Bartow County · Código de ordenanzas
Chapter 68 - TIMBER OPERATIONS
Sec. 68-1. Requirement of notice for timber harvesting.
Sobre este texto
- As published by Municode, current through 2026-09-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) All persons or firms harvesting standing timber in any unincorporated area of Bartow County for delivery as pulpwood, logs, poles, posts, or wood chips to any woodyard or processing plant located inside or outside this state shall provide notice of such harvesting operations to the county community development department prior to entering onto the property if possible, but in no event later than 24 hours after entering onto the property.
Further, such persons shall give notice of cessation of cutting within 24 hours after the job is completed.
(b) This chapter applies to activities which qualify as forestry land management practices or agricultural operations under O.C.G.A. § 12-7-17(5) and (6) on land that is zoned for or used for forestry, silvicultural or agricultural purposes. It shall not authorize land disturbing activities incidental to development in conflict with the limitations set forth in O.C.G.A.
§ 12-7-17(6).
(c) Pre-timber operation meeting. Prior to the notice becoming effective and prior to any timber operations commencing, and onsite meeting with the timber operator will be required with a representative of the community development department. The purpose of the meeting will be to verify installation of required signage (see section 68-10(b)(4)) and the temporary construction exit (see section 68-10(b)(2)).
Historia
(Ord. of 7-13-2022(2))
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.