Sec. 18-16. Inspections and occupancy.
Sobre este texto
- As published by Municode, current through 2025-05-06
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Inspections.
(1) Existing building inspections. Before issuing a permit the building official may examine or cause to be examined any building, electrical, gas, mechanical or plumbing systems for which an application has been received for a permit to enlarge, alter, repair, move, demolish, install, or change the occupancy. He shall inspect all buildings, structures, electrical, gas, mechanical and plumbing systems, from time to time, during and upon completion of the work for which a permit was issued. He shall make a record of every such examination and inspection and of all violations of the construction codes.
(2) Manufacturers and fabricators. When deemed necessary by the building official he shall make, or cause to be made, an inspection of materials or assemblies at the point of manufacture or fabrication. A record may be made of every such examination and inspection and of all violations of the construction codes.
(3) Inspection service. The building official may make, or cause to be made, the inspections required by subsection (a)(6). He/she may accept reports of inspectors of recognized inspection services provided that after investigation he/she is satisfied as to their qualifications and reliability in accordance with state law. A certificate called for by any provision of the construction codes shall not be based on such reports unless the same are in writing and certified by a responsible officer of such service.
(4) Inspections prior to issuance of certificate of occupancy or completion. The building official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building, structure, electrical, gas, mechanical or plumbing system upon completion, prior to the issuance of the certificate of occupancy or completion.
(5) Posting of permit and address. Work requiring a permit shall not commence until the permit holder or his/her agent posts the permit card in a conspicuous location on the premises, visible from the street or road. The permit may be located away from the street or road provided that the address assigned to the premises is permanently posted at the street or road. The permit shall be protected from the weather and placed in such position as to allow the required entries to be made conveniently by the building department representative. The permit holder shall maintain the permit card in such position until such time as work has been completed and the building official has granted final inspection approval.
(6) Required inspections. The building official upon notification from the permit holder or his/her agent shall make the following minimum required inspections, and shall either release that portion of the construction or shall notify the permit holder or his/her agent of any violations which must be corrected in order to comply with the construction codes.
a. Building.
1. Foundation inspection: To be made after (a) trenches are excavated and forms erected or (b) trenches are excavated or forms erected.
2. Frame inspection: To be made after the roof, all framing, fireblocking and bracing are in place, all wiring, all pipes, chimneys, ducts and vents that are to be concealed, are complete.
3. Final inspection: To be made after the building is completed and ready for occupancy.
b. Electrical.
1. Underground inspection: To be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.
2. Rough-in inspection: To be made after the roof, framing, fireblocking and bracing is in place and prior to the installation of wall or ceiling membranes.
3. Final inspection: To be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.
c. Plumbing.
1. Underground inspection: To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place.
2. Rough-in inspection: To be made after the roof, framing, fireblocking and bracing is in place and all soil, waste, vent and supply piping is complete, and prior to the installation of wall or ceiling membranes.
3. Final inspection: To be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.
Note: Reference the Standard Plumbing Code for required tests of soil, waste, vent and supply piping.
d. Mechanical.
1. Underground inspection: To be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.
2. Rough-in inspection: To be made after the roof, framing, fire blocking and bracing are in place and all ducting, and other concealed components are complete, and prior to the installation of wall or ceiling membranes.
3. Final inspection: To be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy.
e. Gas
1. Rough piping inspection: To be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.
2. Final piping inspection: To be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.
3. Final inspection: To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, in order to insure compliance with all the requirements of the construction codes and to assure that the installation and construction of the gas system is in accordance with reviewed plans.
f. Energy
1. Foundation inspection: To be made before slab concrete is poured in place. To verify that perimeter insulation has been installed correctly on any slab on grade foundations, if required.
2. Frame inspection: To be made before exterior wall insulation is concealed by wall board to check installation of exterior walls insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner as to restrict air passage.
3. Final inspection: To be made after the building is completed and ready for occupancy. To verify installation and R-value of ceiling and floor insulation.
To verify correct SEER ratings on appliances.
(7) Other inspections. In addition to the inspection specified as minimum, the building official is authorized to make or require other inspections of any construction, system, component, assembly, fabrication, application, modification, site or premises to ascertain compliance with the provisions of the construction codes or other laws and regulations that are enforced by the building section of the community development department.
(8) Inspection requests. It shall be the duty of the holder of any permit or their duly authorized agent to ensure to the best of their ability that the work conforms to all applicable codes and to notify the building official when the work is ready for inspection. It shall be the duty of the permit holder to provide reasonable access to any structure and/or premises where inspections are required, and to maintain such access until final approval has been made.
(9) Written release. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official. The building official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or shall notify the permit holder or an agent of the permit holder wherein the same fails to comply with any of the construction codes. Any portions shall not be covered or concealed until approved by the building official.
(10) Reinforcing steel, structural frames, insulation, plumbing, mechanical, or electrical systems. Reinforcing steel, structural frame, insulation, service systems, work of any part of any building or structure shall not be covered or concealed without first obtaining a release from the building official.
(11) Plaster fire protection. In all buildings where plaster is used for fire protection purposes, the permit holder or his/her agent shall notify the building official after all lathing and backing is in place. Plaster shall not be applied until the release from the building official has been received.
(b) Certificates.
(1) Certificate of occupancy.
a. Building occupancy. A building, or part thereof, shall not be occupied or used unless the building official has issued a certificate of occupancy. Said certificate shall not be issued until all required electrical, gas, mechanical, plumbing and fire protection systems have been inspected for compliance with the construction codes and other applicable laws and ordinances and approved and released by the building official.
b. Issuing certificate of occupancy. Upon satisfactory completion of construction of a building or structure and installation of electrical, gas, mechanical and plumbing systems in accordance with the construction codes and all other applicable laws and ordinances, reviewed plans and specifications, and after the final inspections have been approved by the required local and/or state agencies, and after the final inspection, the building official shall issue a certificate of occupancy stating the nature of the occupancy permitted, the number of persons for each floor when limited by law, and the allowable load per square foot for each floor in accordance with the provisions of the construction codes.
c. Change of occupancy. If the occupancy of any existing building or structure is changed, the building, electrical, gas, mechanical and plumbing systems shall be made to conform to the intent of the construction codes as required by the building official. If the occupancy or use of the structure is changed, the owner, occupier, or tenant shall be required to comply with the zoning regulations and other applicable county ordinances.
(2) Certificate of completion—Required for utility connection. Upon satisfactory completion of a building, structure, electrical, gas, mechanical or plumbing system, and all other applicable laws and ordinances, a certificate of completion may be issued. This certificate is proof that a structure or system is complete for certain types of permits and released for use so that connection may be made to a utility system. This certificate does not grant authority to occupy or connect a building, such as a shell building, prior to the issuance of a certificate of occupancy.
(3) Certificate of completion for telecommunications structure. Upon the completion of all construction activities and prior to the authorized operation of the telecommunications structure, a compliance inspection(s) of the premise, grounds, and structure shall demonstrate that permittee has satisfied all requirements of the telecommunications ordinance. As-built drawing shall be submitted if requested. If compliance is demonstrated, the building official shall issue a certificate of completion to the authorized representative and the telecommunications structure may be operated as designed.
For purpose of this section, a final inspection may be considered as a certificate of completion.
(4) Service utilities.
a. Connection of service utilities. No person shall make connections from a utility, source of energy, fuel or power to any building or system that is regulated by the construction codes for which a permit is required, until released by the building official and a certificate of occupancy or completion is issued.
b. Temporary connection. The building official may authorize the temporary connection of the building or system to the utility source of energy, fuel or power for the purpose of testing building service systems.
c. Authority to disconnect service utilities. The building official shall have the power to authorize disconnection of utility service to the building, structure or service system regulated by the construction codes, in case of emergency where necessary to eliminate an immediate hazard to life or property. The building official shall notify the serving utility, and whenever possible the owner and occupant of the building, structure or service system of the decision to disconnect prior to taking such action. If not notified prior to disconnecting, the owner or occupant of the building, structure or service system shall be notified in writing, as soon as practical thereafter.
(c) Posting floor loads.
(1) Occupancy. An existing or new building shall not be occupied for any purpose, which will cause the floors thereof to be loaded beyond their safe capacity. The building official, or another appropriate agency, may permit occupancy of a building for mercantile, commercial or industrial purposes, by a specific business, when he/she is satisfied that such capacity will not thereby be exceeded.
(2) Storage and factory-industrial occupancies. It shall be the responsibility of the owner, agent, proprietor or occupant of group S (storage) and group F (factory) occupancies, or any occupancy where excessive floor loading is likely to occur, to employ a competent architect or engineer in computing the safe load capacity. All such computations shall be accompanied by an affidavit from the architect or engineer stating the safe allowable floor load on each floor in pounds per square foot uniformly distributed. The computations and affidavit shall be filed as a permanent record of the building department.
(3) Signs required. In every building or part of a building used for storage, industrial or hazardous purposes, the safe floor loads, as reviewed by the building official on the plan, shall be marked on plates of approved design which shall be supplied and securely affixed by the owner of the building in a conspicuous place in each story to which they relate. Such plates shall not be removed or defaced, and if lost, removed or defaced, shall be replaced by the owner of the building.
(d) Tests. The building official may require tests or test reports as proof of compliance.
Required tests are to be made at the expense of the owner, or his agent, by an approved testing laboratory or other approved agency.
Historia
(Res./Ord. of 6-3-03, § 2)
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.