6.4.4. Proposed conditions model diagram.

Sobre este texto

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A diagram of the hydrologic model should be provided with the report showing how the model was developed and each node is connected.

7. STORMWATER CONCEPT REQUIREMENTS

The county engineer recognizes that some sites will require a substantial investment in time and effort to develop a comprehensive stormwater management plan that will address the requirements contained within this manual. As such, some developments are required to conduct a concept conference with the county engineer prior to submittal of the land disturbance application. A concept conference can be held either in the form in person or via phone. This requirement is aimed at reducing the amount of effort required to develop the final plan and permit the project. Concept conferences are required to be held for all developments that meet one or more of the following criteria:

• Any residential subdivision with greater than 50 lots, unless such development contains 2-acre or greater lots.

• Any non-residential development with a disturbed area of ten acres or greater.

• Any non-residential development regardless of size which has an impervious surface coverage that covers 50 percent or more of the property excluding those lands contained within undisturbed buffers including but not limited to floodplains, stream buffers and undisturbed buffers between dissimilar zonings.

• Any non-residential development regardless of size which is defined as a hot spot land use.

Prior to holding the concept conference the designer should consider submitting any pertinent design documents such as conceptual plans, maps or calculations in order to illustrate the proposed development.

8. HYDROLOGIC AND HYDRAULIC REPORT REQUIREMENTS

All development projects must submit a hydrologic and hydraulic report outlining the impacts of the site on the stormwater system. At a minimum, this report must include the following sections:

• Certification by registered professional.

• Project narrative.

• Existing conditions hydrologic analysis.

• Post-development hydrologic analysis.

• Stormwater management system design.

• Downstream analysis.

• Erosion and sedimentation control plan.

• Planting plan (if applicable).

• Operations and maintenance plan.

The following subsections outline the requirements for each of the elements outlined above.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:whitfield-county/zoning/6.4.4@2026-05-11-c5236ff514

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Whitfield County Zoning Ordinance, 6.4.4. Proposed conditions model diagram | Georgia Commons