains and appurtenances for 1 year from the date of approval of the certificate of development conformance by correcting all defects or deficiencies in materials or workmanship.

Sec. 103-6. Plans and Plats 103-6.1. General

A. All plans must be submitted for review as two sets of either blue line or black line prints. Only one copy of the stormwater management report is required. Re-submitted revisions must also be submitted as the original submittal. After final revisions are approved, three sets as described for the initial submittal must be submitted before release of the permit. If stamped, approved sets are desired in return, then more than three sets should be submitted. If approval signature is desired for future printing, the original sheet bearing the certificate of development plans approval should be submitted. In the case of a final plat, one mylar copy must also be returned for City records after recording and notation of the plat book and page on the plat.

B. When the Department provides written comments during plan review, a written response to those comments must be submitted with the re-submitted revisions. The written response must include the Department's comments and the applicant's responses to them.

C. All approved permit drawings (including a concept plan) must be submitted using email, flash drive, or other means approved by the Director. The desired format is AutoCAD .dwg, however, universal .dxf format will also be acceptable if major plat integrity is maintained. An Acrobat .pdf of all drawings is also required. No other formats may be considered.

D. When a traffic impact analysis is required by Sec. 103-5.2 (Traffic Impact Analysis), it must be included with the plans.

103-6.2. Concept Plan Specifications

A. General The following paragraphs outline the required elements of both the required and optional plans and plats mentioned throughout this section.

B. Scale The concept plan for a subdivision or site development must be clearly and legibly drawn at a scale of not less than 1 inch = 100 feet. Sheet size may not exceed 48 inches by 36 inches, provided, however, a scale of 1 inch = 200 feet may be used to avoid sheets larger than 48 inches by 36 inches. The Director may approve other scales and sheet sizes as deemed appropriate.

C. Freehand Drawing The concept plan may be prepared as a freehand drawing to approximate scale of the proposed improvements, right-of-way, lot lines, etc., shown on a boundary survey or other property outline map of the property.

D. Concept Plan Contents The concept plan must contain the following:

1. Approximate total acreage.

2. Proposed total number of lots and minimum lot size.

3. Size and location of adjoining existing streets or access drives and proposed right-of-way, roadways, and access drives.

4. For multi-family and nonresidential site developments (not subdivisions), the approximate location and arrangement of buildings, parking areas, and other improvements including stormwater detention areas, and all required buffers.

5. Topography with contour intervals no greater than 10 feet.

6. Proposed method of sewage disposal, expressed as a note.

7. Boundary lines of the overall property showing bearings and distances along all lines and the bearings and distance to an existing street intersection or other recognized permanent landmark. The source of this boundary information must be indicated.

8. All contiguous property under the ownership or control of the developer, except those lands of a dissimilar zoning category specifically approved to be excluded by the Department. Areas not planned at the time of the submittal must be shown as "future development."

9. Authorization statement on the concept plan to read as follows:

I hereby submit this Concept Plan as authorized agent/owner of all property shown thereon, and certify that all contiguous property under my ownership or control is included within the boundaries of this Concept Plan, as required by the Development Regulations.

Signature of Authorized Date Agent/Owner

10. Location sketch (vicinity map).

11. Lakes, ponds, and floodplains and the source of floodplain data including the panel number of flood insurance rate maps.

12. Required recreation areas and other public areas to be dedicated to the public or held in common ownership by a homeowner association or other similar entity.

13. Existing zoning of the property and adjoining properties.

14. Land lot and district.

15. Subdivider's name, local, and permanent (if different) address and phone number.

16. Name of company or person who prepared plan, local and permanent river tributary protection areas, if applicable to the property.

17. General development data (in tabular form) for individual multi-family or nonresidential site developments, such as number of residential units, number of gross square feet of nonresidential floor area by building, number of parking spaces, number of stories, etc.

18. General development data (in tabular form) for single-family developments, such as minimum lot size, floor area, and all relevant conditions of zoning.

19. Signature block to read as follows:

This Concept Plan has been reviewed and approved for general compliance with the Unified Development Ordinance of the City of Snellville, Georgia.

Planning and Development Director or Designee Date City of Snellville

20. The concept plan must be stamped and signed by a professional engineer, registered land surveyor, or landscape architect (as appropriate).

103-6.3. Subdivision Development Plans

A. Development Permit Application An application for a development permit for a subdivision shall consist of the preliminary plat, a certified boundary survey, associated slope or construction easements (if any), and such other development plans as may be required by these regulations.

B. Conformance Development plans must generally conform to the concept plan, if any, and must constitute only that portion of the approved concept plan which the subdivider proposes to construct at one time as a single unit, provided that such portion conforms to the requirements of these rules and regulations. If no concept plan was approved on the property, the development plans must include the entire property being developed within the same zoning category.

C. Scale Development plans must be clearly and legibly drawn at a scale of not less than 1 inch = 100 feet. Sheet size may not exceed 48 inches by 36 inches. Plan and profile must have a horizontal scale of no less than 1 inch = 100 feet and a vertical scale of no less than 1 inch = 10 feet.

D. Certified Boundary Survey

1. The preliminary plat must be based on a certified boundary survey delineating the entirety of the property contained within the preliminary plat, and tied to a point of reference (tie point) with the same degree of accuracy as the boundary survey itself.

The survey must have an initial field closure precision of 1 foot in no less than 10,000 feet and must meet all requirements of Georgia law regarding the recording of maps and plats.

2. Each preliminary plat must be drawn on, accompanied by, or referenced to a boundary survey which must at least meet the requirements clause 1 above.

E. Preliminary Plat Contents The preliminary plat must contain the following:

1. Proposed name of the subdivision.

2. Name, address, and telephone number of the owner of record, and of the subdivider (if not the owner).

3. Name, address, and telephone number of each professional firm associated with the Development Plans (engineer, surveyor, landscape architect, etc.).

4. Date of survey, north point, and graphic scale, source of vertical datum, date of plat drawing, and space for revision dates.

5. Proposed use of the site, such as single-family detached residences, duplexes, townhouses, office park, industrial subdivision, etc. For residential, indicate the total number of dwelling units within the plat.

6. Location (land district and land lot), acreage, and density (if applicable).

7. Location sketch locating the subdivision in relation to the surrounding area with regard to well-known landmarks such as major thoroughfares or railroads. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, but not less than 1 inch = 2,000 feet. U.S. Geological Survey maps may be used as a reference guide for the location sketch.

8. Name of former subdivision if any or all of the land in the preliminary plat has been previously subdivided, showing boundaries of the same.

9. Boundary lines of the perimeter of the tract indicated by a heavy line giving lengths in feet and hundredths of a foot, and bearings in degrees, minutes, and seconds.

Bearing and distance to designated tie point.

10. Directional flow arrows for street drainage and individual lot drainage when finished grading of lots is not shown.

11. Contour lines based on sea level datum, or other datum acceptable to the Department. These shall be drawn at intervals of not more than 2 feet. Contour lines shall be based on field surveys or photogrammetric methods from aerial photographs. The basis for the topographic contour shown must be specified and dated.

12. Natural features within the proposed subdivision, including drainage channels, bodies of water, and other known significant features such as extensive exposed rock.

On all watercourses leaving the tract, the direction of flow must be indicated. The 100-year floodplain must be outlined and the source of the depicted floodplain information must be indicated. For those lots containing floodplain, a floodplain lot chart must be provided showing the area (in square feet) of each lot lying inside and outside of the floodplain as though the land disturbance activity were completed.

13. Man-made and cultural features existing within and adjacent to the proposed subdivision including existing right-of-way measured from the centerline, pavements widths, and names of existing and platted streets; all easements, City, and County jurisdiction lines; existing structures on the site and their disposition, and other significant information. Location and dimensions of existing bridges; water, sewer, and other existing utility lines and structures; culverts and other existing features should be indicated.

14. Proposed layout including lot lines, lot numbers, and block letters; proposed street names, roadway, and right-of-way lines; and, sites reserved through covenants, easement, dedication, or otherwise for public uses. Lots must be numbered in numerical order and blocks lettered alphabetically. The minimum building setback line from all streets. Streets must be dimensioned to show right-of-way and roadway widths, central angles, intersection radii, and cul-de-sac roadway and right-of-way radii. Centerline curve data must be provided for all roadway curves [radius, length, amount of superelevation (if any), point of curvature (P.C.), point of tangency (P.T.), etc.] if not shown separately on construction drawings.

15. Identify the unit number, division, or stage of development, if any, as proposed by the subdivider.

16. Existing zoning of the property. Rezoning and variance case numbers, dates of approval and conditions (as applicable). Note minimum lot size and minimum yard setback requirements, and other applicable zoning requirements. Show and dimension any required buffers, landscape strips, no-access easements, etc. Note any approved waivers from these regulations.

17. All adjoining property owners, subdivision names, lot numbers and lot lines, block letters, and zoning.

18. Location of all known existing or previously existing landfills. A statement that no cut trees, timber, stumps, debris, rocks, stones, junk, rubbish, garbage, or other waste material of any kind must be buried in any right-of-way, under any proposed structure, and/or in any onsite/offsite pit.

19. Proposed recreation area, if any; area of the site; area and percent of the site within the 100-year floodplain; proposed disposition of the site (public ownership, homeowners association, etc.).

20. Such additional information as may be reasonably required to permit an adequate evaluation of the subdivision.

21. Plans must be stamped and signed by a professional engineer, registered land surveyor or landscape architect (as appropriate).

F. Certificate of Development Plans Approval and Owner's Acknowledgement Each preliminary plat must carry the following certificate printed or stamped thereon:

All requirements of the City of Snellville Unified Development Ordinance relative to the preparation and submission of a subdivision development permit application having been fulfilled, and said application and all supporting plans and data having been reviewed and approved by all affected City and Gwinnett County Departments as required under their respective and applicable regulations, approval is hereby granted, on this Preliminary Plat and all other development plans associated with this subdivision, subject to all further provisions of said Unified Development Ordinance and other City existing regulations.

Planning and Development Director or Designee Date City of Snellville

THIS CERTIFICATE EXPIRES TWELVE MONTHS FROM THE DATE OF APPROVAL

UNLESS A DEVELOPMENT PERMIT IS ISSUED.

NOTE: The boundaries of the lots shown on this Plat have not been surveyed. This Plat is not for recording.

Owner's Acknowledgement for Preliminary Plat

(STATE OF GEORGIA)

(COUNTY OF GWINNETT)

The owner of the land shown on this plat and whose name is subscribed thereto, and in person or through a duly authorized agent, acknowledges that this plat was made from an actual survey, and accurately depicts the land owned by the undersigned and will dedicate to the use of the public forever all streets, sewer collectors, lift stations, drains, easements, and other public facilities and appurtenances thereon shown, and will transfer ownership of all public use areas in fee simple by deed, for the purposes therein expressed.

SUBDIVIDER OWNER

DATE

G. Additional Plans The preliminary plat must be accompanied by other development plans showing the following information when same is not shown on, or evident from the preliminary plat.

The various plans may be combined where appropriate and clarity can be maintained.

1. Erosion control plan prepared in accordance with the requirements of Sec. 402-2 (Soil Erosion and Sedimentation Control). Erosion control measures may be shown on the grading plan, if desired.

2. Grading plan prepared in accordance with Sec. 402-1 (Grading) if grading is proposed beyond the street right-of-way.

3. Stormwater drainage construction data:

a. Location and size of all proposed drainage structures, including detention ponds, catch basins, grates, headwalls, pipes and any extensions thereof, energy dissipators, improved channels, and all proposed drainage easements to be located outside street right-of-way lines.

b. Profiles of all storm drainage pipes and slope of receiving channels. On storm drainage profiles a pipe chart must be shown which will include pipe numbers, pipe size, pipe material, pipe slope, pipe length, contributing drainage area, design flow, design storm frequency, runoff coefficient, and velocity. On all pipes, the 100-year storm line hydraulic grade line must be shown from the outlet to the farthest upstream catch basin, grated inlet or yard inlet. On all outfall structures from detention ponds, the hydraulic grade line must be shown for the 100-year storm.

c. Profiles of all open channels and ditches including Mannings' 25-year storm normal depth and velocity. On storm drainage profiles an open channel chart must be shown which will include open channel numbers, conveyance size, lining material, length, channel slope, contributing drainage area, design storm frequency, runoff coefficient, and velocity.

d. Hydrological study used in determining the size of structures, including a map of all contributing drainage basins and acreage.

4. If sanitary sewers are required by water pollution control, sanitary sewer plans, including the location and size of all proposed sewer lines, manholes, and any easements required therefore, together with sufficient dimensions to locate the same on the ground.

5. Construction data for new streets and street widenings:

a. Centerline profiles and typical roadway sections of all proposed streets, as well as plans and profiles for all proposed major thoroughfares. Typical roadway sections must be provided for street widenings.

b. Where sanitary or storm sewers are to be installed within a street, the grade;

size, location, and bedding class of pipe; location and invert elevation of manholes must be indicated on the road profile.

c. Profiles covering roadways that are extensions of existing roadways must include: elevations at 50-foot intervals for such distance as may be adequate to provide continuity consistent with the standards required by the Regulations for street improvements, but no less than 200 feet.

d. All elevations must be coordinated and tied into the U.S. Coast and Geodetic Survey or Department of Transportation benchmarks where feasible, or into reference monuments established by the Federal Emergency Management Agency.

e. Stub streets must be profiled at least 200 feet onto adjoining property (no tree cutting).

6. Buffer and landscape plan, if any such areas exist within the subdivision, prepared in accordance with the specifications under this subsection and other articles of this

UDO.

7. Tree preservation/replacement plan, as applicable.

8. Floodplain management plans. If any floodplain areas are located on the property, such data as is required by Sec. 403-4 (Floodplain Protection) must be submitted.

H. Encroachments Where construction is proposed on adjacent property, an encroachment agreement or easement must be submitted to the Department.

103-6.4. Final Plat Specifications

A. Scale The final plat must be clearly and legibly drawn in black ink on Mylar or other permanent reproducible material. The scale of the final plat must be not less than 1 inch = 100 feet.

Sheet size must not exceed 48 inches by 36 inches. Any sheet that is larger than 17 inches by 22 inches must be photographically reduced to no more than 17 inches by 22 inches in order to be recorded with the Clerk of the Superior Court.

B. Certified Boundary Survey The final plat must be based on a certified boundary survey delineating the entirety of the property contained within the final plat, and tied to a point of reference (tie point) with the same degree of accuracy as the boundary survey itself. The survey must have an initial field closure precision of 1 foot in no less than 10,000 feet and must meet all requirements of Georgia law regarding the recording of maps and plats.

C. Conformance The final plat must substantially conform to the preliminary plat and it must constitute only that portion of the approved preliminary plat which the subdivider proposes to record at any one time, provided that such portion conforms to the requirements of these regulations, and said portion is not inconsistent with the public health, safety, or welfare.

Any substantial deviation from the preliminary plat will require revision and reapproval of the preliminary plat.

D. Final Plat Contents The final plat must contain the following information:

1. Name of the subdivision, unit number, land district, and land lot number.

2. Name, address, and telephone number of the owner of record, and the subdivider (if not the owner).

3. Name, address, and telephone number of each professional firm associated with the portion of the subdivision within the final plat (engineer, surveyor, landscape architect, etc.).

4. Date of plat drawing, graphic scale, north point; notation as to the reference of bearings to magnetic, true north or grid north, and an indication whether bearings shown are calculated from angles turned.

5. Location sketch of tract showing major surrounding features.

6. Name of former subdivision, if any or all of the final plat has been previously recorded.

7. Case number, date of approval and all provisions for any applicable rezoning, special use permit, variance or waiver affecting the property.

8. Location and dimension of any buffer, landscape strip, special setback, no-access easement, etc., required by this UDO.

9. Boundary lines of the tract, to be indicated by a heavy line, giving distances to the nearest one-hundredth foot and bearings to the nearest second. Bearing and distance to designated tie point shall be shown. The plat must have an initial field closure precision of 1 foot in no less than 10,000 feet.

10. Municipal or county jurisdictional lines approximately tied to the lines of the subdivision by distance and angles when such lines traverse or adjoin the subdivision; land lot lines traversing or adjoining the subdivision must also be indicated.

11. Locations, widths, and names of all streets and alleys within and immediately adjoining the plat, the location and widths of all internal public crosswalks, and all other public rights-of-way.

12. Street centerlines showing angles of deflection and standard curve data including radii, length of arcs and tangents between curves, point of curvature (P.C.) and point of tangency (P.T.).

13. Lot lines with dimensions to the nearest one-tenth of a foot and bearings to the nearest second, and radii of rounded corners, as necessary to delimit each lot.

14. Building setback lines along streets with dimensions.

15. When lots are located on a curve or when side lot lines are at angles other than 90 degrees, the lot width may be required to be shown, if deemed necessary by the Department.

16. Lots numbered in numerical order and blocks lettered alphabetically.

17. Location and size of all drainage pipe, location and extent of detention ponds, the location and size of all public water mains and fire hydrants, and the location, dimensions, and purpose of any easements, including construction or slope easements if required.

18. Location of any areas to be reserved, donated, or dedicated to public use with notes stating their purpose and limitations. Location of any areas to be reserved by private deed covenant for the common use of all property owners, or dedicated to a homeowner's association.

19. A statement of private covenants if any, and they are brief enough to be put directly on the plat; otherwise, if covenants are separately recorded, a statement as follows:

This plat is subject to the covenants set forth in the separate document(s) attached hereto dated , which hereby become a part of this plat, and which were recorded and signed by the owner.

20. Accurate location, material, and description of monuments and markers (all monuments must be in place before approval of the final plat.) A minimum of two permanent markers is required for horizontal and vertical reference. Additional markers may be required on larger developments.

21. Certificates and statements specified in these regulations, below.

22. Extent of the 100-year floodplain and a floodplain chart showing the area within and outside the floodplain for each lot containing any portion of the 100-year floodplain.

The origin of the floodplain data must be indicated.

23. Street address numbers and block number designations for street names signs on abutting streets, where appropriate.

24. Individual lots must be designated HLP (house location plan), RDP (residential drainage plan) and/or RDS (residential drainage study) if required by the Department and to be approved before issuance of a building permit.

25. All other notes or notations as may be required by the Department.

26. Plat must be stamped and signed by a registered land surveyor.

E. Open Space Lands If any lands are shown on the final plat for dedication to a property owners association in order to meet minimum open space requirements of this UDO, a copy of the deed of transfer for such dedication and a copy of the instrument of incorporation of the property owner's association shall be submitted with the final plat application.

F. Certificates and Statements Each final plat must bear the following certificates or statements printed or stamped thereon as follows:

1. Final surveyor's certificate:

It is hereby certified that this plat is true and correct as to the property lines and all improvements shown thereon, and was prepared from an actual survey of the property made by me or under my supervision; that all monuments shown hereon actually exist, and their location, size, type and material are correctly shown. The field data upon which this plat is based has a closure precision of one foot in feet and an angular error of per angle point, and was adjusted using

rule. This plat has been calculated for closure and is found to be accurate within one foot in feet, and contains a total of

acres. The equipment used to obtain the linear and angular measurements herein was .

By:

REGISTERED GEORGIA LAND SURVEYOR

REG NO

DATE OF EXPIRATION

2. Owners acknowledgment and declaration:

(STATE OF GEORGIA)

(COUNTY OF GWINNETT)

The owner of the land shown on this plat and whose name is subscribed hereto, in person or through a duly authorized agent, acknowledges that this plat was made from an actual survey, and accurately depicts the land owned by the undersigned and dedicated by this Acknowledgement and Declaration to the use of the public forever all streets, sewer collectors, lift stations, drains, easements, and other public facilities and appurtenances thereon shown.

________________________ ___________

SIGNATURE OF SUBDIVIDER DATE SIGNED

————————————————————

PRINTED OR TYPED NAME OF SUBDIVIDER

—————————————————

SIGNATURE OF OWNER DATE SIGNED

—————————————————

PRINTED OR TYPED NAME OF OWNER

3. Final plat approval:

The Planning Commission Chairman and the Director of the City of Snellville, Georgia, certifies that this plat complies with the City of Snellville Unified Development Ordinance, and that it has been approved by all other operational City and county departments, as appropriate. This plat is approved subject to the provisions and requirements of the Development Performance and Maintenance Agreement executed for this project between the Owner and the City of Snellville.

DATED THIS DAY OF , 20 .

_________________________________ Planning Commission Chairman ________________________________________ Planning and Development Director or Designee

4. Health department certification (for subdivisions served by septic tanks):

The lots shown hereon have been reviewed by the Gwinnett County Health Department and with the exception of lots are approved for development.

Each lot is to be reviewed by the Gwinnett County Health Department and approved for septic tank installation prior to the issuance of a building permit.

DATED THIS DAY OF , 20 .

BY:__________________________

TITLE:______________________________

GWINNETT COUNTY HEALTH DEPARTMENT

Note: The above authorization only constitutes approval by the Gwinnett County Health Department. Authorization for development shall not be considered complete and final until the procedure in Sec. 103-5.3.D (Final Plat Approval) has been complied with.

5. Public notice - drainage:

Every single-family detached dwelling final plat must contain the following statement:

a. NOTE: The City of Snellville assumes no responsibility for overflow or erosion of natural or artificial drains beyond the extent of the street right-of-way, or for the extension of culverts beyond the point shown on the approved and recorded subdivision plat.

b. NOTE: Stream Buffer Easements are to remain in a natural and undisturbed condition.

c. NOTE: Structures are not allowed in drainage easements.

Every final plat that is not a single-family detached dwelling subdivision must contain the following statement:

a. NOTE: The City of Snellville assumes no responsibility for overflow or erosion of natural or artificial drains beyond the extent of the street right-of-way or for the extension of culverts beyond the point shown on the approved and recorded subdivision plat. The City of Snellville does not assume the responsibility for the maintenance of pipes in drainage easements beyond the City right-of-way.

b. NOTE: Stream Buffer Easements are to remain in a natural and undisturbed condition.

c. NOTE: Structures are not allowed in drainage easements.

6. House Location Plans (HLP):

On any final plat containing a lot for which a house location plan approval will first be required before issuance of a building permit, the following statement must be included:

HLP HOUSE LOCATION PLAN

A House Location Plan shall be required to be approved by the Department prior to issuance of a Building Permit on those lots labeled HLP. A House Location Plan is a scale drawing submitted by the builder at the time of permit. It is not required that this plan be prepared by a land surveyor or professional engineer. The purpose of this plan is to ensure that the house is properly located on the lot. Please refer to the City of Snellville Development Regulations or contact the Snellville Department of Planning and Development for further information.

7. Residential drainage plan (RDP) or study (RDS):

On any final plat containing a lot for which a residential drainage plan (RDP) or residential drainage study (RDS) will first be required before issuance of a building permit, the following statement must be included, as applicable:

RDP RESIDENTIAL DRAINAGE PLAN

RDS RESIDENTIAL DRAINAGE STUDY

A Residential Drainage Plan or Residential Drainage Study must be approved by the Department of Planning and Development prior to issuance of a Building Permit on those lots labeled "RDP" or "RDS," respectively. Please refer to the City of Snellville Development Regulations and contact the Snellville Department of Planning and Development for further information.

103-6.5. House Location Plan

A. Seale House location plans (HLPs) must be drawn to scale and may be shown on a certified boundary survey of the lot or any other drawing showing the information required below.

The Department may accept a house location plan drawn to the same scale as shown on the final plat where sufficient detail can be shown to support an adequate review and approval. The house location plan may be combined with a residential drainage plan (RDP) if an RDP is required for the lot.

B. Preparation It is not the intent of the Department that the house location plan must be prepared by a registered surveyor or engineer, rather, it may be done by the individual proposing the improvements on the lot. It is the intent, however, to receive a drawing with sufficient readability and accuracy to ensure that the proposed improvements are constructed on the lot in conformance with the requirements of this UDO or other regulations, as applicable.

C. Contents House location plans must show the following as applicable:

1. Boundary lines of the lot, giving distances to the nearest one-tenth of a foot and bearings to the nearest minute.

2. Location and names of all abutting streets or other rights-of-way.

3. Minimum required front, side and rear building setback lines with dimensions, and notation of the existing zoning on the property.

4. The approximate outline of all buildings, driveways, parking areas, swimming pools, recreational courts, patios, accessory structures, and other improvements existing or proposed on the property, and dimensions of buildings and distances between all structures and the nearest property lines.

5. All easements, public water, sewer or storm drainage facilities traversing or located on the property, septic tank, and septic tank drain field.

6. Subdivision name, lot designation, land lot, and district.

7. North arrow and scale.

8. Limit of the 100-year floodplain and any applicable buffers or special building setback lines.

9. All other applicable requirements of this UDO or conditions of zoning approval.

10. Name, address, and telephone number of the owner and the person who prepared the

HLP.

103-6.6. Residential Drainage Plan or Study

A. Scale Residential drainage plans must be drawn to scale on a certified boundary survey of the lot prepared by a registered land surveyor, having an initial field error of closure not exceeding 1 foot in 5,000 feet. The residential drainage plan may be combined with a an HLP if an HLP is required for the lot. The requirements contained herein also apply to lots which formerly required SPED (site plan - engineering division) approval before the issuance of a building permit.

B. Contents Residential drainage plans must show the following, as applicable:

1. Boundary lines of the lot, giving distances to the nearest one-tenth of a foot and bearings to the nearest minute.

2. Location and names of all abutting streets or other rights-of-way.

3. The outline of all buildings, driveways, parking areas, swimming pools, recreational courts, patios, accessory structures, and other improvements existing or proposed on the property, and dimensions of buildings and distances between all structures and the nearest property lines as required to locate the major improvements on the lot.

4. All easements, public water or sewer facilities traversing or located on the property, and septic tank drain field.

5. Subdivision name, lot designation, land lot, and district.

6. North arrow and scale.

7. Contour lines based on sea level datum. These must be drawn at intervals of not more than 2 feet and shall be based on a field survey. The proposed grading of the lot must be shown along with the finished floor elevation of the lowest habitable floor of the house.

8. Stormwater features, including swales, pipes, stormwater detention and other structures, all drainage (D.E.) easements, and directions of flow.

9. Floodplain features, including the limits of the flood hazard area, 100-year flood high water elevation, the origin of the floodplain data, and any proposed modifications to the floodplain limits.

10. Sedimentation and erosion control measures to be taken or placed on the lot during construction.

11. Names, address, and telephone number of the owner and person who prepared the

RDP.

12. Seal, registration number, and date of expiration of the professional engineer or landscape architect who prepared the drainage improvements or modifications shown on the RDP.

13. Add the following notation: RESIDENTIAL DRAINAGE PLAN TO BE FIELD VERIFIED: A certificate of occupancy may not be issued for the structure until a written certification has been received from the developer's or builder's design professional stating that the provisions or improvements required by the residential drainage plan or as a result of the residential drainage study have been field verified.

C. Residential Drainage Study

1. A residential drainage study (RDS) must be conducted by the developer's or builder's design professional before issuance of a certificate of occupancy on those lots so noted on the final plat. The requirements for an RDS contained herein also apply to lots that formerly required SSED (site study - engineering division) approval before the issuance of a building permit.

2. The grading and construction of the lot must be field verified by the developer's or builder's design professional as being in conformance with grading plans and stormwater management studies approved for the subdivision before issuance of a certificate of occupancy.

D. Plans to be Field Verified A certificate of occupancy may not be issued for the structure until a written certification has been received from the developer's or builder's design professional stating that the provisions or improvements required by the residential drainage plan or as a result of the residential drainage study have been field verified.

E. Notation of Stream or Floodplain on Development Plans or Plat If an RDP or RDS is required because a stream or floodplain is on or adjacent to the lot, the notation on the development plans and plat should be "RDP-E" or "RDS-E," as appropriate.

(UDO 22-01, § 1, 2-28-2022)

103-6.7. Site Development Plans

A. Application Criteria An application for a development permit for a multi-family or nonresidential site must consist of the site plan, a certified boundary survey or final plat reference, associated slope or construction easements (if any), and such other development plans as may be required by this UDO.

B. Conformance The development plans must generally conform to the concept plan, if any, and may constitute only that portion of the approved concept plan which the developer proposed to construct at one time as a single unit, provided that such portion conforms to the requirements of these rules and regulations and all setbacks, maximum density, and other zoning district restrictions. If no concept plan was approved on the property, the development plans must include the entire property being developed having the same zoning district.

C. Scale The development plans must be clearly and legibly drawn at an engineering scale convenient to illustrate the details of the project. Sheet size shall not exceed 48 inches by 36 inches. Plan and profile sheets, if any, must have a horizontal scale of no less than 1 inch = 100 feet and a vertical scale of no less than 1 inch = 10 feet.

D. Project Boundary Data

1. The site plan must be based on the boundaries of a lot as recorded on a final subdivision plat or on a certified boundary survey delineating the entirety of the property contained within the project, and tied to a point of reference (tie point) with the same degree of accuracy as the boundary survey itself. The survey must have an initial field closure precision of 1 foot in no less than 10,000 feet and must meet all requirements of Georgia law regarding the recording of maps and plats.

2. Each site plan must be drawn on, accompanied by, or referenced to a boundary survey which shall at least meet the requirements of clause 1 above.

E. Site Plan Contents The site plan must contain the following (on one or more sheets):

1. Proposed name of development. If the project is located within a subdivision, the name of the subdivision, lot, and block number must also be shown.

2. Name, address, and telephone number of the owner of record, and of the developer (if not the owner).

3. Name, address, and telephone number of each professional firm associated with the development plans (engineer, landscape architect, surveyor, etc.).

4. Date of survey, north point, and graphic scale, source of datum, date of plan drawing, and space for revision dates.

5. Proposed use of the site, including gross square footage for each different use type or building.

6. Location (land district and land lot), acreage or area in square feet, and density (if applicable).

7. Location sketch locating the development in relation to the surrounding area with regard to well-known landmarks such as major thoroughfares or railroads. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, but not less than 1 inch = to 2,000 feet. U.S. Geological Survey maps may be used as a reference guide for the location sketch.

8. Size and location of all buildings, building setback lines, minimum yard lines, and distances between buildings and from buildings to property lines; location of outdoor storage areas; parking and loading areas, driveways, curb cuts and designated fire lanes. Each building must be identified with a number or letter.

9. Boundary lines of the perimeter of the tract indicated by a heavy line giving lengths to the nearest one-hundredth of a foot and bearings to the nearest second. Bearing and distance to designated tie point.

10. Directional flow arrows for street drainage.

11. Contour lines based on sea level datum. These must be drawn at intervals of not more than 2 feet and shall include the entire site and all abutting public streets.

Contour lines must be based on field surveys or photogrammetric methods from aerial photographs. The basis for the topographic contour shown must be specified and dated.

12. Natural features within the proposed development, including drainage channels, bodies of water, and other known significant features such as extensive exposed rock.

On all watercourses leaving the tract, the direction of flow must be indicated. The 100-year floodplain shall be outlined and the source of the depicted floodplain information must be indicated. The acreage or area in square feet within the floodplain must be indicated.

13. Man-made and cultural features existing within and adjacent to the proposed development including existing right-of-way measured from the centerline, pavement widths, and names of jurisdiction lines; existing structures on the site and their disposition, and other significant information. Location and dimensions of existing bridges; water, sewer, and other existing utility lines and structures; culverts and other existing features should be indicated.

14. Proposed street names, roadway and right-of-way lines and widths and sites reserved through covenants, easement, dedication or otherwise for public uses.

15. Identify the unit number, division or stage of development, if any, as proposed by the developer.

16. Show all adjoining property owners, subdivision names, lot numbers, lot lines and block letters, and zoning.

17. Show the location and number of parking spaces according to the size of the building on the plans. Show factors used in determining the number of spaces required by Sec. 207-1.5 (Accessible Parking). Accessible parking spaces must be shown as required by the Georgia law.

18. Zoning district rezoning case number, date of approval and conditions (as applicable).

Variances obtained on the property should be shown with the case number, date of approval and conditions (if applicable). Note any approved waivers from these regulations.

19. If buffers or other landscaping or screening treatments are required, show the location, size, and type (natural or planted) on the plans conforming to the tree preservation/replacement plan or buffer and landscape plan, as applicable.

20. Location, height, and size of all freestanding signs to be erected on the site, and an indication of whether lighted or unlighted.

21. Location of all known existing or previously existing landfills. A statement that no cut trees, timber, stumps, debris, rocks, stones, junk, rubbish, garbage, or other waste material of any kind must be buried in any right-of-way, under any proposed structure, and/or in any on-site/off-site pit.

22. Such additional information as may be reasonably required to permit an adequate evaluation of the project.

23. Plans must be stamped and signed by a professional engineer, registered land surveyor or landscape architect (as appropriate).

F. Certificate of Development Plans approval and Owner's Acknowledgement Each site plan must carry the following certificate printed or stamped thereon:

All requirements of the City of Snellville Regulations relative to the preparation and submission of a development permit application having been fulfilled, and said application and all supporting plans and data having been reviewed and approved by all affected city and county departments as required under their respective and applicable regulations, approval is hereby granted of this site plan and all other development plans associated with this project subject to all further provisions of said development and other city regulations.

Planning and Development Director or Designee Date City of Snellville THIS CERTIFICATE EXPIRES TWELVE MONTHS FROM THE DATE OF APPROVAL UNLESS A DEVELOPMENT PERMIT IS ISSUED Owner's Acknowledgement and Declaration:

(STATE OF GEORGIA)

(COUNTY OF GWINNETT)

The owner of the land shown on this plat and whose name is subscribed thereto, and in person or through a duly authorized agent, acknowledges that this plat was made from an actual survey, and accurately depicts the land owned by the undersigned and dedicated by this declaration to the use of the public forever all streets, sewer collectors, lift stations, drains, easements, and other public facilities and appurtenances thereon shown, and transfers ownership of all public use areas in fee simple by deed, for the purposes therein expressed.

SUBDIVIDER OWNER

DATE DATE

G. Additional Plans The site plan must be accompanied by other development plans showing the following information when same is not shown on, or evident from the site plan. The various plans may be combined where appropriate and clarity can be maintained.

1. Erosion control plan prepared in accordance with the requirements of Sec. 402-2 (Soil Erosion and Sedimentation Control). Erosion control measures may be shown on the grading plan, if desired.

2. Grading plan, prepared in accordance with the requirements Sec. 402-1 (Grading).

3. Stormwater drainage construction data:

a. Location and size of all proposed drainage improvements, and all proposed drainage easements to be located outside street right-of-way lines.

b. Profiles of all storm drainage pipes and slope of receiving channels. The hydraulic grade line for the 100-year storm is to be shown on all pipes and detention basin outfalls. On storm drainage profiles a pipe chart must be shown, including pipe numbers, pipe size, pipe material, pipe slope, pipe length, contributing drainage area, design flow, design storm frequency, runoff coefficient and velocity. Profiles of all open channels and ditches must be shown including the design flow normal depth and velocity. On storm drainage profiles an open channel chart must be shown which will include open channel numbers, conveyance size, lining material, length, channel slope, contributing drainage area, design flow, design storm frequency, runoff coefficient and velocity for the required design flow.

c. Acreage of drainage areas and hydrological study used in determining the size of structures, including a map of all contributing drainage basins and acreages.

4. Sewage disposal plans, as follows:

a. Sanitary sewer plans, including the profiles and other information as may be required by Gwinnett County Water Pollution Control.

b. For projects proposed to be served by on-site sewage disposal systems, location and extent of the septic tank, drain field and attendant structures, and other information required by the Gwinnett County Health Department.

5. Street widening and construction data:

a. Centerline profiles and typical roadway sections of all proposed streets, as well as plans and profiles for all proposed major thoroughfares. Profiles (and plans, where required) must be drawn on the standard plan and profile sheet with plan section showing street layout, pavement and right-of-way width, curvature, and required drainage facilities. Typical roadway sections shall be provided for street widenings.

b. Where sanitary or storm sewers are to be installed within a street, the grade, size, location and bedding class of pipe; location and invert elevation of manholes shall be indicated on the road profile.

c. Profiles covering roadways that are extensions of existing roadways shall include; elevations at 50-foot intervals for such distance as may be adequate to provide continuity consistent with the standards required by these regulations for street improvements, but no less than 200 feet.

d. All elevations shall be coordinated and sited into U.S. Coast and Geodetic Survey or Department of Transportation benchmarks where feasible or into reference monuments established by the Federal Emergency Management Agency.

e. Buffer and landscape plan, if any such areas exist within the site, prepared in accordance with the specifications here, and otherwise required by this UDO.

f. Tree preservation/replacement plan, as applicable.

g. Floodplain management plans; if any floodplain areas are located on the property. Such data as is required by the floodplain management ordinance must be submitted.

h. Private water system plans, if any, indicating proposed water main size and location, with fire hydrants, on the site. The distance and direction to all other fire hydrants within 500 feet of the site or buildings along existing streets or other access drives must also be indicated.

i. Street striping plan, showing striping in accordance with the Manual on Uniform Traffic Control devices, for any street newly constructed to four or more lanes, and all newly constructed or widened major thoroughfares.

H. Encroachments Where construction is proposed on adjacent property, an encroachment agreement or easement must be submitted to the Department.

I. Public Notice, Drainage Every site plan must contain the following statement:

1. NOTE: The City of Snellville assumes no responsibility for overflow or erosion of natural or artificial drains beyond the extent of the street right-of-way or for the extensions of culverts beyond the point shown on the approved and recorded plan.

The City of Snellville does not assume the responsibility for the maintenance of pipes in drainage easements beyond the City right-of-way.

2. NOTE: Stream Buffer Easements are to remain in a natural and undisturbed condition.

3. NOTE: Structures are not allowed in drainage easements.

103-6.8. Tree Ordinance Plans

A. Conformance A tree preservation/replacement plan is required only when indicated in Sec. 207-4 (Tree Ordinance).

B. Additional Plans Tree preservation/replacement plans must be prepared in accordance with the specifications contained in Sec. 207-4 (Tree Ordinance). At the developer's option, the plan may be combined with other plans such as a general landscaping plan for the project.

103-6.9. Buffer and Landscape Plans

A. Required A buffer and landscape plan are required when indicted in this UDO.

B. Conformance The buffer and landscape plans must be prepared in accordance with this UDO. At the developer's option, the plan may be combined with other plans such as a general landscaping plan.

Sec. 103-7. Board of Appeals 103-7.1. Proceedings

A. The Board of Appeals must adopt rules necessary to the conduct of its affairs and in keeping with the provisions of this UDO. The Board of Appeals must conduct its regular meetings on the second Tuesday of each month and at such other times as the chairperson or board determines, with the chairperson or board having the right to re-schedule or cancel any meeting. The chairperson, or in their absence, the vice-chairperson, may administer oaths and compel the attendance of witnesses. All meetings must be open to the public.

B. The Board of Appeals must keep minutes of its proceedings, showing the vote of each member upon each question, or, if absent or failing to vote, indicating such fact, and must keep records to its examinations and other official actions, all of which will be a public record and be immediately filed in the office of the board.

103-7.2. Powers and Duties The Board of Appeals has the following powers and duties:

A. Administrative Review To hear and decide appeals where it is alleged there is an error in any order, requirement, decision, or determination made by a staff member of the Department in the enforcement of this UDO. See Sec. 103-7.3 (Administrative Decision Appeals).

B. Variances and Waivers Unless contained in a rezoning amendment in front of the Mayor and Council, to authorize, upon appeal in specific cases, such variance from the terms of this UDO as will not be contrary to the public interest where, owing to special conditions, a literal enforcement of the provisions of the UDO would result in unnecessary hardship. A variance may not be granted by the Board of Appeals unless and until:

1. A written application for a variance or waiver is submitted demonstrating:

a. That special conditions and circumstances exist which are peculiar to the land, structure, or building involved and which are not applicable to other land, structures, or buildings in the same zoning district;

b. That literal interpretation of the provisions of this UDO would deprive the applicant of rights commonly enjoyed by other properties in the same zoning district under the terms of this UDO;

c. That the special conditions and circumstances do not result from the actions of the applicant;

d. That granting the variance or waiver requested will not confer on the applicant any special privilege that is denied by this UDO to other lands, structures, or buildings in the same zoning district.

No nonconforming use of neighboring lands, structures, or buildings in the same zoning district, and no permitted or nonconforming use of lands, will be considered grounds for the issuance of a variance.

2. Application Requirements. Any application for an administrative review, variance, and/or waiver must be submitted by 4:00 p.m., 50 calendar days before the date on which it is to be considered by the Board of Appeals. The application submittal must contain the following:

a. Written narrative detailing the administrative review (appeal) or requested variance or waiver and hardship levied as a result of the UDO requirement.

b. Site plan, drawn to scale, showing: property lines with dimensions; any improvements, structures and buildings; location of requested variance;

building setbacks; easements, public water, sewer, or storm drainage facilities traversing or located on the property; limits of the 100-year floodplain; and any applicable buffers.

c. Responses to items (a)—(d) in Sec. 103-7.2.B.1.

d. Nine stapled or bound copies of the application and any supporting documents and exhibits,

e. One unbound application bearing original signatures.

f. A digital copy in .pdf format of all materials must be submitted using email, flash drive, or other means approved by the Director.

g. Verification by Gwinnett County and the City of Snellville that all county and city property taxes owed have been paid and account is current.

h. Warranty deed, security deed, or quit claim deed for all lots/parcels subject to the application.

i. Map indicating the subject property and the adjacent properties, identified by tax parcel number.

j. Payment of application fee and public notification fees (public notice sign and notice to adjoining property owners) as determined by the Department fee schedule.

k. An initiating party must also file any other information or supporting materials that are required by the City Council, and/or the Department.

3. Public Notifications. The Department must provide notice of the date, time and place of the public hearing as follows:

a. Legal ad published in the newspaper which carries the legal advertisements of the City, by advertising the application and date, time, place and purpose of the public hearing not fewer than 30 days, nor more than 45 days before the date of the Board of Appeals hearing.

b. Notification to the owners of adjoining properties of the property for which the appeal, variance, or waiver is sought and/or their agent by first class USPS mail to the mailing address provided by the Gwinnett County Tax Commissioner's office. The notification must be mailed not fewer than 30 days, nor more than 45 days before the Board of Appeals hearing. The notification must include a description of the application and the date, time, and place of the public hearing.

c. Posting of a Public Notice Sign on the property, one sign per road frontage, per parcel, posted at least 30 days before the public hearing. The sign must include a description of the application and the date, time, and place of the public hearing.

4. Once advertised the public hearing must be held. Any party may appear in person, or by agent or attorney.

5. The Board of Appeals must further make findings that the requirements of Sec.

103-7.2.B have been met by the applicant for a variance or waiver.

6. The Board of Appeals must further make a finding that the reasons set forth in the application justify the granting of the variance or waiver is the minimum variance that will make possible the reasonable use of the land, building, or structure.

7. The Board of Appeals must further make a finding that the granting of the variance or waiver will be in harmony with the general purpose and intent of this UDO, and will not be injurious to the neighborhood, or otherwise detrimental to the public welfare.

In granting any variance, the Board of Appeals may prescribe appropriate conditions and safeguards in conformity with this UDO. Violation of such conditions and safeguards, when made a part of the terms under which the variance is granted, will be deemed a violation of this UDO that is punishable under its provision.

(UDO 23-02, § 1, 6-12-2023)

103-7.3. Administrative Decision Appeals

A. Appeals to the Board of Appeals concerning interpretation or administration of this UDO may be taken by any person aggrieved or by any officer or bureau of the governing body of the City affected by any decision of a staff member of the Department of Planning and Development. Appeals must be filed with the Department within 15 days of said decision on the form/application provided by the City, including payment of application fee and public notification fees as determined by the Department fee schedule. The Director must forthwith transmit to the board all papers constituting the record upon which the action appealed from was taken.

B. An appeal stays all proceedings in furtherance of the action appealed from unless the Director certifies to the Board of Appeals that, by reason of facts stated in the certificate, a stay would, in their opinion, cause imminent peril, to life or property. In such a case, proceedings may not be stayed otherwise than by the Zoning Board of Appeals or by a restraining order granted by a court of record on application, and notice to the Director for good cause shown.

C. The person requesting the appeal must first submit to Department a written statement clearly defining the nature of the disagreement, the specific reference to the sections of the regulations at issue, and the applicant's own opinion.

D. If the Department fails to respond within ten business days from the date of transmittal of the appeal, the Department must automatically forward a copy of the appeal to the Board of Appeals for final action in their normal course of business.

E. The Board of Appeals must hear and act upon within 50 days of receipt of the appeal application and give public notice thereof in accordance with Sec. 103-7.2.B.3 (Public Notifications). At the hearing, any party may appear in person or by agent or attorney.

F. In exercising the above-mentioned powers, the Board of Appeals may, so long as such action is in conformity with the terms of the this UDO, reverse or affirm, wholly or partly, or may modify the order, requirement, decision, or determination as ought to be made, and to that end will have the powers of the Department staff member from whom the appeal is taken.

(UDO 23-02, § 1, 6-12-2023)

103-7.4. Reapplication If an application for a variance or waiver is denied by the Board of Appeals, a reapplication for such variance or waiver may not be made earlier than 12 months from the date of the original application.

(UDO 23-02, § 1, 6-12-2023)

103-7.5. Appeals Any person aggrieved by a decision or order of the Board of Appeals may appeal by certiorari to the Superior Court of Gwinnett County. Such appeal must be filed within 30 days from the date of the decision of the Board of Appeals. Any petition for writ of certiorari may be served through the City Manager on behalf of the lower judiciary body being appealed. The Mayor may be served with the petition on behalf of the City. Upon failure to file the appeal within 30 days from the date of decision, the decision of the Board of Appeals will be final.

(UDO 23-02, § 1, 6-12-2023)

Sec. 103-8. Administrative Variances 103-8.1. General

A. The Director may modify the following standards during development review:

1. Front yard or street side yard. Variance not to exceed five feet.

2. Interior side yard. Variance not to exceed two feet.

3. Rear yard. Variance not to exceed four feet.

4. Height of building. Variance not to exceed five feet, provided the maximum number of stories allowed may not be increased.

5. Side or rear yard. A variance for a zero-foot setback may be granted when part of a commercial or mixed-use development and planned as a unit with a similar architectural composition and not a miscellaneous assemblage of stores, provided, however, that before any issuance of the variance, the applicant must obtain approval from the affected side and/or rear yard property owner(s).

6. Sidewalk setback. Variance for a zero-foot setback.

7. The one exception would cover nonconforming structures. Structures that preceded this UDO and do not conform to it may be granted an administrative variance not identified in clauses 1 through 6 above when ownership is changing and the mortgage company requires conformity to the UDO.

B. The Director may also modify other standards as specifically provided in this UDO in Sec. 201-1.6.D (Driveways); 201-3.1 (General Architectural Standards); 201-4 (Enhanced Architectural Standards); 401-3.4.H (Interparcel Access); 403-1.4 (Stream Buffer and Setback Requirements); and 403-1.5.E (Lots of Record in Big Haynes Creek Watershed) so long as the procedures, notice requirements, and criteria for approval are followed as stated herein.

C. Any other modification beyond those contained in paragraphs A or B above must be considered by the Board of Appeals as a variance.

(UDO 23-02, § 1, 6-12-2023)

103-8.2. Criteria for Approval The applicant must demonstrate, and the Director must find, that all of the following criteria are present when approving a request for an administrative variance:

A. There are clear and compelling reasons that are not purely financial demonstrating that the required standard cannot be met;

B. The variance is the minimum amount necessary to meet the objectives identified above;

C. The requested adjustment will not contravene the public interests or negatively impact adjoining properties; and

D. And any additional criteria provided in this UDO and sections identified in Sec.

103-8.1.B.

(UDO 23-02, § 1, 6-12-2023)

103-8.3. Procedure

A. Any application for administrative variance, and/or waiver must be submitted by 4:00 p.m., 50 calendar days before the date on which it is to be considered by the Director. The application submittal must contain the following:

a. Written narrative detailing the administrative variance request, hardship levied as a result of the UDO requirement and demonstration that approval criteria is present.

b. Site plan, drawn to scale, showing: property lines with dimensions; any improvements, structures and buildings; location of requested variance; building setbacks;

easements, public water, sewer, or storm drainage facilities traversing or located on the property; limits of the 100-year floodplain; and any applicable buffers.

c. Two stapled or bound copies of the application and any supporting documents and exhibits.

d. One unbound application bearing original signatures.

e. A digital copy in .pdf format of all materials must be submitted using email, flash drive, or other means approved by the Director.

f. Verification by Gwinnett County and the City of Snellville that all county and city property taxes owed have been paid and account is current.

g. Warranty deed, security deed, or quit claim deed for all lots/parcels subject to the application.

h. Map indicating the subject property(ies) and the adjacent properties, identified by tax parcel number.

i. Payment of application fee and public notification fees (public notice sign and notice to adjoining property owners) as determined by the Department fee schedule.

j. An initiating party must also file any other information or supporting materials that are required by the City Council, and/or the Department.

B. Public Notifications.

The Department must provide notice of the date, time and place of the public hearing as follows:

a. Legal ad published in the newspaper which carries the legal advertisements of the City, by advertising the application and date, time, place and purpose of the public hearing not fewer than 30 days, nor more than 45 days before the date of the public hearing.

b. Notification to the owners of adjoining properties of the property for which the variance, or waiver is sought and/or their agent by first class USPS mail to the mailing address provided by the Gwinnett County Tax Commissioner's office. The notification must be mailed not fewer than 30 days, nor more than 45 days before the public hearing. The notification must include a description of the application and the date, time, and place of the public hearing.

c. Posting of a Public Notice Sign on the property, one sign per road frontage, per parcel, posted at least 30 days before the public hearing. The sign must include a description of the application and the date, time, and place of the public hearing.

C. Once advertised the public hearing must be held. Any party may appear in person, or by agent of attorney.

D. Any person aggrieved by a decision of the Director may appeal to the Board of Appeals in accordance with Sec. 103-7.3.

(UDO 23-02, § 1, 6-12-2023)

Sec. 103-9. Amendments 103-9.1. Applicability

A. Zoning Amendments Amendments to the provisions of this UDO that constitute a zoning ordinance under Sec.

101-1.6.B (Zoning Compliance Law) or that involve the Future Land Use Map of the Comprehensive Plan must conform to this section.

B. Non-Zoning Amendments Amendments to the provisions of this UDO that are not included in paragraph A above may be amended using the City's general procedures for ordinance amendments.

103-9.2. General The regulations, restrictions, and boundaries contained in this UDO may from time to time be amended, supplemented, changed, or repealed, provided, however, that no such action may be taken until after a public hearing in relation thereto, at which parties in interest and citizens must have an opportunity to be heard. This UDO, including the Official Zoning Map and the Future Land Use Map, may be amended from time to time by the City Council, but no amendment is effective unless it has been proposed by or has first been submitted to the Planning Commission for review and recommendation.

103-9.3. Initiation of Amendments

A. Prior to the submittal of an amendment application, the applicant must meet with the planning department staff for a Pre-Submittal Review Meeting.

B. Amendment applications may be in the form of proposals to amend the text, the Future Land Use Map, or the Official Zoning Map. An application to amend the text of this UDO may be initiated by the Department, submitted to the Planning Commission by the City Council, or submitted by any person with an interest in the city. An application to amend the Future Land Use Plan or the Official Zoning Map may be initiated by the Planning Commission or be submitted to the Planning Commission by the City Council. Unless initiated by the City Council or the Planning Commission, all applications to amend the Future Land Use Plan, Official Zoning Map, or conditions of zoning must be submitted by the owner of the affected property or the authorized agent of the owner. Such authorization must be notarized and attached to the application.

(UDO 22-03, § 1, 1-9-2023)

103-9.4. Application Requirements Each application to amend the text of this UDO, the Future Land Use Map, or the Official Zoning Map must be filed with the Department. Applications must be submitted in compliance with the following:

A. UDO Text Amendments UDO text amendment applications must include the following:

1. Payment of the appropriate application fee.

2. Name and address of the applicant.

3. Current provisions of text to be affected by the amendment.

4. The proposed wording of text change.

5. Letter of intent explaining what is proposed and the reason for the request.

6. Applicant's certification.

7. Conflict of interest certification and disclosure of campaign contributions.

8. Ten stapled or bound copies of the text amendment application and all supporting documents, in addition to one unbound application bearing original signatures. In addition, a digital copy in .pdf format of all submitted materials must be submitted using email, flash drive, or other means approved by the Director.

B. Future Land Use Map Amendments Future Land Use Map amendment applications must include the following:

1. Payment of the appropriate application and public notification fees as determined by the Department fee schedule.

2. A current legal description of the site proposed for amendment. If the site proposed for amendment includes multiple lots, provide a separate legal description for each individual lot, together with a composite legal description for the site.

3. Ten printed boundary surveys of the site that is to have a revised land use under the applicant's proposal, at least one of which should be an 11 x 17-inch (or smaller) reduction. In addition, a digital copy in .pdf format must be submitted using email, flash drive, or other means approved by the Director.

The survey must have been prepared by a Georgia registered land survey no more than 24 months before the date of submittal.

4. All permitted land uses for the identified area under the existing Future Land Use Map.

5. All changes to existing land use designations that are proposed by the application.

6. All land uses immediately adjacent to the subject property under the existing Future Land Use Map.

7. A letter listing all the reasons for the amendment application.

8. Applicant's and/or owner's certification.

9. Names and addresses of the owner(s) of the land or their agent(s), if any, authorized to apply for an amendment.

10. A written, documented analysis of the impact of the proposed land use change that specifically addresses each of the following matters:

a. Whether the proposed land use change will permit uses that are suitable in view of the uses and development of adjacent and nearby property.

b. Whether the proposed land use change will adversely affect the existing uses or usability of adjacent or nearby property.

c. Whether the proposed land use change will result in uses which will or could cause excessive or burdensome uses of existing streets, transportation facilities, utilities, or schools.

11. Whether there are other existing or changing conditions affecting the use and development of the affected land areas which support either approval or disapproval of the proposed land use change.

12. Ten stapled or bound copies of the Future Land Use Map amendment application and all supporting documents, in addition to one unbound application bearing original signatures. In addition, a digital copy in .pdf format must be submitted using email, flash drive, or other means approved by the Director.

13. Verification by Gwinnett County and the City of Snellville that all county and city property taxes owed have been paid (for all parcels/lots subject to this application).

14. A warranty deed, security deed, or quit claim deed (for all lots subject to the application).

15. A map indicating the site and the adjacent properties, identified by tax parcel number.

16. An initiating party must also file any other information or supporting materials that are required by the City Council, Planning Commission and/or the Department.

C. Zoning Map Amendments Zoning map amendment applications must include the following:

1. Payment of the appropriate application and public notification fees as determined by the Department fee schedule.

2. A current legal description of the site to be rezoned. If the site proposed for amendment includes multiple lots, provide a separate legal description for each individual lot, together with a composite legal description for all lots.

3. Ten printed boundary surveys of the site to be rezoned, at least one of which should be an 11 x 17-inch (or smaller) reduction. In addition, a digital copy in .pdf format must be submitted using email, flash drive, or other means approved by the Director. The survey must have been prepared by a Georgia registered land survey no more than 24 months before the date of submittal.

4. Ten copies of the proposed site plan, and one 11 x 17-inch (or smaller) reduction of the plan, drawn to scale, showing: a north arrow; land lot, district, and parcel number: the dimensions with bearing and distance; acreage; location of the tract(s); the present zoning district of all adjacent lots; the proposed location of structures, driveways, parking, and loading areas; and the location and extent of required buffer areas. The site plan must be prepared by an architect, engineer, landscape architect or land surveyor whose State registration is current and valid. The site plan must be sealed, signed and dated by one of the four above-mentioned professionals no more than 12 months before the date of submittal. In addition, a digital copy in .pdf format must be submitted using email, flash drive, or other means approved by the Director.

5. Letter of intent explaining what is proposed.

6. Any requests for variances or waivers from the requirements of the UDO demonstrating:

a. That special conditions and circumstances exist which are peculiar to the land, structure, or building involved and which are not applicable to other land, structures, or buildings in the same requested zoning district.

b. That literal interpretation of the provisions of this UDO would deprive the applicant of rights commonly enjoyed by other properties in the same requested zoning district under the terms of this UDO.

c. That the special conditions and circumstances do not result from the actions of the applicant.

d. That granting the variance or waiver requested will not confer on the applicant any special privilege that is denied by this UDO to other lands, structures, or buildings in the same requested zoning district.

7. Ten stapled or bound copies of the zoning map amendment application and all supporting documents, in addition to one unbound application bearing original signatures. In addition, a digital copy of all materials in .pdf format must be submitted using email, flash drive, or other means approved by the Director.

8. Applicant's and/or owner's certification.

9. Conflict of interest certification and disclosure of campaign contributions.

10. The present and proposed zoning district for the site.

11. The names and addresses of the owners of the land and their agents, if any.

12. Each zoning map amendment application, whether submitted by the City or by another party, must include with it a written, documented analysis of the impact of the proposed rezoning with respect to each of the following matters:

a. Whether the zoning proposal will permit a use that is suitable in view of the use and development of adjacent and nearby properties.

b. Whether the zoning proposal would adversely affect the existing use or usability of adjacent or nearby property.

c. Whether the property to be affected by the zoning proposal has a reasonable economic use as currently zoned.

d. Whether the zoning proposal will result in a use that will or could cause excessive or burdensome use of existing, streets, transportation facilities, utilities, or schools.

e. Whether the zoning proposal is in conformity with the policy and intent of the Future Land Use Map.

f. Whether there are other existing or changing conditions affecting the use and development of the property, which give supporting grounds for either approval or disapproval of the zoning proposal.

13. Architectural building renderings indicating each building elevation, colors, construction materials, etc. of which the facades and roofs will consist.

14. Verification by Gwinnett County and the City of Snellville that all county and city property taxes owed have been paid (for all parcels/lots subject to this application).

15. A warranty deed, security deed, or quit claim deed (for all lots subject to the application).

16. A map indicating the site and the adjacent properties, identified by tax parcel number.

17. A traffic impact analysis when required by Sec. 103-5.2.A.

18. An initiating party must also file any other information or supporting materials that are required by the City Council, Planning Commission, and/or the Department.

D. Timing Applications must be submitted by noon at least 42 days before the date on which it is to be considered by the Planning Commission. Any application that does not include all of the components required in paragraphs A, B, and C above will be considered incomplete; submission date will be considered the date upon which the application is accepted as complete by the Department. Fees for an application to amend this UDO, the Official Zoning Map, the Future Land Use Map, or any combination thereof, must be paid by the applicant upon submission, except that a fee is not charged for applications initiated by the City Council or Planning Commission.

E. Withdrawal

1. Once an application for a Future Land Use Map amendment and/or Official Zoning Map amendment has been received by the Department, the applicant may withdraw such application without prejudice until such time that the legal ad has been ordered advertising the City Council public hearing date (no less than 28 days before the City Council public hearing). No application may be withdrawn less than 28 days before the City Council public hearing unless the request for withdrawal is granted by the City Council at the public hearing.

Otherwise, all applications must be considered by the City Council.

2. There will be no reimbursement for withdrawn applications. An applicant may request reimbursement in writing to the City Council. Said request will be considered during a regular meeting of the City Council.

F. Denial If an application for a Future Land Use Map amendment and/or an Official Zoning Map amendment is denied by the City Council, no application affecting any portion of the same property may be submitted less than 12 months from the date of denial.

G. Zoning Action by Mayor and Council Related to Multifamily Uses Pursuant to O.C.G.A. § 36-66-4, if the proposed amendment is initiated by the City and relates to an amendment of the UDO to revise one or more zoning classifications or definitions relating to single-family residential uses of property so as to authorize multifamily uses of property pursuant to such classification or definitions, or to grant blanket permission, under certain or all circumstances, for property owners to deviate from the existing zoning requirements of a single-family residential zoning, the Mayor and City Council shall comply with the following requirements:

1. The zoning decision shall be adopted at two regular meetings of the City Council, during a period of not less than 21 days apart; and

2. Prior to the first meeting provided for in subparagraph (1) of this paragraph, at least two public hearings shall be held on the proposed action. Such public hearings shall be held at least three months and not more than nine months prior to the date of final action on the zoning decision. Furthermore, at least one of the public hearings must be held between the hours of 5:00 p.m. and 8:00 p.m.

The hearings required by this paragraph shall be in addition to any hearing required under Sec. 103-9.7 of the Ordinance. The local government shall give notice of such hearing by:

a. Posting notice on each affected premises in the manner prescribed by Sec.

103-9.8 of this Code section; provided, however, that when more than 500 parcels are affected, in which case posting notice is required every 500 feet in the affected area; and

b. Publishing in a newspaper of general circulation within the territorial boundaries of the local government a notice of each hearing at least 15 days and not more than 45 days prior to the date of the hearing.

c. Both the posted notice and the published notice shall include a prominent statement that the proposed zoning decision relates to or will authorize multifamily uses or give blanket permission to the property owner to deviate from the zoning requirements of a single-family residential zoning of property in classification previously relating to single-family residential uses. The published notice shall be at least nine column inches in size and shall not be located in the classified advertising section of the newspaper.

The notice shall state that a copy of the proposed amendment is on file in the Office of the City Clerk of the City of Snellville and in the Office of the Clerk of the Superior Court of Gwinnett County for the purpose of examination and inspection by the public. The City of Snellville shall furnish anyone, upon written request, a copy of the proposed amendment, at no cost.

(UDO 23-02, § 1, 6-12-2023)

103-9.5. Department Study

A. The Department, upon receiving an application to amend this UDO, Future Land Use Map, or the Official Zoning Map, may do the following:

1. Consult with other departments of the City or County to fully evaluate the impact of any land use category or zoning district change upon public facilities and services including, but not limited to, schools, drainage, traffic, and related facilities.

2. Conduct a site review of the property and surrounding area.

3. Submit a written record of its investigation and recommendations to the Planning Commission and City Council. This report will be a matter of public record.

B. The Department's report may recommend amendments to the applicant's request which would reduce the land area for which the application is made, change the land use category or zoning district requested, and/or recommend conditions of rezoning which may be deemed advisable so that the purpose of this UDO will be served and the public health, safety, morality, and general welfare secured.

103-9.6. Planning Commission Action The Planning Commission must hold a public hearing on each application in accordance with a schedule adopted by the City Council. Staff recommendations on each application must be submitted to the Planning Commission before the public hearing. In addition, the Planning Commission must, with respect to each application, investigate and make a recommendation as to each of the matters set forth in Sec.103-9.4.B.10 and/or Sec.

103-9.4.C.12 for approval, denial, deferral, withdrawal without prejudice, or no recommendation. Proponents and opponents of any amendment will be allotted at least 10 minutes, per side, for the presentation of data, evidence, and opinion during said public change. A written report of the Planning Commission's investigation and recommendation, along with the investigation and recommendation of the Department, must be submitted to the City Council and will be of public record.

(UDO 23-02, § 1, 6-12-2023)

103-9.7. City Council Public Hearing Before taking action on a proposed amendment and after receipt of the Department of Planning and Development and Planning Commission recommendations and reports thereon where required, the City Council will hold a public hearing on the proposal. At the public hearing, the City Council will review the reports prepared by the Department of Planning and Development and the Planning Commission. So that the purpose of this UDO will be served and the public health, safety, morality, and general welfare secured, the City Council may approve or deny the application, reduce the land area for which the application is made, change the district or land use category requested, and/or add or delete conditions of the application that are more or less restrictive than the current regulations. Proponents and opponents of any amendment will be allotted a minimum of 10 minutes, per side, for the presentation of data, evidence, and opinion during said public hearing. An action by the City Council to defer the application will include a statement of the date and time of the next meeting at which the application will be considered, which statement will constitute public notice of the hearing on the application and no further notice, such as that required by Sec.

103-9.8 (Public Notification), is required.

103-9.8. Public Notification The following are required for applications to amend the Future Land Use Map, Official Zoning Map, conditions of rezoning, or for a special use permit:

A. Legal Notice Due notice of the Planning Commission meeting and the City Council public hearing must be published in a newspaper of general circulation within the City and the newspaper which carries the legal advertisements of the City, by advertising the application and date, time, place and purpose of the public hearing, not fewer than 15 days, nor more than 45 days before the date of the Planning Commission meeting and the City Council public hearing. If the application is to amend the Future Land Use Map, the notice must include location, current land use category and proposed land use category. However, if the application is for an amendment to the Official Zoning Map, then the notice must also include the location of the property, the present zoning district of the property, and the proposed zoning classification of the property.

B. Signs Posted The Department must post a sign containing information that indicates that the application(s) has been filed and the date, time, and place of both the Planning Commission meeting and City Council public hearing at which the application(s) will be considered. The sign(s) must be posted at least 15 days, nor more than 45 days before the Planning Commission public hearing and must be posted in a conspicuous place on the property adjacent to and visible from each public street abutting the property for which an application has been submitted. Sign(s) must remain posted d through the time of final City Council decision. The Department is responsible for the removal of all public notice sign(s).

C. Letters to Property Owners The Department must notify the owners of adjoining properties of the property for which the amendment application or special use permit is sought and/or their agent by first class USPS mail to the mailing address provided by the Gwinnett County Tax Commissioner's office. The notification must be mailed at least 15 days, nor more than 45 days before the Planning Commission meeting. A second notification mailing must be mailed at least 15 days, nor more than forty-five (45) days before the City Council public hearing. The notification must include a description of the application and the date, time, and place of the public hearing.

(UDO 23-02, § 1, 6-12-2023)

103-9.9. Rezoning Condition Alteration

A. An application to alter conditions of rezoning must be submitted and processed in accordance with all provisions applicable to map amendments through the Department, the Planning Commission for a public hearing, and to the City Council for a public hearing.

B. The City Council may add or delete conditions to rezoning applications during the public hearing that are more or less restrictive than this UDO.

103-9.10. Order of Amendments The permitted order in which amendments may be made to the text of this UDO, the Future Land Use Map, and the Official Zoning Map, respectively, is as follows:

A. The text of this UDO may be amended without prior or subsequent amendment to the Future Land Use Map or the Official Zoning Map.

B. The Official Zoning Map may be amended without an amendment to the Future Land Use Map if the proposed amendment would permit a use that is permitted by the Future Land Use Map.

C. If a proposed amendment to the Official Zoning Map would permit a use that is not authorized within the land use category of the subject property as shown on the Future Land Use Map, then the applicant must obtain an appropriate amendment to the Future Land Use Map before applying for the rezoning. The applicant may apply for an appropriate amendment to the Future Land Use Map and at the same time apply for zoning map amendment.

D. The Future Land Use Map may be amended regardless of the zoning districts that apply to the subject property.

E. Where an application to amend the Future Land Use Map and an application to amend the Official Zoning Map each affect the same property and are scheduled to be heard at the same hearing, the application to amend the Future Land Use Map must be heard first and action authorized by this section taken before the application to amend the Official Zoning Map may be heard and action taken with respect thereto.

103-9.11. Failure to Implement Plans If a site development plan or preliminary plat has not been submitted to the Department within 12 months of the date of approval of the rezoning application, then the Planning Commission may review each case to determine if there are circumstances clearly justifying such delays. If justifying circumstances do not exist, the Planning Commission may recommend to City Council that the zoning map be amended to change the land to its prior zoning classification.

103-9.12. Evaluation of Amendments

A. In considering the applications for an amendment to this UDO or Official Zoning Map, or in making other zoning decisions, the following factors may be considered:

1. The impact upon the appearance of the city;

2. The impact upon thoroughfare congestion and traffic safety;

3. The impact upon population density and the potential for overcrowding and urban sprawl;

4. The impact upon the provision of water, sewerage, transportation, and other urban services;

5. The protection of property against blight and depreciation;

6. Consistency with the adopted Future Land Use Map and/or the Comprehensive Plan;

7. The impact upon adjacent property owners if the amendment is approved;

8. The impact upon the applicant if the amendment is denied; and/or

9. Any other factor affecting the health, safety, morals, convenience, order, prosperity, or general welfare of the present and future inhabitants of the City of Snellville.

103-9.13. Appeals Any person aggrieved by a decision or order of the City Council may appeal by writ of certiorari to the Superior Court of Gwinnett County. Any such appeal must be filed within 30 days from the date of the decision of the City Council. Upon failure to file the appeal within 30 days, the decision of the City Council will be final.

(UDO 23-02, § 1, 6-12-2023)

Sec. 103-10. Special Use Permits 103-10.1. General Special use permits are intended as a means for the City Council to authorize certain uses that are not permitted by-right in a zoning district. Special use permits may be subject to meeting specific standards by Chapter 200 Article 6 (Use Provisions), but still require individual review by City Council because of the increased potential for incompatibility with its immediate neighborhood.

103-10.2. Application Requirements

A. Each application for a special use permit must be filed with the Department and must include the following:

1. Payment of the appropriate application fee.

2. A current legal description of the site. If the site includes multiple lots, provide a separate legal description for each individual lot, together with a composite legal description for all lots.

3. Ten printed boundary surveys of the site, at least one of which should be an 11 x 17-inch (or smaller) reduction. In addition, a digital copy in .pdf and .dwg. format must be submitted using email, flash drive, or other means approved by the Director.

The survey must have been prepared by a registered land survey no more than 12 months before the date of submittal.

4. Ten copies of the proposed site plan, and one 11 x 17-inch (or smaller) reduction of the plan, drawn to scale, showing: a north arrow; land lot, district, and parcel number:

the dimensions with bearing and distance; acreage; location of the tract(s); the present zoning district of all adjacent lots; the proposed location of structures, driveways, parking, and loading areas; and the location and extent of required buffer areas. The site plan must be prepared by an architect, engineer, landscape architect or land surveyor whose State registration is current and valid. The site plan must be stamped and sealed by one of the four above-mentioned professionals no more than 6 months before the date of submittal. In addition, a digital copy in .pdf and .dwg format must be submitted using email, flash drive, or other means approved by the Director.

5. Letter of intent explaining what is proposed.

6. Ten stapled or bound copies of the special use permit application and all supporting documents, in addition to one unbound application bearing original signatures. In addition, a digital copy in .pdf format of all plan submittals must be submitted using the means requested by the Director.

7. Architectural building renderings indicating building elevation, colors, construction materials, etc. of which the facades and roofs will consist.

8. Additional information deemed necessary by the Director in order to evaluate a proposed use and its relationship to the surrounding area must be submitted.

9. A traffic impact analysis when required by Sec. 103-5.2.

B. Special use permits may not be used for securing early zoning for conceptual proposals which may not be undertaken for more than 6 months from the date the application is submitted. A special use permit application will be considered only if it is made by the owner of the property or their authorized agent.

103-10.3. Review Criteria In reviewing applications for a special use permit, the following standards and factors must be considered by the Planning Commission and the City Council in place of the matters identified in Sec. 103-9.4.B.10 and/or Sec. 103-9.4.C.11:

A. Applicable use standards of Chapter 200 Article 6 (Use Provisions); and

B. Whether the proposed use would be consistent with the needs of the neighborhood or community as a whole and would not be in conflict with policies and objectives of the Comprehensive Plan; and

C. Whether the proposed use has adverse impacts on the surrounding area, especially with regard to, but not limited to, traffic, storm drainage, land values and compatibility of land use activities; and

D. Whether the proposed use is desired for development and a more intensive zoning district which contains that use as a use by right would not be appropriate for the property; or

E. Whether a proposed use is desired for development and no zoning district contains that use as a use by right; or

F. Whether a unique use not addressed in any zoning district is desired for development and is not likely to be duplicated within the City; or

G. Whether the density of development may be affected by the height of a building.

103-10.4. Review Process

A. Applications for special use permits must be submitted to the Department no later than noon, 42 days before the meeting date of the Planning Commission.

B. The Department may prepare a study in accordance with Sec. 103-9.5 (Department Study), which must also include how the proposed use conforms to the review criteria in this subsection. The study may recommend conditions of approval which may be deemed advisable so that the purpose of this UDO will be served and the public health, safety, morality, and general welfare secured.

C. The Planning Commission must hear the application for special use permit following the same procedures required for a rezoning in Sec. 103-9.6 (Planning Commission Action), except as follows:

1. The Planning Commission may not consider the matters set forth in Sec. 103- 9.4.B.10 and/or Sec. 103-9.4.C.11 as part of a special use permit.

2. In lieu of the matters identified in clause C.1 above, the Planning Commission must consider the review criteria in this subsection.

3. The Planning Commission may propose conditions that will ensure that the use standards identified in that clause are met and the public health, safety, and general welfare are secured.

D. At least 15 days before the date of the public hearing to be held by the City Council, the special use request must be duly advertised and heard, following the same procedure required for a rezoning in Sec. 103-9.7 (City Council Public Hearing) and Sec. 103-9.8 (Public Notification). The City Council may approve conditions that will ensure that the review criteria in this subsection are met and the public health, safety, and general welfare are secured.

E. If the special use permit application is denied by the City Council, no special use application affecting any portion of the same property may be submitted less than 6 months from the date of denial.

103-10.5. Appeals Any person aggrieved by a decision or order of the City Council may appeal by certiorari to the Superior Court of Gwinnett County. Any such appeal must be filed within 30 days from the date of the decision of the City Council. Upon failure to file the appeal within 30 days, the decision of the City Council will be final.

103-10.6. Following Approval

A. If an application is approved and a special use permit is granted, all conditions which may have been attached to the approval are binding on the property. All subsequent development and use of the property must be in accordance with the approved plan and conditions. All final site plans must be approved by the Director before the issuance of any permits. Once established, the special use must be in continuous operation. Upon discovery that the operation of the special use has or had ceased for a period of 180 days or more and the owner of the property has not requested voluntary termination of the special use permit, the Director must forward a report to City Council through the Planning Commission which may recommend that action be taken to remove the special use permit from the property.

B. Changes to a special use or development of a site for the special use will be treated as an amendment to the special use permit and will be subject to the same application and review process as a new application.

C. The special use for which a special use permit is granted must commence operations or construction within 12 months of the date of approval by the City Council. If, at the end of this 12-month period, the Director determines that active efforts are not proceeding toward operation or construction, a report may be forwarded to the City Council through the Planning Commission which may recommend that action be taken to remove the special use permit from the property.

D. The Director or an officer of the City of Snellville Police Department has the right to periodically examine the operation of the specific use to determine compliance with the requirements of any conditions. If the Director determines that the requirements and conditions are being violated, a written notice will be issued to the owner of the property outlining the nature of the violations and giving the owner of the property a maximum of 30 days to come into compliance. This 30-day maximum will be amendable in the reasonable discretion of the Director. If after 30 days the violations continue to exist, the Director must forward a report to the City Council through the Planning Commission, which may recommend that action be taken to remove the special use permit from the property.

E. Upon approval by the City Council, a special use permit must be identified on the Official Zoning Maps.

F. Upon approval by the City Council of a special use permit, the owner of the property must be issued a notice from the Director, which states the specific use permitted, the requirements of this subsection and any conditions attached to the approval.

G. The Department may not issue a certificate of occupancy for the specific use unless all requirements and conditions of the special use permit have been fulfilled by the owner of the property.

Sec. 103-11. Nonconformities 103-11.1. Purpose

A. Within the districts established by this UDO or amendments thereto that may later be adopted there exist lots, structures and uses of land and structures which were lawful before this UDO was passed or amended, but which would be prohibited under the terms of this UDO or any future amendment.

B. It is the intent of this UDO to permit these nonconformities to continue until they are removed, but not to encourage their survival. It is further the intent of this UDO that nonconforming uses may not be enlarged upon, expanded nor extended, nor be used as a basis for additional structures or uses prohibited elsewhere in the same zoning district.

C. To avoid undue hardship, nothing in this UDO may be deemed to require a change in the plans, construction or designated use of any building on which actual construction was lawfully begun before the effective date of adoption or amendment of this UDO and upon which actual building construction has been diligently carried on. Actual construction is hereby defined to include the placing of construction materials in a permanent position and fastened in a permanent manner, and demolition, elimination and removal of an existing structure in connection with such construction, provided that actual construction work shall be diligently carried on until the completion of the building involved.

103-11.2. Nonconforming Lots of Record In any district in which single-family detached dwellings are permitted, notwithstanding limitations imposed by other provisions of this UDO, a single-family detached dwelling and customary accessory buildings may be erected on any single lot of record, as officially recognized by the City, at the effective date of this UDO. This provision will apply even though such lot fails to meet the requirements for area or width, or both, that are generally applicable in the zoning district, if yard dimensions and other requirements not involving area or width, or both, of the lot must conform to the provisions of this UDO.

103-11.3. Nonconforming Uses

A. The lawful use of any building or structure or land existing at the time of the enactment or amendment of this UDO may be continued, even though such use does not conform with the provisions of this UDO, except that the nonconforming use may not be:

1. Extended to occupy a greater area of land.

2. Extended to occupy a greater area of a building or structure unless such additional area of the building or structure existed at the time of the passage or amendment of this UDO and was clearly designed to house the same use as the nonconforming use occupying the other portion of the building or structure.

3. No such nonconforming use may be moved in whole or in part to any portion of the lot other than that occupied by such use at the effective date of adoption of this UDO.

4. Reestablished after discontinuance for 6 months as based on available City records.

5. Changed to another nonconforming use.

103-11.4. Nonconforming Buildings and Structures Where a lawful building or structure (excluding signs) exists at the effective date of adoption or amendment of this UDO that could not be built under the terms of these regulations and standards by reason of restrictions on area, lot coverage, height, yards, its location on the lot, or other requirements concerning the structure, such structure may be continued so long as it remains otherwise lawful, subject to the following provisions:

A. No such nonconforming structure may be enlarged or altered in a way which increases its nonconformity, but any structure or portion thereof may be altered to maintain or improve its condition or to decrease its nonconformity.

B. If such a nonconforming structure or nonconforming portion of a structure is destroyed by any means to an extent of more than 50% of its replacement cost at the time of destruction, it may not be reconstructed except in conformity with the provisions of this UDO.

C. If such a structure is moved for any reason for any distance whatever, it must thereafter conform to the regulations for the district in which it is located after it is moved.

D. Structures that are nonconforming due to front, side or rear yard requirements may be expanded or extended only in conformance with this UDO.

E. Variances to non-conforming buildings and structures may be granted by the Board of Appeals.

103-11.5. Nonconforming signs

A. The lawful use of a permanent sign existing at the time of the adoption of the UDO may be continued in nonconformance, except that the nonconforming sign may not be enlarged, altered, modified, improved or rebuilt. However:

1. A nonconforming sign may be repaired to the extent necessary to maintain it in a safe condition and neat and orderly appearance.

2. A change in the advertising message on the sign shall not constitute an alteration or modification of the sign.

3. Routine maintenance and changing of copy are permitted as long as such maintenance or changing of copy does not result in or change the shape, size or design.

B. No structural repair or change in shape, size or design, is permitted except to make a nonconforming sign comply with all requirements of this UDO or to render the sign structurally sound.

C. A nonconforming sign may not be removed by an act of the owner and later replaced by another nonconforming sign.

D. No sign variances are allowed.

103-11.6. Uses Under Prior Special Use Permits and Rezoning with Conditions Any use for which a conditional use permit, special use permit, or a rezoning with conditions has been issued under a prior zoning code or ordinance will not be deemed a nonconforming use but may be deemed a conforming use in the district under the conditions required for the issuance and validity of the special use permit or rezoning.

103-11.7. Repairs and Maintenance

A. Work may be done on any nonconforming structure, or portion of a structure, containing a nonconforming use, on ordinary repairs, or on repair or replacement of load-bearing or non-bearing walls, fixtures, wiring, or plumbing, to an extent not exceeding 50% of the current replacement cost of the nonconforming structure or on conforming portion of the structure as the case may be, provided that the square footage or cubic content existing when it became nonconforming may not be increased.

B. If a nonconforming structure or portion of a structure containing a nonconforming use becomes physically unsafe or unlawful due to lack of repairs and maintenance and is declared by any duly authorized official to be unsafe or unlawful by reason of physical condition, it shall not thereafter be restored, repaired or rebuilt except in conformity with the regulations of the district in which it is located.

C. Nothing in this UDO may be deemed to prevent the strengthening or restoring to a safe condition of any building or part thereof declared to be unsafe by any official charged with protecting the public safety, upon order of such official.

CHAPTER 200. ZONING AND LAND USE

ARTICLE 1. RULES FOR ALL ZONING DISTRICTS

Sec. 201-1. Measurements and Exceptions 201-1.1. Sites

A. Defined A site is any lot or group of contiguous lots owned or controlled by the same person or entity, assembled for the purpose of a single development.

B. Site Area Site area is the cumulative area of all contiguous lots that the site is composed of. It excludes existing public rights-of-way but does include planned public or private rights-of-way that will be created in the development.

C. Site Frontage All sites must have at least 25 feet of frontage upon a public street or private street built to public standards.

201-1.2. Density

A. Dwelling Units Allowed

1. The maximum number of dwelling units allowed on a site is calculated by either:

a. Multiplying the site area by the maximum number of units per acre allowed in the zoning district, when applicable; or

b. Conforming to minimum lot sizes.

Minimum lot sizes in some districts may appear to allow additional units to be developed on a site beyond what is allowed by sentence a above; however, the zoning district's allowed density serves as the cap on the maximum number of units on a site.

2. The maximum number of dwelling units allowed on a site or portion of a site located within a floodplain must be further reduced when required by the FH district standards of Sec. 205-3.3.A.

B. Accessory Dwelling Units Accessory dwelling units are not counted in density calculations.

201-1.3. Lots

A. Defined A parcel of land either vacant or occupied intended as a unit for the purpose, whether immediate or for the future, of transfer of ownership, or possession, or for development.

Lot types include the following:

1. Corner Lot. Any lot with frontage on two streets at their intersection.

2. Interior Lot. A lot with frontage on only one street.

3. Flag lot. A lot that does not meet the minimum frontage and/or width requirements and where access to the public street is by a narrow right-ofway or driveway.

4. Through Lot. A lot other than a corner lot with frontage on two or more streets.

B. Lot Area The area included within the rear, side, and front lot lines. Lot area does not include existing or proposed rights-of-way, whether dedicated or not dedicated to public use.

C. Lot Coverage The percentage of total lot area, excluding any streetscape easements provided in accordance with Sec. 401-4.2.A.3, that includes:

1. The horizontal area of the building footprint measured within the outside of the exterior walls of the ground floor of all principal buildings and any roofed accessory buildings on the lot;

and

2. Any impervious parking areas, driveways, walkways, steps, terraces, uncovered patios and decks, swimming pools, and any similar features. The Director may establish rules for determining the extent to which partially pervious materials are exempt from lot coverage.

D. Lot Depth The distance between midpoints of straight lines connecting the foremost points of the side lot lines in front and the rearmost points of the side lot lines in the rear.

E. Lot Frontage

1. Defined. The portion of a lot adjacent to a street or specified courtyard for a cottage court.

2. Minimum Frontage.

a. Every lot must have at least 25 feet of frontage upon either a public street, a private street built to public standards, or a specified courtyard for a cottage court, except when less frontage is allowed by zoning district regulations or when more frontage is required along cul-de-sacs.

b. Every lot along a cul-de-sac must have at least 35 feet of frontage, measured along a straight line along the chord of the arc at the right-of-way line.

F. Lot Width

1. Defined. The distance between side lot lines measured at the minimum required front yard setback, except as provided for cul-de-sacs below.

2. Lot Width along Cul-de-Sacs. For a lot with the majority of its frontage on a cul-de-sac, the lot width may be measured at the minimum required front setback line or at a line parallel to said setback line at no more than twice the minimum front setback distance from the street.

G. Through Lots

1. Through lots are required for residential subdivisions along major thoroughfares where internal access can be provided, except as otherwise allowed by clause G.2 below.

2. Interior and corner lots are allowed along major thoroughfares in the TCO, TC, MU, and NR districts when these lots have internal access from an alley or shared driveway."

3. When a through lot is required by clause G.1 above, a no-access landscape strip must also be provided when required by Sec. 207-3.2.C.

H. Lot Size

1. New lots must conform to the size requirements of the applicable zoning district, except as otherwise allowed by paragraph I below.

2. No lot, even though it may consist of one or more adjacent lots in the same ownership at the time of passage of this UDO, may be reduced in size so that its width, size of yards, lot area per dwelling unit, or any other requirements of this UDO are not maintained. This does not apply when a portion of a lot is acquired for public use.

3. New lot size is determined by Sec. 401-4.2.A.3.c on existing public streets where there is insufficient right-of-way for the required streetscape improvements and an easement is provided in accordance with Sec. 401-4.2.A.2.

I. Lot Size Exceptions

1. No lot served by a septic tank may have a lesser area than that approved by the Environmental Health Section for safe drinking water and septic tank operation.

2. Lots used exclusively for common areas, open spaces, private alleys, or stormwater facilities are exempt from lot size requirements.

3. Lots used exclusively for subdivision entrance sign or subdivision entrance landscape features are exempt from lot size requirements when:

a. The lot is located at an entrance to the subdivision as an "island" in the right-of-way of a local or minor collector street; and

b. The subdivision provides a mandatory homeowner association (or nonresidential equivalent) that is responsible for maintaining the lot in perpetuity;

and

c. Right-of-way with a minimum width of 6 feet from the back of the curb is provided adjacent to the perimeter of the lot;

d. Landscape plantings are not allowed in the right-of-way, except as otherwise provided in this UDO within the streetscape planter by Sec. 401-4.2 (Streetscape Required).

J. Substandard Lots of Record.

Any lot of record existing at the time of the adoption or amendment of the UDO, that has an area or width that is less than is required by the UDO, may be used, subject to the following:

1. Individual Lot Not Meeting Minimum Lot Size Requirements.

a. Except as set forth in sentences J.1.b and c below, in any zoning district where single-family detached dwellings are permitted, any lot of record existing at the time of adoption or amendment of the UDO which has an area, width or depth less than that required by the UDO may be used as a building site for one single-family detached dwelling.

b. In the case of such a lot, when it is not possible to provide the required side setbacks and at the same time build a minimum width single-family detached dwelling, the Board of Appeals is authorized to grant a variance reducing the side setback requirements for such lot the minimum amount necessary for a reasonable dwelling, but in no case may each of the side setbacks be less than 5 feet in width or the new structure located less than 10 feet from an principal structure on an adjacent lot.

c. In the case of such lot, when the lot was previously approved in a final plat for use as a common area, open space, private alley, stormwater facilities, or similar amenity or infrastructure use, it may not be used as a building site for one single-family detached dwelling.

2. Adjoining Lots. When two or more adjoining lots of record with continuous frontage are in one ownership at any time after the adoption or amendment of the UDO and such lots, individually, have an area or width that is less than is required by the UDO, then such contiguous lots are considered as a single lot or several lots of the minimum width and area required by the zoning district in which they are located and must be combined.

201-1.4. Building Setbacks

A. Type of Setbacks

1. There are four types of setbacks - front, side (street), side (interior), and rear.

2. Building setbacks apply to both principal and accessory buildings or structures, except where it explicitly states otherwise in this UDO.

B. Measurement of Building Setbacks Building setbacks are measures as follows, except when paragraph C below applies:

1. A front setback is measured at a right angle (perpendicular) to the front lot line, except as otherwise required by clause B.7.

2. A side (street) setback is measured at a right angle (perpendicular) to the side street lot line, except as otherwise required by clause B.7.

3. A rear setback is measured at a right angle (perpendicular) to the rear lot line.

4. Lot lines which are not front, side (street), or rear lot lines are considered side (interior) lot lines for the purpose of measuring setbacks. Side (interior) setbacks are measured at a right angle (perpendicular) to the side interior lot line.

5. Setbacks must be drawn using an extension of a line perpendicular to the lot line until they intersect with another setback line.

6. Where street right-of-way dedication occurs, setbacks are measured from the final lot line.

7. Where a streetscape easement is provided in accordance with Sec. 401-4.2.A.3, setbacks must be measured from the easement.

C. Irregularly Shaped Lots The Director will determine how setbacks apply to irregularly shaped lots.

D. Front Setback Exceptions The following applies in all districts except the TCO, TC, MU, and NR districts.

1. Front setback requirements do not apply on lots where the average depth of the front yards of existing buildings on adjoining lots located wholly or partially within 100 feet on each side of such lot within the same block and zoning district and fronting on the same side of the street is either more or less than the minimum required front setback.

2. If the average depth of the front yards is more than the required front setback, then the lot's required front setback is the average depth of the front yards of the above-referenced buildings but not more than 150% of the otherwise required front setback.

3. If the average depth of the front yards is less than the required minimum front setback, then lots required front setback is the average of the front yards of the aforementioned buildings.

201-1.5. Building Setback Encroachments All principal buildings and structures must be located at or behind the required zoning district setbacks, except as listed below. Unless specifically stated in this UDO, no building or structure may extend into a required easement or public right-of-way.

A. Non-Profit Private Clubhouse, Non-Profit Private Recreation Zoning district setbacks do not apply to non-profit private clubhouse and non-profit private recreation uses. Both must conform to the setbacks provided in Article 7 for their use.

B. Principal Building Features

1. Porches, stoops may not encroach, except as allowed in Sec. 201-2.14 (Building Elements) in zoning districts where building types apply.

2. Balconies and awnings/canopies may encroach up to 6 feet, except where a greater distance is allowed in Sec. 201-2.14 (Building Elements) in zoning districts where building types apply.

3. Building eaves, roof overhangs, gutters, downspouts, and light shelves may encroach up to 4 feet, provided that such extension is at least 2 feet from the vertical plane of any lot line.

4. Bay windows and oriels less than 10 feet wide may encroach up to 4 feet, provided that such extension is at least 2 feet from the vertical plane of any lot line.

5. Chimneys may encroach up to 4 feet, provided such extension is at least 2 feet from the vertical plane of any lot line.

6. Cornices, belt courses, sills, buttresses, or other similar architectural features may encroach up to 2 feet.

7. Unenclosed and uncovered patios, decks, swimming pool decking, or terraces may encroach up to 4 feet into a side (interior) setback, or up to 8 feet into a required rear setback, provided that such extension is at least 2 feet from the vertical plane of any lot line.

8. Handicap ramps may encroach to the extent necessary to perform their proper function.

9. Structures below and covered by the ground may encroach to any extent.

C. Accessory Use and Structure Setback Encroachments Accessory uses and structures may encroach into building setbacks in accordance with Sec. 201-1.6 (Accessory Uses and Structures - Residential Districts) and Sec.

201-1.7 (Accessory Uses and Structures - Nonresidential Districts).

D. Buffer Setbacks See Sec. 201-1.9 (Buffer Setbacks) for an additional buffer setback that applies even when a lesser setback is otherwise allowed by this subsection.

(UDO 22-01, § 2, 2-28-2022)

201-1.6. Accessory Uses and Structures - Residential District The following applies in residential and TC-R zoning districts:

A. General Accessory Use and Structure Locations

1. No accessory structure except driveways and individual mailboxes may be in a public right-of-way.

2. Landscaping may not be in a public right-of-way of a City street unless approved by the Director.

3. No accessory structure in a public right-of-way may create a sight hazard to the traveling public. See Sec. 201-1.8 (Intersection Visibility).

4. Accessory uses and structures are only allowed in rear yards, except as shown in Table 201-1.6 or otherwise allowed in this UDO.

5. Accessory uses and structures are subject to the additional buffer setback requirements of Sec. 201-1.9 (Buffer Setbacks), which apply even when a lesser setback is otherwise allowed by this subsection.

6. When an accessory use or structure is allowed in a specific yard, it has no setback requirements, except as shown in Table 201-1.6, clause 5 above, or otherwise in this UDO.

Table 201-1.6. Allowed Locations of Residential District Accessory Uses and Structures

Accessory Use or Structure A = Allowed in yard "—" = Not allowed in yard Front Yard Side Yard (street) Side Yard (interior) Rear Yard Additional Setbacks Standards Additional Standards Basketball goal A A A A May not be located in the right-ofway Bee keeping — — A A See Sec.

206-8.6.B See Sec.

206-8.6.B Canopy and covered entrance A A A A See Sec.

201-1.6.C Canopy (shade, tent, and other temporary shelters) A A A A See Sec.

201-1.6.B See Sec.

206-8.30 Clothes line — — — A Accessory Use or Structure A = Allowed in yard "—" = Not allowed in yard Front Yard Side Yard (street) Side Yard (interior) Rear Yard Additional Setbacks Standards Additional Standards Covered mail kiosk A A — — See Sec.

201-1.6.B See Sec.

206-8.26 Carport (with metal support posts and metal roof) — — — — Deck (uncovered) — — A A See Sec.

201-1.5.B Deck (covered or enclosed) Considered a building addition. See applicable district regulation space limits

Decorative landscaping, such as steppingstones, fountains, birdbaths, birdhouses, light posts, statuary, and bridges

A A A A

Driveway A A A A See Sec.

201-1.6.D Dumpster — — A A See Sec.

201-1.6. B See Sec.

206-8.10 Electric vehicle (EV) charging station — — — — See Sec.

206-8.31 Fence and wall (includes gate) A A A A See Sec.

207-2.3 Flagpole A A A A Front porch, stoop, balcony A A — — See Sec.

201-1.5.B Gatehouse A A — — Gazeebo — — A A See Sec.

201-1.6 See Sec.

206-8.26 Greenhouse — — A A See Sec.

201-1.6 See Sec.

206-8.26 Handicap ramp A A A A See Sec.

201-1.5.B Koi pond A A A A See Sec.

201-1.6.B See Sec.

206-8.28 Lamppost A A — — Mailbox A A — — Mechanical equipment A A A A See Sec.

201-1.6.F See Sec.

207-2.2 Modular office/classroom — — A A See Sec.

201-1.6.B See Sec.

206-8.17 On-site parking A A A A See Sec.

201-1.6.G See Sec.

206-8.18 Parking of business vehicles See Sec. 206-8.21 Parking of recreational vehicles See Sec. 206-8.22 Parking of watercraft See Sec. 206-8.23 Patio (unenclosed and/or uncovered) — — A A See Sec.

201-1.5.B Patio (enclosed and/or covered) Considered a building addition. See applicable district regulation space limits

Pergola — — A A See Sec.

201-1.6.B See Sec.

206-8.29 Playground equipment — — — A See Sec.

201-1.6.B See Sec.

206-8.29 Accessory Use or Structure A = Allowed in yard "—" = Not allowed in yard Front Yard Side Yard (street) Side Yard (interior) Rear Yard Additional Setbacks Standards Additional Standards Portable accessory structure (PODS) A A A A See Sec.

201-1.6.B See Sec.

206-8.24 Roofed accessory structure, except as shown in this table — — A A See Sec.

201-1.6.B See Sec.

206-8.26 Satellite dish antenna — — A A See Sec.

206-8.27 Screened porch or sunroom Considered a building addition.

See applicable district regulation space limits Sidewalk A A — — Sign A A — — See Sec.

207-6 Solar energy system (hybrid) — — — — See Sec.

206-8.32 Stormwater infrastructure A A A A See Sec.

201-1.6.H Swimming pool, hot tub, spa, and associated decking — — A A See Sec.

201-1.6.B See Sec.

206-8.28 Tennis, pickleball, badminton, or shuffleboard court — — — A See Sec.

201-1.6.I See Sec.

206-8.29 Trampoline — — — A See Sec.

201-1.6.B See Sec.

206-8.29 Unroofed accessory structure (not listed herein) — — — — See Sec.

206-8.29 Vegetable garden under 100 sf.

in combined area A A A A See Sec.

201-1.6.B Vegetable garden 100 sf. or more in combined area — — A A See Sec.

201-1.6.B Walkway A A A A

B. Accessory Use and Structure Setback Requirements When shown in Table 201-1.6, accessory uses and structures must observe the following setback requirements adjacent to all lot lines, except when the required building setback is less than the following distances:

1. Up to 100 square feet in area: min. 5-foot setback.

2. 101 to 300 square feet: min. 10-foot setback.

3. 301 to 500 square feet: min. 15-foot setback.

4. Over 500 square feet: min. 20-foot setback.

C. Canopies and Covered Entrances Canopies and covered entrances for places of worship may encroach:

1. Into the required side (interior) or rear yard up to 3 feet; and

2. Into the required front yard or side (street) yard, provided such extensions are not closer than 15 feet from the street right-of-way line or future right-of-way line as designated on the Gwinnett County Long Range Road Classification Map, whichever is greater.

D. Driveways

1. No more than 35% of the front yard area may be used for driveways or authorized on-site parking. See paragraph G below.

a. The Director is authorized to grant administrative variances to the requirement of this section, in order to meet the requirements of Sec.

201-1.6.D.2. or Sec. 201-1.6.D.3.

2. All garage doors facing a public or private street must observe a minimum 22-foot front and side (street) setback from sidewalk in all residential districts.

3. Build to Rent residential districts require a minimum 24-foot wide driveway and minimum 30-foot driveway length, measured from inside edge (house side) of sidewalk to garage door.

E. Fences and Walls

1. Fences, walls, and retaining walls are allowed in all yards, except as provided for in Sec. 201-1.9 (Buffer Setbacks) and clause E.2 below.

2. Fences, walls, and retaining walls in a front yard or side (street) yard must be placed within 2 feet of the vertical plane of any lot line unless a greater distance is required by Sec. 201-1.8 (Intersection Visibility).

F. Mechanical Equipment

1. Mechanical equipment associated with residential uses, such as HVAC units, swimming pool pumps or filters, and security lighting, may encroach into a side (interior) or rear yard, provided that such extension is at least 3 feet from the vertical plane of any lot line.

2. Mechanical equipment associated with residential uses may only encroach into a front or side (street) yard when less than 30 square feet in footprint.

3. Mechanical equipment not associated with residential uses must conform to Sec. 201-1.7.F.

4. See Sec. 207-2.2 for screening requirements.

G. On-Site Parking

1. No parked vehicle or any portion of a parked vehicle, including those in driveways, may be within the public right-of-way including sidewalk, except for authorized on-street parking.

2. When parking is allowed in the front yard, no more than 35% of the front yard area may be used for parking or authorized driveways.

3. When parking is allowed in the rear yard, no more than 20% of the rear yard area may be used for parking, and the parking must be screened from view of adjacent residential uses.

H. Stormwater Infrastructure Stormwater infrastructure may only encroach into a front or side (street) yard when:

1. The infrastructure is completely covered by ground; or

2. The infrastructure consists exclusively of management practices, such as normally dry storage and retention facilities or ponds always maintaining water. These must be designed by a qualified professional as formal or natural amenities with additional uses other than stormwater management, such as an amphitheater, sports field, or a pond or pool as part of the landscape design.

(UDO 22-01, §§ 2, 2(Exh. A), 2-28-2022; UDO 22-03, § 2, 1-9-2023) 201-1.7. Accessory Uses and Structures - Nonresidential Districts The following applies in all nonresidential districts except TC-R.

A. General Accessory Use and Structure Locations

1. No accessory structure, except driveways and individual mailboxes, may be in a public right-of-way.

2. Landscaping may not be in a public right-of-way of a City street unless approved by the Director.

3. No accessory structure in a public right-of-way may create a sight hazard to the traveling public. See Sec. 201-1.8 (Intersection Visibility).

4. Accessory uses and structures are only allowed in rear yards, except as shown in Table 201-1.7 or otherwise in this UDO.

5. Accessory uses and structures are subject to the additional buffer setback requirements of Sec. 201-1.9 (Buffer Setbacks), which apply even when a lesser setback is otherwise allowed by this subsection.

6. Accessory uses and structures are subject to the additional landscape strip restrictions of Sec. 207-3.2.D (Structures in Landscape Strip), which apply even when a lesser setback is otherwise allowed by this subsection.

7. When an accessory use or structure is allowed in a specific yard, it has no setback requirements, except as shown in Table 201-1.7, clause A.5 above, or otherwise in this UDO.

Table 201-1.7. Allowed Locations of Nonresidential District Accessory Uses and Structures

Accessory Use or Structure A = Allowed in yard "—" = Not allowed in yard Front Yard Side Yard (street) Side Yard (interior) Rear Yard Additional Setbacks Standards Additional Standards Basketball goal A A A A Canopy A A A A See Sec.

201-1.7.C Cart coral A A A A Covered mail kiosk A A — — See Sec.

201-1.7.B See Sec.

206-8.26 Decorative landscaping, such as steppingstones, fountains, birdbaths, birdhouses, light posts, statuary, and bridges

A A A A

Drive-thru A A A A See Sec.

206-8.9 Driveway A A A A See Sec.

201-1.7.D Dumpster — — A A See Sec.

201-1.7.B See Sec.

206-8.10 Emergency power generator — — A A See Sec.

201-1.7.F Accessory Use or Structure A = Allowed in yard "—" = Not allowed in yard Front Yard Side Yard (street) Side Yard (interior) Rear Yard Additional Setbacks Standards Additional Standards Electric vehicle (EV) charging station A A A A See Sec.

206-8.31 Fence and wall (includes gates) A A A A See Sec.

201-1.7.E See Sec.

207-2.3 Flagpole A A A A Gasoline pump A A A A See Sec.

201-1.7.B See Sec.

206-8.26 Gatehouse A A — — Koi pond A A A A See Sec.

201-1.7.B See Sec.

206-8.28 Lamppost A A — — Mailbox A A — — Mechanical equipment — — A A See Sec.

201-1.7.F Modular office/classroom — — A A See Sec.

201-1.7.B See Sec.

206-8.17 On-site parking A A A A See Sec.

201-1.7.G See Sec.

206-8.18 Parking of business vehicles See Sec. 206-8.21 Parking of recreational vehicles See Sec. 206-8.22 Parking of watercraft See Sec. 206-8.23 Portable accessory structure (PODS) — — A A See Sec.

201-1.7.B See Sec.

206-8.24 Roofed accessory structure, except as shown in this table — — A A See Sec.

201-1.7.B See Sec.

206-8.26 Sidewalk A A — — Sign A A — — See Sec.

207-6 Solar energy system (hybrid) — — — — See Sec.

206-8.32 Stormwater infrastructure A A A A See Sec.

201-1.7.H Swimming pool, hot tub, spa — — A A See Sec.

201-1.7.B See Sec.

206-8.28 Vacuum and tire pressure stand A A A A Vegetable garden under 100 sf.

in area A A A A Vegetable garden 100 sf. or more in area — — A A Walkway A A A A

B. Setback Requirements When shown in Table 201-1.7, accessory uses and structures must observe the following setback requirements adjacent to all lot lines, except when the required principal building setback is less than the following distance:

1. Up to 100 square feet in area: min. 5?foot setback.

2. 101 to 300 square feet: min. 10?foot setback.

3. 301 to 500 square feet: min. 15?foot setback.

4. Over 500 square feet: min. 20?foot setback.

C. Canopies

1. When a canopy not over a pump island is utilized in connection with a commercial or industrial use it may encroach into a required front or side (street) yard, subject to the following:

a. No portion of a canopy may be closer than 10 feet from the vertical plane of any street right-of-way, nor closer than 20 feet from the vertical plane of the face of the curb of the street.

b. No canopy may occupy more than 50% of a required yard over which it extends.

c. Canopies must be completely unenclosed.

2. Canopies over pump islands may extend up to the street right-of-way line or future right-of-way line as designated on the Gwinnett County Long Range Road Classification Map, whichever is more restrictive.

D. Driveways Driveways and alleys providing inter-parcel access are allowed in all required yards but may not exceed 24 feet in width and must be placed generally perpendicular to the yard.

E. Fences and Walls

1. Fences, walls, and retaining walls are allowed in all yards, except as provided for in Sec. 201-1.9 (Buffer Setbacks), Sec. 207-2.3 (Fences and Walls), Sec.

207-3.2.D (Structures in Landscape Strip), and clause E.2 below.

2. Fences, walls, and retaining walls in a front yard or side (street) yard must be placed within 2 feet of the vertical plane of any lot line unless where a greater distance is required by Sec. 207-3.2 (Landscape Strips) or Sec. 201-1.8 (Intersection Visibility).

F. Mechanical Equipment

1. Mechanical equipment may encroach into a side (interior) or rear yard.

2. Mechanical equipment may only encroach into a front or side (street) yard when less than 30 square feet in footprint.

3. Minor structures accessory to utilities (such as hydrants, manholes, sanitary sewer lift stations, emergency power generators, transformers, and other cabinet structures, and related fences) may encroach into a rear or side (interior) yard but are not allowed in a front of side (street) yard.

4. See Sec. 207-2.2 for screening requirements.

G. On-Site Parking

1. No parked vehicle or any portion of a parked vehicle, including those within driveways, may be within the public right-of-way, except for authorized on-street parking.

2. The parking of any vehicle in any yard is allowed, except where specifically not allowed by district regulations, building types, or use standards.

H. Stormwater Infrastructure Stormwater infrastructure may only encroach into a front or side (street) yard when:

1. The infrastructure is completely covered by ground; or

2. The infrastructure consists exclusively of management practices, such as normally dry storage and retention facilities or ponds always maintaining water. These must be designed by a qualified professional as formal or natural amenities with additional uses other than stormwater management, such as an amphitheater, sports field, or a pond or pool as part of the landscape design.

(UDO 22-01, § 2(Exh. A), 2-28-2022) 201-1.8. Intersection Visibility

A. Except in districts allowing the construction of buildings or structures to the lot line, an unobstructed view must be provided across the triangles formed as follows:

1. By a diagonal line connecting two points located on intersecting lines of the street right-of-way, each point being 20 feet from the intersecting lines.

2. By a diagonal line connecting two points located on intersecting street right-of-way, alley easement, or alley edge lines, each point being 15 feet from the intersecting lines.

3. Within these triangles, there may be no sight obscuring wall, fence, entrance sign, marker, or foliage higher than 30 inches above grade, or in the case of trees, foliage lower than 8 feet. Vertical measurements are made at the top of the curb on the street or alley adjacent to the nearest side of the triangle or if no curb exists, from the edge of the nearest traveled way.

B. Heights of fences, hedges, and other continuous foliage are measured from the adjacent top of the street curb, the surface of an alley or the official established grade thereof, whichever is the higher. On interior lot lines, the measurement is from the average grade of the lot line of the property with the lower elevation.

C. The City Council or Board of Appeals may approve, or may direct as a condition of approval, fences or plantings taller than allowed by paragraph A and B above in order to provide screening between different uses or between like uses upon agreement between the affected parties. No such approval may have the effect of reducing visibility required by this subsection.

D. See Sec. 401-5.13.D for additional corner sight distance requirements along minor collectors or major thoroughfares.

201-1.9. Buffer Setbacks Structures, including driveways, parking facilities, and retaining walls must be located at least 5 feet from any buffer required by Sec. 207-2.1.B (Buffer Requirements).

201-1.10. Floor Area

A. Single-Family Dwelling Floor Area Floor area is the sum of finished and conditioned floor area on all floors within surrounding exterior walls of a building. Floor area does not include unenclosed balconies, unenclosed porches, unenclosed stoops, unfinished attics, unfinished basements, garages, or carport.

B. Floor Area of all Other Uses Floor area is the sum of floor area on all floors within surrounding exterior walls of a building. Areas of a building not provided with surrounding walls are included in the floor area if such areas are included within the horizontal projection of the roof or floor above.

Floor area does not include unenclosed balconies, unenclosed porches, unenclosed stoops, or parking structures.

201-1.11. Height

A. General

1. No building or structure may be erected, converted, enlarged, reconstructed, moved or structurally altered to exceed the height limit established for the zoning district it is located in.

2. The height of buildings and structures is also regulated by the building construction codes, which only apply for building construction code purposes.

B. Measurement Height is measured as the vertical distance from the mean finished ground level at the front of the building to the highest point of a roof or parapet.

C. Height Variances Buildings and structures exceeding the height limitations contained in this UDO, and which have not been granted approval by the City Council through a related zoning action, require variance approval by the Board of Appeals.

D. Height Encroachments The maximum height limits of the district do not apply to:

1. Cupolas, weathervanes, chimneys, parapets and similar architectural features, or satellite dishes or other necessary mechanical rooftop appurtenances provided they do not exceed the height limit by more than 20 feet.

2. Steeples, domes, belfries or ornamental towers, if they are 100 feet in height or less.

3. Barns, silos, and similar agricultural structures, if they are 75 feet in height or less.

4. Water towers, smokestacks, conveyors, derricks, and similar industrial structures, if they are 75 feet in height or less.

5. Flagpoles, if they are 80 feet in height or less.

6. All other structures, except buildings and signs, if they are 50 feet in height or less.

7. The height of transmission towers, radio or television towers and antennas and other telecommunication facilities, which are regulated in Sec. 206-4.3.D (Telecommunications Antenna and Tower).

201-1.12. Street Classification For purposes of this UDO, all of the streets, roads, and highways are classified in the current adopted Gwinnett County Unified Plan or Long-Range Transportation Plan.

(UDO 25-01, § 1, 3-10-2025)

201-1.13. Fenestration

A. Fenestration is the minimum percentage of window and door glass that must cover a façade.

B. Glass used to satisfy fenestration requirements must be unpainted, must have a transparency (visible light transmission) higher than 70%, and must have an external reflectance of less than 15%. Transparency and external light reflectance must be established using the manufacturer's specifications.

C. Fenestration is measured from the top of the finished floor to the top of the finished floor above.

D. When there is no floor above, fenestration is measured from the top of the finished floor to the top of the wall plate.

E. Window signs must conform to the coverage restrictions of Sec. 207-6 (Signs).

F. Adhesive film, fabric, paper, and other materials that are affixed to the window surface or otherwise installed in a way that prevents visibility into the building interior are prohibited. This prohibition does not apply to curtains, shades, Venetian blinds, interior or exterior shutters, and other window treatments that are in operable condition and capable of being adjusted, opened, or closed daily.

201-1.14. Blank Wall Area

A. Blank wall area means a portion of the exterior façade of the building that does not include: fenestration, columns, pilasters, or other articulation greater than 12 inches in depth.

B. Blank wall area applies in both a vertical and horizontal direction.

C. Blank wall area applies to ground and upper story street-facing facades only.

201-1.15. Pedestrian Access

A. A pedestrian entrance and walkway providing ingress and egress, operable to residents at all times and operable to customers, visitors, and employees during business hours, is required to meet any street-facing pedestrian entrance requirements. Additional entrances off another street, pedestrian area, civic space, amenity space, or internal parking area are permitted but must have the same or shorter hours of operability as the street-facing entrance.

B. A street address number must be located above the street-facing pedestrian entrance utilizing numbers that are 6 to 10 inches in height. When multiple entrances exist on a street-facing façade, only one address is required.

C. An angled or mitered pedestrian entrance may be provided at either corner of a building along the street to meet the street-facing pedestrian entrance requirements.

D. These requirements may also apply abutting a civic space in TC Districts, as determined by the Director. In making this determination, the Director must consider the use and design of the civic space, the use of the proposed building, and the public health, safety, and welfare.

E. A front porch or stoop is required to meet the street-facing pedestrian entrance requirements when required by building type.

Sec. 201-2. Building Types 201-2.1. General

A. Applicability

1. This section only applies in zoning districts where building types are utilized.

2. All principal buildings in zoning districts where building types apply must comply with this section.

B. Intent Building types are used to improve the design of development in certain districts in order to reinforce their character and scale.

C. Determination of Buildings Type Applicants must select which allowed building type corresponds to the building they are proposing to construct or alter, subject to the approval of the Director.

D. Graphic Depictions are Illustrative Only All graphic depictions of building types are for illustrative and zoning purposes only.

E. Relationship to Building Codes Building types are not linked to building construction codes.

201-2.2. Detached House

A. Defined A building type that accommodates one single-family detached dwelling unit on an individual lot with yards on all sides.

Not for nonresidential use.

B. Specific Standards Lot Detached house units per lot: 1 max.

Pedestrian Access Entrance facing street: Required Walkway width: 3 ft. min./ 5 ft. max.

Front porch or stoop: Required Parking Location No on-site parking is allowed between the building and the street, except in driveways that conform to applicable UDO standards.

(UDO 22-01, § 2, 2-28-2022)

201-2.3. Carriage House

A. Defined A building type that accommodates an accessory dwelling unit on the same lot as a detached house, semi-detached house, or townhouse but is physically separated from the principal dwelling unit. Carriage houses may also contain garages, workshops, and similar uses. Not for

nonresidential use.

B. Specific Standards Lot Carriage house units per lot: 1 max.

Size Dwelling Floor Area:

800 sf. max. (excluding garage, workshops, and similar) Bedrooms: 1 max.

Pedestrian Access Entrance facing street: Not Required Walkway width: n/a Parking Location On-site parking located is determined by the principal dwelling unit.

201-2.4. Cottage Court

A. Defined A building type that accommodates five to ten detached dwelling units organized around a shared internal courtyard. Units may not be vertically mixed. Not for nonresidential use.

B. Specific Standards Site Site area: 20,000 sf. min.

Units per courtyard: 5 min./ 10 max.

Courtyard Area: 3,000 sf. min.

Width: 40 ft. min.

Courtyard may not be parked or driven upon, except emergency access and permitted temporary events.

Pedestrian Access Entrance facing street: Required for units along street Walkway width: 3 ft. min./ 5 ft. max.

Front porch or stoop: Required Parking Location No on-site parking is allowed between the building and the street, except in driveways that conform to applicable UDO standards.

201-2.5. Semi-Detached House

A. Defined A building type that accommodates one two-family dwelling. Units may be arranged horizontally or vertically. Not for nonresidential use.

B. Specific Standards Lot Semi-detached house units per lot: 2 max.

Pedestrian Access Entrance facing street: Required Walkway width: 3 ft. min./ 5 ft. max.

Front porch or stoop: Required Parking Location No on-site parking is allowed between the building and the street, except in driveways that conform to applicable UDO standards.

201-2.6. Townhouse

A. Defined A building type that accommodates three or more dwelling units where each unit is separated by a common sidewall. Units may not be vertically mixed. Not for nonresidential use.

B. Specific Standards Site Townhouse units per: 3 min.

Townhouse units in a row:

8 max. [1] Fenestration Ground floor: 10% min.

Upper story: 10% min./ 35% max.

Blank wall area: 20 ft. max.

Pedestrian Access Entrance facing street: Required for units along street Walkway width: 3 ft. min./ 5 ft. max.

Front porch or stoop: Required Parking Location and Access Rear-entry garages and driveways with access from alley only. Front-entry garages prohibited. No onsite parking is allowed between the building and the street.

Design No more than three adjacent units may have the same front façade designs. Differentiation between adjacent units may be accomplished by a change in materials, building height, color, roof form, or setbacks.

Table Note:

[1] Units in separate buildings connected by a canopy, pergola, or similar exterior feature are considered separate rows.

(UDO 22-01, § 2, 2-28-2022; UDO 25-01, § 1,

3-10-2025) 201-2.7. Walk-Up Flat

A. Defined A building type that accommodates three to eight dwelling units vertically and horizontally integrated. Not for nonresidential use.

B. Specific Standards Site Walk-up flat units per building: 3 min./8 max.

Floor to Ceiling Height All stories: 9 ft. min.

Fenestration Ground floor: 15% min.

Upper story: 10% min./ 40% max.

Blank wall area: 20 ft. max.

Pedestrian Access Entrance facing street:

Required for lobby (if provided) or ground floor units along street (if no lobby) Walkway width: 3 ft. min./ 6 ft. max.

Front porch or stoop: Required Parking Location No on-site parking is allowed between the building and the street, including in driveways.

201-2.8. Stacked Flat

A. Defined A building type that accommodates nine or more dwelling units vertically and horizontally integrated. Not for nonresidential use.

B. Specific Standards Site Stacked flat units per building: 9 min.

Street facing façade length: 200 ft. max.

Floor to Ceiling Height All stories: 9 ft. min.

Fenestration Ground floor: 15% min.

Upper story: 10% min./ 40% max.

Blank wall area: 20 ft. max.

Pedestrian Access Entrance facing street:

Required for lobby and ground floor units along street Walkway width: 3 ft. min./ 8 ft. max.

Front porch or stoop Required Parking Location No parking lot is allowed between the building and the street, including within driveways.

201-2.9. Commercial House

A. Defined A building type that accommodates nonresidential uses in a building that resembles a detached house. Not for residential uses.

B. Specific Standards Site Street facing façade length: 100 ft. max.

Floor to Ceiling Height All stories: 9 ft. min.

Fenestration Ground floor: 10% min./ 30% max.

Upper story: 10% min./ 30% max.

Blank wall area: 20 ft. max.

Pedestrian Access Entrance facing street: Required for businesses facing a street Walkway width: 6 ft. min.

Front porch or stoop Required Parking Location No on-site parking is allowed between the building and the street, including within driveways.

201-2.10. Shopfront

A. Defined A single-story building type that typically accommodates single-use retail or commercial activity. Not for residential

uses.

B. Specific Standards Site Street facing façade length: 200 ft. max.

Floor to Ceiling Height Ground floor: 14 ft. min.

Other stories: 9 ft. min.

Fenestration Ground floor: State route/local street:

30% min./ 70% min.

Blank wall area: State route/local street:

40 ft. max./ 20 ft. max.

Pedestrian Access Entrance facing street: Required every 75 ft. of frontage Walkway width: 6 ft. min.

Parking Location No parking lot is allowed between the building and the street, including within driveways.

201-2.11. Mixed-use Building

A. Defined A multi-story building type that typically accommodates ground floor retail, office or commercial uses with upper-story residential or office uses. Not for ground floor dwelling units except when such units are not along a street-facing façade.

B. Specific Standards Site Street facing façade length: 200 ft. max.

Floor to Ceiling Height Ground floor: 14 ft. min.

Other stories: 9 ft. min.

Fenestration Ground floor: State route/local street:

30% min./ 70% min.

Blank wall area: State route/local street:

40 ft. max./ 20 ft. max.

Upper story: 10% min./ 40% max.

Pedestrian Access Entrance facing street: Required every 75 ft. of frontage Walkway width: 6 ft. min.

Parking Location No parking lot is allowed between the building and the street, including within driveways.

201-2.12. General building

A. Defined A multi-story building type that typically accommodates nonresidential uses such as industrial, hotel or office uses on all stories. Not for residential use.

B. Specific Standards Site Street facing façade length: 200 ft. max.

Floor to Ceiling Height Ground floor: 11 ft. min.

Other stories: 9 ft. min.

Fenestration Ground floor: State route/local street:

20% min./ 50% min.

Blank wall area: State route/local street:

40 ft. max./ 20 ft. max.

Upper story 20% min./ no max.

Pedestrian Access Entrance facing street: Required every 150 ft. of frontage Walkway width: 6 ft. min.

Parking Location No on-site parking is allowed between the building and the street, including within driveways.

201-2.13. Civic Building

A. Defined A building type that accommodates civic uses. Not for commercial, retail, office, or residential uses.

B. Specific Standards Fenestration Ground floor: 15% min.

Blank wall area: 60 ft. max.

Upper story: 15% min.

Pedestrian Access Entrance facing street: Required Walkway width: 6 ft. min.

Parking Location No on-site parking is allowed between the building and the street, including within driveways.

201-2.14. Building Elements

A. Intent The following standards are intended to ensure that certain building elements, when added to a street-facing façade, are of sufficient size to be both usable and functional and be architecturally compatible with the building they are attached to.

B. Applicability

1. This subsection applies in all zoning districts where building types are utilized.

2. This subsection also applies in other districts when indicated in district regulations.

C. Front Porch A raised structure attached to a building, forming a covered pedestrian entrance to a doorway.

1. A front porch must be at least 6 feet deep (not including the steps).

2. A front porch must be contiguous, with a width not less than 33% of the building façade from which it projects.

3. A front porch must be roofed and may be screened but may not be fully enclosed.

4. A front porch may extend up to 9 feet, including the steps, into a required front setback, provided that such extension is at least 2 feet from the vertical plane of any lot line.

5. A front porch must not encroach into the public right-of-way or required sidewalk.

6. Steps leading to front porches must have enclosed risers.

7. Round roof support columns must have a minimum diameter of 8 inches.

8. Square roof support columns must have a minimum width of 6 inches.

D. Stoop A small raised platform that serves as a pedestrian entrance to a building.

1. A stoop must be no more than 6 feet deep (not including the steps).

2. A stoop may be covered but may not be fully enclosed.

3. A stoop may extend up to 6 feet, including the steps, into a required setback, provided that such extension is at least 2 feet from the vertical plane of any lot line.

4. A stoop must not encroach into the public right-of-way or required sidewalk.

5. Steps leading to stoops must have enclosed risers.

6. Stoop columns, where provided, must be a minimum width of 8 inches.

E. Balcony A platform projecting from the wall of an upper story of a building with a railing along its outer edge, often with access from a door or window.

1. A balcony must be at least 4 feet deep and may extend up to 6 feet into a required setback, provided that such extension is at least 2 feet from the vertical plane of any lot line.

2. A balcony must have a clear height above the sidewalk of at least 10 feet.

3. A balcony may be covered and screened but may not be fully enclosed.

4. A balcony may encroach up to 6 feet into the public right-of-way or required sidewalk but must be at least 2 feet inside the curb line or edge of the pavement, whichever is greater.

5. No signage may be affixed to a balcony.

F. Awning/Canopy A wall-mounted, cantilevered structure providing shade and cover from the weather for a sidewalk.

1. Awnings must be located on the ground floor.

2. An awning must be a minimum of 10 feet clear height above the sidewalk and must have a minimum depth of 6 feet.

3. An awning may extend into a required setback.

4. An awning may encroach up to 9 feet into the public right-of-way or required sidewalk but must be at least 2 feet inside the curb line or edge of the pavement, whichever is greater.

5. Awnings must be made of canvas or other woven fabric and may not be reflective or shiny.

6. Awnings must have open ends called "shed awnings" to allow views into buildings.

7. Awnings may not be internally lit nor allow light to pass through awning materials.

8. Awnings may only be externally lit from above for below.

9. Awnings may not be narrower than, nor 2 feet wider than, the door or window opening that they serve. Where multiple doors and windows are less than 2 feet apart, multiple awnings may be combined into a single awning.

G. Gallery A covered passage extending along the outside wall of a building supported by arches or columns that is open on three sides.

1. A gallery must have a clear depth from the support columns to the building's façade of at least 8 feet and a clear height above the sidewalk of at least 10 feet.

2. A gallery must be contiguous and extend over at least 75% of the width of the building façade from which it projects.

3. A gallery may extend into a required setback.

4. A gallery may encroach up into the required sidewalk but not the required planter.

Sec. 201-3. General Architectural Standards 201-3.1. General

A. Applicability This section applies to buildings and sites in all zoning districts, except the TCO, TC, MU, and NR districts.

B. Alternative Standards The City Council may approve alternative standards to this section as a condition of rezoning.

C. Intent These regulations are intended to:

1. Maintain high quality, long-lasting, and sustainable development in Snellville.

2. Enhance the visual appeal and livability of the city.

3. Foster architectural diversity and interest, yet achieve and maintain a consistent, durable and pleasing aesthetic/visual quality.

4. Ensure that large commercial buildings incorporate designs that reduce their visual mass and create the impression of smaller buildings.

D. Application Requirements

1. Building plans submitted as an application for a building permit must clearly indicate the proposed building materials and colors for each facade as described in this section. The plans must also clearly show the location and calculate the percentages of all building materials per facade.

2. Groups of buildings on the same site may be reviewed and permitted as a single application. This is encouraged to minimize the number of reviews required and to allow for originality and design flexibility.

E. Relief

1. The Director is authorized to grant administrative variances to the requirements of this section.

2. Administrative variances may only be granted to permit a practice that is not consistent with a specific provision of this section but is justified by their intent.

3. Administrative variances relating to a physical element or numeric measurements must be based upon credible submitted evidence demonstrating that:

a. Approval, if granted, would not offend the intents of paragraph C above;

b. There are such extraordinary and exceptional situations or conditions pertaining to the particular piece of property that the literal or strict application of the regulations would create an unnecessary hardship due to size, shape or topography or other extraordinary and exceptional situations or conditions not caused by the applicant;

c. Relief, if granted would not cause a substantial detriment to the public good and surrounding properties; and

d. That the public safety, health, and welfare are secured, and that substantial justice is done.

201-3.2. Basic Standards

A. Applicability The following applies to any new building that is not used for a single-family detached, two-family, or attached dwelling.

B. General

1. Permanent mounted exterior neon lights are not allowed.

2. Back-lit awnings, roof-mounted lights, and roof-mounted flag poles are not allowed.

3. Satellite dishes must be located and painted to blend with the background as much as practical.

C. Exterior Wall Finish Materials Exterior wall finish materials (excluding foundations, architectural accents, windows, and doors) are limited to the following and Table 201-3.2.C and Table 201-3.2.D:

1. Unpainted full-depth brick where each brick is placed on the exterior wall during construction, but not including half-depth brick, thin brick, or simulated brick veneers;

2. Stone, including unpainted natural stone, unpainted cast stone with the appearance of natural stone, and unpainted terra cotta;

3. True hard coat stucco;

4. Concrete block, which must be painted;

5. Split-face block and painted concrete masonry units (CMU);

6. Wood, including natural wood or cement-based artificial wood siding;

7. Shingles, including wood or cement-based shakes and shingles;

8. Tilt/architectural pre-cast concrete; and

9. Glass.

D. Exterior Wall Finish Material Combinations Exterior wall finish materials may only be combined horizontally, with the visually heavier below the lighter as shown in Table 201-3.2.C. This does not apply to architectural accents or glass.

Table 201-3.2.C. General Architectural Standards Visual Weight Table This table shows the visual weight of permitted materials. Those at the top are lighter than those at the bottom and must be combined accordingly.

True Hard Coat Stucco Shingles Wood/Cement-Based Siding Brick, CMU, Pre-Cash Concrete Natural/Manufactured Stone _______________________________________________________________________________________________ Table 201-3.2.D.1. Allowed Building Materials: All Uses

Yes = Material is allowed with no limitations Percent (%) = Material is allowed but may not exceed the indicated percent of the total façade area (calculated per facade) and may not be combined with another material with a percentage restriction.

No = Material is not allowed Zoning District Brick Stone Glass Tilt/ PreCast True Hard Coat Stucco Concrete Block CMU/SplitFace Block Siding Front Side/ Rear Front/ Side Rear Front/ Side Rear Front Side/ Rear

RES

SPECIAL

USE

Yes Yes No No Max. 50% per facade Max. 50% per facade No No No No Max. 50% per facade Max. 50% per facade

R-DU, RM,

RX, R0

Yes Yes No No Max. 50% per facade Max. 50% per facade No No No No Max. 50% per facade Max. 50% per facade OP, CI Yes Yes Yes No Max. 25% per facade Max. 50% per facade No No No No No [3] No [3] MU Yes Yes Yes No Max. 25% per facade Max. 50% per facade No Yes [1] No Yes [1] No 25% BG Yes Yes Yes No Max. 25% per facade Max. 50% per facade No Yes [1] No Yes [1] No 25% HSB Yes Yes Yes No Max. 25% per facade Max. 50% per facade No Yes [1] No Yes [1] No 25% LM[2] Yes Yes Yes No Max. 50% per facade Yes No Yes [1] Max.

50% per facade Yes [1] Yes [4] Yes Table Notes [1] Allowed only on rear facades of buildings larger than 10,000 square feet floor area. When allowed it must be tinted or painted to blend with the balance of the building. Concrete block and CMU/split-face block are prohibited when the rear building faces a residential property or public street.

[2] For industrial/warehouse buildings less than 30,000 square feet floor area.

[3] Allowed for buildings intended to have a residential appearance. A minimum 4:12 roof pitch is required.

[4] Allowed for building facades that are setback at least 150 feet from the right-of-way.

Table 201-3.2.D.2. Allowed Building Materials: Uses over 30,000 square feet Floor Area

Yes = Material is allowed with no limitations Percent (%) = Material is allowed but may not exceed the indicated percent of the total façade area (calculated per facade) and may not be combined with another material with a percentage restriction.

No = Material is not allowed Zoning District Brick Stone Glass Tilt/ PreCast True Hard Coat Stucco Concrete Block CMU/Split-Face Block [1] Siding Front Side/Rear Front/ Side Rear Front/ Side Rear Front Side/ Rear BG Yes Yes Yes Yes [1] Max. 25% per facade Max. 50% per facade No Yes [1] No Yes [1] No No HSB Yes Yes Yes Yes [1] Max. 25% per facade Max. 50% per facade No Yes [1] No Yes [1] No No LM Yes Yes Yes Yes [1] Max. 50% per facade Yes No Yes [1] Max.

25% per facade Yes [1] Yes [2] Yes Table Notes [1] Allowed only on rear facades. When allowed it must be tinted or painted to blend with the balance of the building. Concrete block and CMU/split-face block are prohibited when the rear building faces a residential property or public street.

[2] Allowed for building facades that are setback at least 150 feet from the right-of-way.

E. Architectural Accent Materials Architectural accents are limited to the following:

1. Any allowed exterior wall finish materials;

2. EIFS, provided the total combined area of EIFS and the other materials identified in clause 3 below may not exceed 15% of total wall area per façade; and

3. Small amounts of other materials, provided the total combined area of these accents may not exceed 10% of the total wall area per facade.

F. Building Color

1. All exterior wall finish, foundations, windows, and door material colors must use hues from or equivalent to any historic palettes from any major paint manufacturer, except that primary and fluorescent colors are not allowed.

2. Colors other than those allowed by clause F.1 above may be used for accents but may not exceed 10% of the total façade wall area.

G. Building Massing Variation in the roofline of buildings and offsets in pitched roofs and gables are required.

Parapets on individual facades exceeding 125 continuous linear feet must vary in height and projection at least once every 125 feet and must use decorative elements such as crown moldings, dentils, brick soldier courses, or similar details.

(UDO 22-01, § 2(Exhs. C, D), 2-28-2022) 201-3.3. Small Residential Building Standards

A. Applicability The following applies to:

1. New single-family detached dwellings not in subdivisions;

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:snellville/zoning/whole@2026-07-13-45b520c7a7

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Snellville Zoning Ordinance (the whole text) (Parte 2 de 7) | Georgia Commons