Sec. 2-414. Deceleration and turning lanes.
Sobre este texto
- As published by Municode, current through 2022-10-28
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Generally. Access improvements such as deceleration lanes, dedicated left-turning lanes, center turn lanes, merge lanes, signalization, etc., required as deemed necessary for safe traffic operations by the zoning administrator shall be installed at all entrance roads into a development or major subdivision. The zoning administrator shall use the Georgia Department of Transportation Regulations for Driveway and Encroachment Control, Revision 5.2, dated
March 5, 2021, Section 4.9, "Auxiliary Turn Lanes," as may be amended from time to time, as a basis for determining whether deceleration lanes and other lanes are required; unless otherwise determined appropriate by the zoning administrator, if the DOT driveway regulations would require an improvement if the road were a state route, the zoning administrator shall require the same such improvements.
(b) Length. Generally, deceleration lanes and turn lanes shall be a minimum length of 150 feet, with an additional 50-foot taper length, and a pavement width of 12 feet (exclusive of curb and gutter). Deceleration lanes and tapers may be required to be of greater length, based on the design speed of the road
(c) Right-of-way. If needed, additional right-of-way to accommodate the deceleration lane or turn lane and a ten-foot shoulder shall be dedicated by the developer to the city.
(d) Drainage. Associated drainage improvements as deemed necessary by the city in the construction of the deceleration or turn lane shall also be required. The developer will pay the cost of any cross-drain pipe relocations and catch basins that must be constructed along an existing state or city road as a result of installing a required deceleration or turning lane.
(e) Utilities. Utilities shall be relocated at the developer's expense outside of a deceleration or turning lane.
Historia
(Ord. of 5-17-2021(1))
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.