Waycross · Código de ordenanzas
Part II - CODE OF ORDINANCES / Part A - GENERAL ORDINANCES / Chapter 103 - BUILDINGS AND BUILDING REGULATIONS / Article II - ADMINISTRATION AND ENFORCEMENT
Sec. 103-26. Inspections.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Existing building inspections. Before issuing a permit, the building and code manager or his designee may examine or cause to be examined any building, electrical, gas, mechanical, or plumbing systems for which an application has been received for a permit to enlarge, alter, repair, move, demolish, install, or change the occupancy. All buildings, structures, electrical, gas, mechanical, and plumbing systems shall be inspected from time to time, during and upon completion of the work for which a permit was issued. The building and code manager or his designee shall make a record of every such examination and inspection and of all violations of the technical codes.
(b) Manufacturers and fabricators. When deemed necessary by the building officials, an inspection of materials or assemblies at the point of manufacture or fabrication may be made.
A record shall be made of every such examination and inspection and of all violations of the technical codes.
(c) Inspection service. The building and code manager may make, or cause to be made, the inspections required by subsection (f) of this section. Reports may be accepted of inspectors of recognized inspection services provided that after investigation, their qualifications and reliability are satisfactory. A certificate called for by any provision of the technical codes shall not be based on such reports unless the same are in writing and certified by a responsible officer of such service.
(d) Inspections prior to issuance of certificate of occupancy or completion. The building officials shall inspect at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building, structure, electrical, gas, mechanical, or plumbing system upon completion, prior to the issuance of the certificate of occupancy or completion.
(e) Posting of permit. Work requiring a permit shall not commence until the permit holder or his agent posts the permit card in a conspicuous place on the premises. The permit card shall be protected from the weather and located in such position as to permit the building officials to conveniently make the required entries thereon. This permit card shall be maintained in such position by the permit holder until the certificate of occupancy or completion is issued.
(f) Required inspections. Upon notification from the permit holder or his agent, the following inspections and such other inspections as necessary, shall be made by the building officials and they shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical codes:
(1) Building.
a. Foundation inspection. To be made after trenches are excavated and forms erected.
b. Frame inspection. To be made after the roof, all framing, fireblocking, and bracing have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.
c. Final inspection. To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to ensure compliance with all the requirements of this Code and to assure that the installation and construction of the gas system is in accordance with reviewed plans.
(2) Energy.
a. Foundation inspection. To be made before slab concrete is poured in place. To verify float perimeter insulation has been installed correctly on any slab on grade foundations.
b. Frame inspection. To be made before exterior wall insulation is concealed by wall board to check installation of exterior walls insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner as to restrict air passage.
c. Final inspection. To be made after the building is completed and ready for occupancy. To verify installation and R-value of ceiling and floor insulation. To verify correct SEER ratings on appliances.
(g) Written release. Work shall not be done on any part of a building, structure, electrical, gas, mechanical, or plumbing system beyond the point indicated in each successive inspection without first obtaining a written release from the building officials. Such written release shall be given only after an inspection has been made of each successive step in the construction or installation as indicated by each of the foregoing three inspections.
(h) Reinforcing steel, structural frames, insulation, plumbing, mechanical, or electrical systems. Reinforcing steel or structural frame work of any part of any building or structure shall not be covered or concealed without first obtaining a release from the building officials.
(i) Plaster fire protection. In all buildings where plaster is used for fire protection purposes, the permit holder or his agent shall notify the building department after all lathing and backing is in place. Plaster shall not be applied until the release has been received from the building officials.
(j) Building and mobile home vacancy permits and inspections required. The owner or renter shall be required to obtain a vacancy permit and inspection for any building or mobile home that has not had power and/or water supplied to the building or mobile home for a period of six months or more before the power and/or water can be supplied to the mobile home or building.
Once the owner or renter has obtained the vacancy permit, the city building department shall, at the owner's or renter's request, schedule an inspection of the existing conditions of the mobile home or building to ensure compliance with all current technical codes and any other city codes and ordinances.
Historia
(Code 1977, § 7-106; Ord. No. 96-34, § 1, 11-5-1996; Ord. No. 16-06, § 1, 4-5-2016)
Reuniones que se refieren a esta sección
- Waycross City Commission, 1 de julio de 2025 (Actas)Se refiere a esta sección en las actas: “Section 103-26”
- Waycross City Commission, 30 de junio de 2025 (Actas)Se refiere a esta sección en las actas: “Section 103-26”
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.