Sec. 106-174. Group projects.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) A group project (including, but not limited to, residential, commercial, industrial, educational, medical, religious, or civic uses) of two or more buildings to be constructed on a plot of land at least two acres not subdivided into customary streets and lots, and which will not be so subdivided, may be constructed provided:
(1) Such uses are limited to those permitted within the district in which the project is located;
(2) The over-all intensity of land use is no higher, and the standard of open space is no lower, than that permitted on the district in which the project is located;
(3) The distance of every building from the nearest property line shall meet the front-yard setback and side-yard requirements of the district in which the project is located;
(4) The building heights do not exceed the height limits permitted in the district in which the project is located; and
(5) On property that lies within or abuts upon a residential district, there shall be a ten-foot planted buffer strip along the rear and/or side lot lines abutting the residential properties.
(b) Approval process. Approval shall be provided by the planning commission of Tallapoosa. An application form/request letter, which may be provided by the department of planning, shall be presented. An application fee of $150.00 shall be included with the application. Said fee shall be amended from time to time by the mayor and council by resolution. The application for group project status shall be advertised in the legal advertising organ of Haralson County or similar newspaper of general circulation in a similar fashion as a rezoning application (including posting the property): at least 15 days prior to, but no more than 45 days prior to, the upcoming planning commission meeting. A site plan must be provided that shows the following:
(1) A plat of the property showing dimensions of parcel. Also include location and size of structures to be constructed, parking spaces allocated to new construction and their location on the property. If required, the 10-foot planted buffer zone, indicating type of plant to be installed.
(2) Verification of available sewer and water (statement from public works director or city manager).
(3) The planning coordinator, city manager or his/her designee, shall conduct a preliminary evaluation of the submitted site plan to verify that all required information has been included. Site plan review shall require a fee of $50.00. Said fee shall provide two reviews of the site plan. If still not correct after the second review, an additional fee of $25.00 per review shall be assessed. Said fees may be amended by the mayor and council from time to time by resolution. If site plan is not complete at the time the planning commission convenes, this shall be grounds for denying the group project status request. Plans must be submitted at the time of the application being submitted.
Application must be submitted in a timely fashion to allow all necessary advertising to be accomplished.
(4) If the request is denied, a second request for the same property shall not be submitted for a minimum of 12 months from the date of the denied group project request.
(5) Based upon the planning commissions' review of the supplied information, including public comments upon the proposal, the planning commission shall approve or deny the group project request. If any party is aggrieved of the decision by the planning commission, the aggrieved party may appeal to the City of Tallapoosa's mayor and council for review of the decision.
Historia
(Ord. No. 01252, Sec. 106-84, 12-12-2005; Ord. No. 01312, § 1(Exh. 2024-B), 3-11-2024)