Sec. 13-52. Rate schedules.

Sobre este texto

  • As published by Municode, current through 2026-10-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

The following schedules are applicable to the service furnished by the electric system. Rates and charges are on file at the city clerk's office and the administrative offices of the utilities department:

(1) Electric residential service.

a. Applicability. For all domestic uses of a residential customer in a separately metered single-family dwelling unit. A separately metered pump may be billed on this rate if it supplies domestic water to an individual residence. Largest motor shall not exceed 7½ horsepower.

b. Type of service. Power normally supplied under this rate will be 115/230 volts, single phase, 60 hertz. The generation charges, monthly rates, and other requirements shall be those published on the electric residential service rate schedule ER, as approved by the city council, and maintained in the office of the city clerk and the superintendent of the utilities department.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Multiple service. Where it is impractical to separately meter each unit, two or more dwelling units may be served through a single meter. Where this is done each kWh block in the monthly rate will be multiplied by the number of separate dwelling units so served. The minimum monthly bill under this option shall be the minimum monthly charge times the number of dwelling units served.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

(2) Security lighting.

a. Availability. To property owners where the low voltage distribution lines of the city are within 500 feet. Service may be made available to tenants in accordance with the terms of the contract period

b. Applicability. Applicable to security lighting on customer property by means of highpressure sodium vapor luminaries supported by short brackets mounted on wood poles in the city's existing distribution system or extension from this system, or on poles owned by the customer, conforming to standard specifications and mutually satisfactory to both the customer and the city. In all cases, the luminaire, bracket and control equipment shall be installed, owned and maintained by the city. Where the use of poles other than wood is desired by the customer, the customer shall install, own and maintain such poles and the city shall install, own and maintain the overhead conductors, the brackets and lighting equipment. Where the use of underground conductors is desired by the customer, the customer shall install, own and maintain the underground conductors and the risers up the poles. Security lighting service will be provided only at locations which are accessible to city trucks for servicing purposes. Original locations of lighting fixtures shall be by mutual agreement and any relocation requested by owner after installation is in operation shall be made at owner's expense.

c. Maintenance. Existing mercury vapor luminaires will only be maintained by replacement or bulbs or photo-electric cells. Any maintenance requirement beyond bulb and photoelectric cell replacement will result in the removal of the mercury vapor fixture and the installation of a comparable (lumen output) high-pressure sodium vapor fixture. Maintenance will be performed as soon as can reasonably be done after notification of the city by the customer that service has been interrupted. Maintenance will be done only during regular working hours.

d. Contract period. Three years.

e. Cancellation of contract. Contract may be canceled by either party on 60 days' written notice; however, should the customer cancel the contract during the first 36 months, the customer shall pay to the city to cover the unamortized cost of installation and removal for each month remaining in the original 36-month period. Tenants wishing to contract for this service may be required to make a deposit per lamp. Such deposit, if required, will be returned on request at the end of the original 36-month contract period.

(3) Electric general service—Small.

a. Applicability. To any general service, commercial or industrial customer of less than 50 kilowatts of maximum monthly demand delivered and metered at one point. Service to two or more premises shall not be combined nor shall service hereunder be shared with others. Service hereunder shall not be resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest kW measurements during the current month and the preceding 11 months as follows:

1. July through October (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (November through June).

2. November through June (winter), the greater of:

(i) 95 percent of the highest summer month (July through October); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less than the contract minimum, nor less than five kW.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not less than one year.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(4) Electric general service—Medium.

a. Applicability. To any general service, commercial or industrial customer of greater than 50 kW and less than 500 kW of maximum monthly demand delivered and metered at one point. Service to two or more premises shall not be combined nor shall service hereunder be shared with others. Service hereunder shall not be resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest KW measurements during the current month and the preceding 11 months as follows:

1. July through October (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (November through June).

2. November through June (winter), the greater of:

(i) 95 percent of the highest summer month (July through October); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less than the contract minimum, nor less than 25 kW.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the above monthly rate.

g. Term of contract. Not less than one year.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(5) Electric general service—Large.

a. Applicability. To any general service, commercial or industrial customer of greater than 500 kilowatts and less than 5,000 kilowatts of maximum monthly demand delivered and metered at one point, service to two or more premises shall not be combined nor shall service hereunder be shared with others. Service hereunder shall not be resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest KW measurements during the current month and the preceding 11 months as follows:

1. July through October (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (November through June).

2. November through June (winter), the greater of:

(i) 95 percent of the highest summer month (July through October); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less than the contract minimum, nor less than 250 kW.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not less than five years.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing, and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(6) Electric general service—Non-demand.

a. Applicability. To any general service, commercial or industrial customer using less than 3,000 kWh monthly and having a maximum 30-minute demand of less than 30 kW delivered and metered at one point. Service to two or more premises shall not be combined nor shall service hereunder be shared with others. Service hereunder shall not be resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. Not applicable.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not applicable.

h. Transformer substation. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(7) Electric temporary/seasonal service, non-agricultural.

a. Applicability. To temporary or seasonal service. The term "temporary service" means service rendered to a transient customer for a single short term of less than five months duration. The term "seasonal customer" means a customer with a recurring seasonal pattern of service requirements whether permanently or not permanently connected. A temporary or seasonal customer may elect at the temporary or seasonal customer's option, to contract for service at a regular applicable rate when it appears that the temporary or seasonal customer's total bill thereunder including all charges, minimums, and guarantees incident to an annual contract will be less than under this schedule.

However, contracting for service at a regular rate does not exempt this type customer from paying any applicable connection charges.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The demand for any delivery point shall be based on the highest 30-minute kW measurements during the current month.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not applicable.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(8) Electric seasonal service, agricultural.

a. Applicability. To any general service, commercial or industrial customer for all electric service of one standard voltage, delivered and metered at one point that also qualifies as an agricultural seasonal customer as described herein. An agricultural seasonal customer operates primarily during non- electrical peak months (September through June) setting operational demands considerably in excess of the non-operational demand. Service to two or more premises shall not be combined, nor shall service thereunder be shared with others. Service thereunder shall not be resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest KW measurements during the current month and the preceding 11 months as follows:

1. July through October (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (November through June).

2. November through June (winter), the greater of:

(i) 95 percent of the highest summer month (July through October); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less the contract minimum, nor less than five kW.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate;

g. Term of contract. Not less than one year up to and including 500 kW maximum anticipated 30 minute kW, nor less than five years over 500 kW maximum anticipated 30 minute kW;

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer;

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(9) Electric public school general service.

a. Applicability. To any city or county public educational institution offering regular elementary or high school courses.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest KW measurements during the current month and the preceding 11 months as follows:

1. June through September (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (October through May).

2. October through May (winter), the greater of:

(i) 95 percent of the highest summer month (June through September); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less than the contract minimum, nor less than five kW. The on-peak billing demand shall be based on the average of the five highest monthly 30 minute kW measurements during the period from June 15 to September 15. This on-peak billing demand will be that average monthly demand that occurs between the hours of 3:00 p.m. and 7:00 p.m. (EST or EDT) Monday through Friday.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not less than one year. up to and including 500 kW maximum anticipated 30-minute kW, nor less than five years over 500 kW maximum anticipated 30 minute kW.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(10) Electric high demand general service.

a. Applicability. To any general service, commercial, or industrial customers of greater than 5,000 kW of maximum monthly demand during eight out of 12 consecutive calendar months delivered and metered at one point. Service hereunder shall not be shared with others or resold to any third party.

b. Type of service. Single- or three-phase, 60 hertz, at a standard voltage.

c. Power cost adjustment. All bills shall be increased or decreased in an amount per kWh equal to the difference between the total cost kWh of bulk power and the base power cost per kWh as determined from monthly wholesale power billings rendered to the city by MEAG Power.

d. Environmental compliance cost recovery (ECCR). The monthly environmental compliance cost recovery adjustment (ECCR), in cents per kWh, shall be added to all metered bills for this service. The ECCR shall represent an amount no higher than that which may be calculated using the economic compliance cost reporting issued from time to time by the city's principal electricity supplier, MEAG Power.

e. Determination of demand. The maximum billing demand shall be based on the highest KW measurements during the current month and the preceding 11 months as follows:

1. July through October (summer), the greatest of:

(i) The current actual demand;

(ii) 95 percent of the highest actual demand occurring in any previous applicable summer month; or

(iii) 60 percent of the highest actual demand occurring on any previous applicable winter month (November through June).

2. November through June (winter), the greater of:

(i) 95 percent of the highest summer month (July through October); or (ii) 60 percent of the highest winter month (including the current month).

In no case shall the billing demand be less than the contract minimum demand, nor less than 2,500 kW.

f. Unmetered service. Where the installation of metering equipment is impractical or installed equipment fails, monthly kWh may be estimated by the city and billed at the applicable monthly rate.

g. Term of contract. Not less than ten years.

h. Transformer substations. Specification of primary or secondary metering shall be at the city's option. The city will own, operate and maintain the transformer substation where a single standard secondary voltage is used and only one transformer is required. Where the customer purchases service at primary voltage in order to obtain consolidated billing and requires more than one transformer station to serve separate loads, all necessary transformer stations shall be owned, operated and maintained by the customer.

i. Delivery point to major supplier. The city may elect to sell power under this rate to a major power supplier when such supplier has requested a power delivery point.

(11) Automatic annual rate adjustment. Effective beginning January 1, 2026 and January 1 of each calendar year thereafter (each an "effective date"), each and every rate and charge for services provided for in this section, including any minimum base or similar charges, shall be automatically increased by reference to the Seasonally Adjusted Consumer Price Index for All Urban Consumers (1982-1984 = 100), U.S. City Average: All Items, published by the U.S. Department of Labor, Bureau of Labor Statistics ("CPI") as follows:

a. In each instance every rate, charge, and/or fee provided for by this section for the calendar year preceding an effective date shall be increased as follows:

1. Find the percentage change between (i) the June CPI number published for the month of June immediately preceding each such effective date and (ii) the June CPI number for the month of June for the year prior to the year of the June CPI number published for the month of June immediately preceding each effective date.

2. Multiply the percentage change by 75 percent.

3. Multiply the product of that calculation by the rate, charge or fee to be increased.

4. Add the product of that calculation to the rate, charge or fee to be increased and the sum is the increased rate, charge and/or fee for the calendar year of each such effective date.

Provided however, no adjustment shall be made pursuant to this subsection that will reduce any such rate, charge, and/or fee below the amount set for the calendar year immediately preceding each such effective date.

Provided further, that no adjustment shall be made pursuant to this subsection that will increase any such rate, charge, and/or fee in an amount that is greater than three percent of the rate, charge, and/or fee for the calendar year immediately preceding each such effective date. For the avoidance of doubt, any automatic adjustment made pursuant to this subsection shall not preclude or prohibit the additional increase of any rate, charge, or fee provided for in by section by the city council.

b. By way of illustration and not limitation, if the June 2024 CPI number was 313.131, the June 2025 CPI number was 321.500, and the 2025 residential service minimum base charge was $18.00, then the 2026 residential service minimum base charge would be calculated as follows:

1. 321.500 - 313.131 = 8.369 / 321.500 = .0260 (100) = 2.60%

2. 2.60% (75%) = .020

3. 0.020 ($18.00) = .36

4. 0.36 + $18.00 = $18.36.

(Code 1958, § 18-26; Code 1991, § 13-55; Ord. of 1-12-1987(1); Ord. of 1-28-1988; Ord. of 11-28-1988(2);

Ord. of 1-8-1990; Ord. of 6-11-1990(1); Ord. of 7-23-1990; Ord. of 10-26-1992; Ord. of 10-10-1994, § I;

Ord. of 1-25-1995, § I; Ord. of 5-28-1998, § I; Ord. of 5-24-1999; Ord. No. 05082000-6, § I, 5-8-2000; Ord.

No. 11252002-6, § I, 11-25-2002; Ord. No. 04112005-1, § I, 4-11-2005; Ord. No. 09082014-2, 9-8-2014;

Ord. No. 09142020-1, § XIII, 9-14-2020; Ord. No. 42-12102025, § II, 12-10-2025)

Reuniones que se refieren a esta sección

Encontradas: 1. Son reuniones de este gobierno cuyas actas o transcripciones automáticas nombran esta sección, o una ordenanza de su línea de historia, de la más reciente a la más antigua. Halladas por regla a partir de las propias palabras de esos registros. Una referencia es un enlace a otro registro, no una afirmación de que la sección se aplica o se cambió.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:thomasville/code/13-52@2026-10-20-9b50a6a61d

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Thomasville Code of Ordinances, Sec. 13-52. Rate schedules | Georgia Commons