2.3.2. Stormwater Runoff Quality/Reduction in Redevelopment.

Sobre este texto

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Stormwater management systems for redevelopment be designed to retain the first 1.0 inch of rainfall on disturbed area of site to the maximum extent practicable. The determination by the county that it is infeasible to apply the stormwater runoff quality/reduction standard, on part or all of a project, must be documented with the site plan review documents. If the first 1.0 inch of rainfall can be retained onsite using runoff reduction methods, then no additional water quality treatment is required. If the 1.0 inch cannot be retained onsite, the remaining runoff from a 1.2-inch rainfall event must be treated to remove at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the LDM and GSMM. This standard assumes that BMPs will be designed, constructed and maintained according to the criteria in the GSMM.

Stormwater discharges from land uses or activities with higher or special potential pollutant loadings may require the use of specific structural practices and pollution prevention practices. A detailed overview of BMPs is provided in chapter 4 of the GSMM.

For further discussion on this standard, see section 2.2.4.1 of the GSMM.

The county encourages the designer to implement specific stormwater credits for reducing the water quality treatment requirements on site. These credits can be found in section 2.3.3 of the GSMM.

However, the county recognizes that water quality treatment of stormwater runoff from certain areas of a site is not feasible. As such, the following areas are exempt from water quality treatment.

Portions of the site that lie within 50 feet of the property line and drain away from the site assuming that no impervious surfaces (including compacted gravel/rock) lie within the 50-foot zone except retaining walls.

Impervious surfaces associated with any new driveway (maximum width of each driveway allowed for exemption is 50 feet) for the first 50 feet as measured from the edge of pavement of the public street to which it connects.

Additional, water quality requirements may be specified for hotspot land uses and activities.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:whitfield-county/zoning/2.3.2@2026-05-11-e561e69208

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.