Ware County · Código de ordenanzas
Part II - CODE OF ORDINANCES / Chapter 68 - CRYPTOCURRENCY AND DATA MINING.
Sec. 68-4. Standards for commercial cryptocurrency mining operations.
Sobre este texto
- As published by Municode, current through 2025-12-08
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) All principal and accessory structures used for cryptocurrency mining operations, server farms, and/or data mining centers, shall be arranged, designed, and constructed to be harmonious and compatible with the site and with the surrounding properties. If prefabricated, pre-engineered or modular structures are installed, the following standards are required:
(1) All structures shall have concrete foundations.
(2) All exterior facades shall have muted earth tone colors, and shall not be defective, decayed, or corroded.
(3) If intermodal shipping containers are utilized, such installation shall comply with the requirements of the most recent edition of Industrialized Building Rules and Bulletins of the Georgia Department of Community Affairs, and O.C.G.A. Title 8, Chapter 2, Article 2. Part 1.
(b) The operations shall not cause the dissemination of vibration or noise in excess of the maximum environmental noise level established by this Code chapter 46, section 46-1.
(c) The operators shall not cause, allow, or permit the operation of any source of sound which creates at an occupied residential building or defined sensitive receiver, as may exist at the time of the issuance of a certificate of completion or occupancy, a sound level that exceeds a daytime continuous sound level of 50 dBA or a nighttime continuous sound level of 45 dBA.
(d) The operators shall not cause, allow, or permit the operation of any source of sound or vibration which creates a pure tone where the one-third octave band sound pressure level in the band of interest exceeds the arithmetic average of the sound-pressure levels for the two adjacent one-third octave bands by the corresponding decibel (dB(Flat)) values as follows:
(1) Five dB for center frequencies of 500 Hertz and above,
(2) Eight dB for center frequencies between and including 160 and 400 Hertz, and
(3) 15 dB for center frequencies less than or equal to 125 Hertz.
(4) A pure tone shall be deemed present by measurement.
(e) For permitting and compliance purposes, measurements shall be performed using a calibrated type 1 sound level meter, configured to log and record one-third octave flat-weighted equivalent sound pressure levels, and A-weighted equivalent level (Leq), slow time weighting, with a 15-minute averaging interval. Measurements shall be made proximate to, but no closer than 100 feet from any adjacent property line. Transient background sounds must be excluded from the measurement period by post-processing or other means. Compliance is indicated if the noise solely generated by the operator cannot be discriminated from the equivalent-continuous background sound pressure level, or if the noise levels solely generated by the operator otherwise conform to the requirements of section 68-4(c) and section 68-4(d).
(f) Prior to the issuance of a certificate of completion or occupancy, a report with noise level test results shall be submitted for approval by the applicant from a noise control engineering professional for the purpose of demonstrating compliance. The expense for testing and reporting the results, in written format, to the county will be the responsibility of the applicant.
(g) A noise reduction barrier or device may be required at the discretion of the county when it is conclusive that noise level tests do not conform to sections 68-4(c) and 68-4(d). If this is required of the applicant or facility, the expense of compliance shall be the applicant's expense and not the county's.
(h) Terminology as used herein related to acoustic levels and measurements follow American National Standard ANSI S12.9: "Quantities and Procedures for Description and Measurement of Environmental Sound - Part 1: Basic Quantities and Definitions," and ANSI S12.9: "Quantities and Procedures for Description and Measurement of Environmental Sound. Part 3: Short-term measurements with an observer present".
(i) The equipment used in any commercial cryptocurrency mining operation shall be housed in a metered (either individually or collectively in primary-metered services), electrically grounded, and pre-engineered metal-encased structure with a fire rating designed to resist an internal electrical fire for at least 30 minutes. The containment space shall contain baffles that will automatically close in the event of fire independent of a possible electric system failure.
(j) Commercial cryptocurrency mining data center will undergo SOC 2 auditing resulting in successful certification. The data center will also maintain the SOC 2 certification for the duration of operation. Validation of certification will be provided to the county within 13 months of beginning operation and annually thereafter.
(k) Any use or activity producing air, dust, smoke, glare, exhaust, heat, or humidity in any form shall be carried on in such a manner that it is not perceptible at or beyond the property line.
(l) Any use of ISO shipping containers or similar as housing, whether horizontally combined or independent of other structures for the commercial cryptocurrency mining operation, shall not be vertically combined to exceed a height greater than nine feet.
(m) Each commercial cryptocurrency mining and data mining operation shall provide a 24-hour emergency contact signage visible at the access entrance. Signs shall include company name if applicable, owner/representative name, telephone number, and corresponding local power company and telephone number.
(n) All requirements of this chapter must be maintained after the issuance of a certificate of occupancy. Any violation of such will be handled in accordance with section 68-6.
(o) Each commercial cryptocurrency mining and data mining operation shall be set back at least 1,000 feet from any residential structure. The distance shall be measured from the closest corner of the residential structure to the closest corner of the commercial cryptocurrency mining or data mining structure in a straight line, or colloquially known as, "as the crow flies".
(p) A fence of at least six feet high shall be required around the site. The fence shall be constructed of a solid material or barrier. If constructed of another material, fence shall block vision.
(q) Prior to approval of the certificate of completion or occupancy, the applicant shall provide written verification from the electrical service provider stating the following:
(1) Adequate capacity is available on the applicable supply lines and substation to ensure that the capacity available to serve the other needs of the service area is consistent with the normal projected load growth envisioned by the provider;
(2) Utility supply equipment and related electrical infrastructure are sufficiently sized and can safely accommodate the proposed use;
(3) The use will not cause electrical interference or fluctuations in line voltage on and off the operating premises; and
(4) Prior to approval of the certificate of completion or occupancy, the applicant shall provide the city/county with written verification that the electrical work has passed a third-party final inspection.
(r) Any commercial cryptocurrency mining operation that is not operated for a continuous period of 12 months and for which there are no applications pending for permitted use of the structure at the end of such 12-month period, shall be considered abandoned, whether or not the owner or operator intends to make use of the device(s). The owner of an abandoned server farm or data center, and the owner of the property where the abandoned server farm and data center are located shall be under a duty to remove such facilities. If such facilities are not removed within a reasonable time, not to exceed three months, after receipt of notice from the governing authority notifying the owner(s) of such abandonment, the governing authority may remove such facilities and place a lien upon the property for the costs of removal. The governing authority may pursue all legal remedies available to it to insure that abandoned device(s) are removed. Delay by the governing authority in taking action shall not in any way waive the governing authority's right to take action.
Historia
(Ord. No. 2025-02, § C, 4-14-2025)
Reuniones que se refieren a esta sección
- Ware County Board of Commissioners, 14 de abril de 2025 (Actas)Nombra una ordenanza de la historia de esta sección en las actas: “Ordinance 2025-2”
- Ware County Board of Commissioners, 14 de abril de 2025 (Actas)Nombra una ordenanza de la historia de esta sección en las actas: “ORDINANCE 2025-02”
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.