Appendix B - SIGN ORDINANCE § 13[12] / Article 4 - DEVELOPMENT CONSTRUCTION APPROVAL

Sec. 4.3. Development permit process.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

1. Initiation of process.

a. A developer shall submit to the code compliance officer:

(1) One copy plus a digital version of an application for a development permit; and

(2) One copy plus a digital version of all construction plans required by these regulations.

b. The code compliance officer shall distribute copies for the city manager and city engineer to review.

c. The code compliance officer shall forward a copy of the documents to all relevant county offices (i.e.: environmental health, emergency management, school district, etc.), the Soil and Water Conservation Commission District, the Georgia DOT or others as appropriate, for their review and comment.

2. Process for approval of application and plans for development permit. An application for a development permit may proceed simultaneously with an application for a preliminary plat, but may not be issued prior to approval of such plat.

a. The application package must include:

(1) Application on the form furnished by the city.

(2) One copy of the preliminary plat plus a digital copy.

(3) One copy of the construction plans plus a digital copy.

(4) Two copies of the hydrology study plus a digital copy.

(5) One copy of the soil tests (if applicable).

(6) Payment of any development permit fee, as established from time to time by city council resolution.

b. Incomplete application packages will be rejected and returned to the applicant.

c. Upon receipt of a complete application package, the code compliance officer shall:

(1) Refer the soil erosion and sedimentation control plan to the city engineer and the soil and water conservation commission.

(2) Refer the grading plan, the stormwater management plan, the floodplain management/ flood damage prevention plan (if any), and the street improvements plan to the city engineer.

(3) Refer the water and sewerage public utility plans to the county utilities department.

(4) Refer the on-site septic system plans to the county health department.

d. The applicant may be required by the city engineer to secure development approval from other agencies if affected by the development, such as: Fire marshal, Georgia Department of Transportation, Georgia Department of Natural Resources, U.S. Army Corps of Engineers, and U.S.

Environmental Protection Agency.

e. Upon receipt of comments from other departments and/or agencies, the city engineer will indicate in writing all comments related to these regulations, conditions of zoning approval, and other regulations or ordinances.

f. The comments shall also encompass all requirements in 4.4 below.

g. The city engineer will forward all comments to the applicant.

h. The applicant must respond satisfactorily to all of the comments, and the city engineer and involved individuals, agencies and departments will confirm such, then advise the city in writing.

i. Following receipt of approvals from all involved agencies, individuals and receipt of all required bonds, a final set of construction plans shall be submitted to the code compliance officer.

j. No development permit will be issued unless the tax commissioner's office certifies that all ad valorem taxes on the property and due and owing have been paid.

k. Upon written certification from the city engineer of:

(1) Compliance, and

(2) Receipt of final approved construction plans, the mayor and council will then consider the application and plans at their next regular meeting, and formally approve such.

l. Then, the code compliance officer shall issue the development permit, only after all requirements of these regulations and other agencies are met and approval by the city engineer and mayor and council has been obtained.

m. No development permit will be issued by the code compliance officer unless the plan has been approved by the above departments and entities, and any bonding, if required, has been obtained.

n. The permit authorizes development per the approved final construction plans.

o. If the tract is developed in phases, a separate permit shall be required for each phase.

p. The applicant will be responsible for compliance with all codes, regulations and zoning requirements. In the event of any conflict between these regulations and the zoning ordinance, the provisions of the zoning ordinance will govern.

3. Expiration of development permit. A development permit shall expire if the development per the permit is not begun within one year from issuance. Provided, however, for good cause shown, upon written application from the applicant, the mayor and council may extend the deadline for an additional 12 months. Any change of construction plans that may materially impact the permit shall require a permit amendment. Amendments shall follow the same procedure as original applications for a development permit, subject to the requirements as of the date of application of such amendment.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:watkinsville/zoning/4.3@2026-11-11-e3d15c0913