Sec. 34-281. Land disturbance permit application requirements.
Sobre este texto
- As published by Municode, current through 2026-09-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Land disturbance permit required. No person shall conduct any land-disturbing activity within the jurisdictional boundaries of the county without first obtaining a land disturbance permit from the county to perform such activity and shall provide to the county a copy of the NOI submitted to EPD if applicable. Application under this article should be made in conjunction with application for permits under the county stormwater management ordinance (sections 34-551 et seq.), as no land-disturbing activity can take place except in compliance with that ordinance. In addition, the applicant is required to comply with all applicable provisions of the ordinances listed in subsection 34-280(a).
(b) Application. The application for a land disturbance permit shall be submitted to the county and must include the applicant's erosion, sedimentation and pollution control plan with supporting data, as necessary. Said plans shall include, as a minimum, the data specified in section 34-282 of this article. Applications for a permit will not be accepted unless accompanied by five copies of the applicant's soil erosion, sedimentation and pollution CD34:49 Supp. No. 9
control plan. All applications shall contain a certification stating that the plan preparer or the designee thereof visited the site prior to creation of the plan in accordance with EPD Rule 391-3-7-10.
(c) Fees.The county assesses local permitting fees and also state-mandated fees. All applicable fees shall be paid prior to issuance of the land disturbance permit.
(1) Local permitting fees. Except as otherwise provided for herein, fees for an application for a permit on a per-acre of land disturbed basis, as required by this article, shall be as established by the commissioner of the county from time to time by resolution of the commissioner.
(2) State-mandated fees. In addition to the local permitting fees, state-mandated fees shall also be assessed pursuant to O.C.G.A. § 12-5-23(a)(5), provided that such fees shall not exceed $80.00 per acre of land-disturbing activity, and these fees shall be calculated and paid by the primary permittee as defined in the state general permit for each acre of land-disturbing activity included in the planned development or each phase of development. All applicable fees shall be paid prior to issuance of the land disturbance permit. In a jurisdiction that is certified pursuant to O.C.G.A. § 12-7- 8(a), one-half of such fees levied shall be submitted to the division; except that any and all fees due from an entity which is required to give notice pursuant to O.C.G.A.
§ 12-7-17(9) or (10) shall be submitted in full to the division, regardless of the existence of a local issuing authority in the jurisdiction.
(d) Review by district. Immediately upon receipt of an application and plan for a permit, the county shall refer the application and plan to the district for its review and approval or disapproval concerning the adequacy of the erosion, sedimentation and pollution control plan. The district shall approve or disapprove a plan within 35 days of receipt. Failure of a district to act within 35 days shall be considered an approval of the pending plan. The results of the district review shall be forwarded to the county. No permit will be issued unless the plan has been approved by the district, and any variances required by subsections 34-267(c)(15) and (16) have been obtained, all fees have been paid, and bonding, if required as per subsection 34-281(f), have been obtained. Such review will not be required if the local issuing authority and the district have entered into an agreement which allows the local issuing authority to conduct such review and approval of the plan without referring the application and plan to the district. The local issuing authority with plan review authority shall approve or disapprove a revised plan submittal within 35 days of receipt. Failure of the local issuing authority with plan review authority to act within 35 days shall be considered an approval of the revised plan submittal.
(e) Repeat violations; fraudulent submissions.
(1) Repeat violations. If a permit applicant, has had two or more violations of previous permits, this article (including predecessors), or the Erosion and Sedimentation Act of 1975, as amended, within three years prior to the date of filing of the application under consideration, the county may deny the permit application.
(2) Fraudulent submissions. Fraudulent submissions are prohibited, and any falsehoods or misinformation on a permit application shall subject the application to rejection, and subject any permit to revocation. If a permit is granted to a person who is later determined by the county engineer to be a �strawman,� (i.e., not the actual operator, but rather a front for the actual operator), the permit shall be revoked.
(3) Appeals of denials/revocations. Any person whose permit has been denied or revoked pursuant to this subsection may appeal to the board of zoning appeals. See section 34-299. Any applicant that wishes to appeal the decision of the board of zoning appeals may do so appealing to the county commissioner. See section 34-299. Any person aiding in an attempt to circumvent this paragraph may be cited for violation of this article. Whenever a permit is revoked pursuant to this subsection, the letter of credit posted pursuant to subsection (d) of this section may be called and funds therefrom used to stabilize the property subjected to land-disturbing activities.
(f) Surety requirements. The county shall require the permit applicant to post a surety in an amount equal to $3,000.00 per acre or fraction thereof of the proposed land-disturbing activity, prior to issuing the permit. The surety shall be in the form of government security, cash, irrevocable letter of credit, or any combination thereof, in a format approved by the county. The surety requirement may be combined with other surety requirements of other provisions of the County Code relating to roads, storm water, utilities and others. If the applicant does not comply with this article or with the conditions of the permit after issuance, the county may draw against the surety or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.
If, through inspection, it is determined that a person engaged in land-disturbing activities has failed to comply with the approved plan, a written notice to comply shall be served upon that person. The notice shall set forth the measures necessary to achieve compliance with the plan and shall state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he shall be deemed in violation of this article and, in addition to other penalties, his surety may be drawn against as follows:
(1) Process and appeal. If the permit holder believes they are not in violation of this article such that the surety should not be drawn against, the permit holder shall have five days to appeal any notice to comply to the county commissioner. The appeal provisions of section 34-299 shall not apply to this decision. Appeal shall be made by filing a written notice of appeal with the county engineer stating the basis for the appeal. The commissioner shall consider the appeal as soon as possible, at a public meeting. Except in emergency situations, the surety shall not be drawn against until the appeal is considered.
(2) Partial release. The county engineer may release a portion of the letter of credit, for the land-disturbing amount, after final stabilization is complete and all permanent CD34:51 Supp. No. 9
vegetation and stabilization measures are in place. Any portion of the letter of credit relating to roads, stormwater, utilities or other provisions of the County Code shall be governed by its particular section of the Code.