Chapter 34 - ENVIRONMENT / Article II - FLOODPLAIN MANAGEMENT/FLOOD DAMAGE PREVENTION / Division 4 - PERMIT PROCEDURES AND REQUIREMENTS

Sec. 34-62. Floodplain management plan requirements.

Sobre este texto

  • As published by Municode, current through 2026-09-02
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

An application for a development project with any area of special flood hazard located on the site will be required to include a floodplain management/flood damage prevention plan.

This plan shall include the following items:

(1) Site plan drawn to scale, which includes but is not limited to:

a. Existing and proposed elevations of the area in question and the nature, location and dimensions of existing and/or proposed structures, earthen fill placement, amount and location of excavation material, and storage of materials or equipment;

b. For all proposed structures, spot ground elevations at building corners and 20-foot or smaller intervals along the foundation footprint, or one-foot contour elevations throughout the building site;

c. Proposed locations of water supply, sanitary sewer, and utilities;

d. Proposed locations of drainage and stormwater management facilities;

e. Proposed grading plan;

f. Base flood elevations and future-conditions flood elevations;

g. Boundaries of the base flood floodplain and future-conditions floodplain;

h. If applicable, the location of the floodway; and

i. Certification of the above by a registered professional engineer or surveyor.

(2) Building and foundation design detail, including but not limited to:

a. Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures;

b. Elevation in relation to mean sea level to which any non-residential structure will be flood-proofed;

c. Certification that any proposed non-residential flood-proofed structure meets the criteria in subsection 34-92(2);

d. For enclosures below the base flood elevation, location and total net area of foundation openings as required in subsection 34-91(5).

e. Design plans certified by a registered professional engineer or architect for all proposed structure(s). Design plans shall include general site plans as well as specific foundation design for any structure erected in the floodplain, and shall contain sufficient detail to allow the department to determine if the provisions of this article are satisfied. Additionally:

1. Non-residential and residential plan review is required for all proposed structures located within the floodplain.

2. The final certificate-of-occupancy (C.O.) will be issued with additional language stating the structure is located within the floodplain.

CD34:17 Supp. No. 14

3. The crawl space must be allowed to drain. Finished grade in the under floor surface shall be as high as the outside finished grade or an approved drainage system must be provided.

(3) Description of the extent to which any watercourse will be altered or relocated as a result of the proposed development;

(4) Hard copies and digital files of computer models, if any, copies of work maps, comparison of pre- and post-development conditions base flood elevations, futureconditions flood elevations, flood protection elevations, special flood hazard areas and regulatory floodway widths, flood profiles and all other computations and other information similar to that presented in the FIS;

(5) Copies of all applicable state and federal permits necessary for proposed development; and

(6) All appropriate certifications required under this article.

The approved floodplain management/flood damage prevention plan shall contain certification by the applicant that all development activities will be done according to the plan or previously approved revisions. Any and all development permits and/or use and occupancy certificates or permits may be revoked at any time if the construction and development activities are not in strict accordance with approved plans.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 10-10-2007, § 402; Ord. of 3-10-2021(2), § I)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:bartow-county/code/34-62@2026-09-02-1eccfe0565

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Bartow County Code of Ordinances, Sec. 34-62. Floodplain management plan requirements | Georgia Commons