Sec. 90-41. Line extensions.

Sobre este texto

  • As published by Municode, current through 2026-04-13
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) authority's responsibility for line extension. When public funds are available for line extensions, the authority will carry out construction in the order established in a priority road list adopted by the authority. This list shall be based upon a balance of sound engineering and service to a maximum customer base. A current road priority list for line extensions on roads unincorporated Butts County shall be maintained by the authority and made available to the public.

(b) Plans and specifications for construction of water lines. The authority shall have the right to specify the requirements, plans, and specifications for construction of water lines in unincorporated Butts County. All water lines constructed, or paid for, by the authority, any municipality, utility, contractor, consumer, owner, or developer shall be constructed according to the plans and specifications established by the authority for the construction of water lines in Butts County.

No water line shall be covered without first being inspected and approved by the authority. No line shall be put into service without being approved by the authority for disinfection and pressure tightness.

(c) Extensions not initiated by the authority.

(1) Water line extensions to existing residential, industrial, and commercial development.

The authority recognizes that areas of pre-existing development may have property owners who desire water service prior to public funds being available for construction.

Therefore, on existing public roads, the authority will provide labor and equipment at no charge for line extensions to existing development under the following conditions:

a. Right-of-way. Water lines may only be extended along county roads which have sufficient dedicated right-of-way.

b. Payment for design, materials, blasting. The customer will be required to pay to the authority, prior to the commencement of construction, an amount sufficient to pay for all costs associated with design and materials that are required to build the proposed line and to extend the authority's water main from the existing water main which has sufficient size to service the proposed line.

The cost of the project will be determined by the authority. The authority will provide an initial estimate of cost to the interested parties at no charge. It is immaterial whether the costs for the line are shared equally by the customers or whether one or more property owners or customers pays for the water line extension.

In the event that it becomes apparent to the authority that construction of said line will cost more than the original estimated cost, the authority may terminate work until such time as adequate funds have been placed with the authority.

(2) Authority consideration. The authority's board of directors will consider an application from an existing development, or group of owners of existing development, when the following are provided:

a. Documentation of sufficient right of way and/or easements as required by the county and the authority.

b. A petition of property owners to be served with the signature of all participants, the number of connections to be made for each participant, and an indication of the cost to be borne by each participant.

c. Deposit of the estimated funds for design, materials, and any anticipated blasting.

d. Deposit of the required connection fees for individual customers.

If the request is approved by the authority board, an estimated date of completion will be given to the customer, but a date of completion cannot be guaranteed because of changes in work schedule, weather conditions, equipment breakdown, delays in delivery of materials, improvement of the right of way, or other unpredictable circumstances.

(3) Ownership of lines. All water lines built will become the property of the authority.

(4) Unused funds. Any unused funds provided by the property owners for line construction will be reimbursed by the authority upon completion of construction.

(d) Water line extensions to serve new residential, commercial, and industrial development.

(1) Developer responsible for all costs of extension. This section applies inside new residential subdivisions, industrial sites, and commercial sites and to necessary extensions along existing public roads to reach those sites.

The owner of any new development will be required to pay for labor, materials, design and all other costs of water line extension. At the option of the authority, construction of extensions to and within new development may be done by the authority or by a qualified contractor working for the developer. In any case, line construction must adhere strictly to adopted authority specifications.

(2) Authority consideration. Extensions to new development will be considered under the following conditions:

a. Sufficient dedicated right-of-way must be available along public roads required to access the development.

b. The developer must provide a letter from the Butts County Community Services Department that the property has been approved for the proposed use according to the zoning and development regulations of Butts County.

c. The developer must provide the authority with three (3) copies of a plat or accurate drawing of the property to be served at a format and scale that meets the authority's specifications. Said plats or drawings shall contain the following information:

1. Location of the closest existing water line of the authority which is of sufficient size to serve the property;

2. Location of the existing and proposed roads to serve the property;

3. Exact size, material, and footage of water line that will have to be installed in order to serve the property;

4. Location of all water lines and appurtenances to be constructed in the area to be developed; and

5. Documentation that lines and appurtenances have been sized to meet the specifications the county and the authority for customer demand and fire flows.

d. The developer must document financial ability to pay the cost of construction. If the construction will be provided by the authority, the total cost of the project, as estimated by the authority, must be paid to the authority.

A letter of credit signed by the president of an accredited bank in the State of Georgia will be acceptable in lieu of cash. In the event that it becomes apparent to the authority that construction of said lines will cost more than the original estimated cost, the authority may terminate work until such time as adequate funds have been placed with the authority, or a revised letter of credit with an adequate figure is received.

(3) Construction by authority. Water lines will only be placed within easements established for such purposes, or within right of way lines of streets and roads which have been certified as being part of the public road system of Butts County. An estimated date of completion cannot be guaranteed because of changes in work schedule, weather conditions, equipment breakdown, delays in delivery of materials, improvement of the right of way, or other unpredictable circumstances.

All water lines built are the property of the authority.

Any unused funds deposited by the Developer for the line construction will be reimbursed by the authority upon commencement of water services.

(4) Construction by developer. Lines will normally be allowed to be constructed by the Developer only within the development itself.

During construction, the authority will inspect work as necessary.

Upon completion of construction by the developer, but prior to the initiation of water service the following must be done:

a. The authority will conduct tests to ensure that completed water lines meet authority specifications for pressure, flow and water quality.

b. The developer must post a deed conveying the water line, appurtenances thereto, and any required permanent easements to the authority.

c. The developer must post a surety bond, or a letter of credit from any banking institution within the State of Georgia, with the authority in the amount of ten percent (10%) of the total cost of the construction of said line, which said bond, or letter of credit, shall guarantee payment to the authority for any repairs or maintenance needed in said line over a period of one (1) year from the date of conveyance of said line. The authority will conduct a final comprehensive inspection of the water infrastructure once the facility has been in service between eleven (11) and twelve (12) months. The developer will be responsible for any corrections and listed noted through that time.

d. The developer must furnish three (3) copies of as-built water lines and appurtenances in the size and format specified by the authority.

e. The developer must execute an affidavit prescribed by the authority stating that the cost of all labor and materials has been paid accompanied by copies of all invoices.

(e) Construction by municipalities or other water utilities in unincorporated Butts County.

(1) Approval. Water line construction by municipalities or other water utilities within unincorporated Butts County must adhere strictly to adopted authority specifications and must be approved by the authority's board of directors prior to construction.

In cases of such extensions, the developer of said extensions must provide the authority with three (3) copies of a plat or accurate drawing of the property to be served. Said plats or drawings shall contain the following information:

a. Location of the closest existing water line of the authority which is of sufficient size to serve the property;

b. Location of the existing and proposed roads to serve the property;

c. Exact size, material, and footage of water line that will have to be installed in order to serve the property;

d. Location of all water lines and appurtenances to be constructed in the area to be developed; and

e. Documentation that lines and appurtenances have been sized to meet the specifications the county and the authority for customer demand and fire flows.

The authority is authorized to assess a fee for plan approval.

(2) As-Built documentation. Upon completion of construction, but prior to the initiation of water service, documentation that the extension has been tested for pressure, flow, and water quality must be provided to the authority.

The municipality installing water infrastructure in unincorporated Butts County must furnish three (3) copies of as-built water lines and appurtenances in the size and format specified by the authority.

(f) Permit from Butts County board of commissioners. A permit, or easement, from the Butts County Board of Commissioners is required for water line installation along county rights of way. Said permit, or easement, may be granted for such installation only after approval of construction plans by the authority.

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.