Sec. 17-25. Decommissioning.
Sobre este texto
- As published by Municode, current through 2025-04-15
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) No later than the end of the fifth full year of the solar project's operation, and every five years thereafter that the solar project remains in operation, the solar project permit holder shall:
(1) Reevaluate decommissioning costs for the solar project; and
(2) Provide to the county security sufficient for such decommissioning costs in the form of a new or modified guaranty to ensure the availability of funds for such costs. The guaranty shall be from an entity having (1) at the time of delivery of such guaranty, a senior unsecured long-term debt rating of BBB- or better from Standard and Poor's and Baa3 or better from Moody's; or (2) audited financial statements, prepared by a nationally-recognized firm of independent auditors and indicating a financial net worth of at least $10,000,000.
(b) Upon failure to accomplish the provisions in the decommissioning plan, the land owner must file a claim on the bond and decommission the project.
Historia
(Ord. of 6-16-2020)