Sec. 86-172. Stormwater detention.

Sobre este texto

  • As published by Municode, current through 2025-05-06
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Stormwater management report required.

(1) Every project shall provide a stormwater management report prepared by professional engineer currently registered in the state. The purpose of this report shall be to formulate a plan to manage stormwater runoff so that stormwater runoff hazards are not created and existing runoff-related problems are not exacerbated, either upstream or downstream from or within the boundaries of the property being developed.

(2) The stormwater management report shall include a written narrative and shall identify the locations and quantities of stormwater runoff entering and exiting the site for both pre- and post-developed conditions. Analysis of the off-site properties shall anticipate future development in addition to addressing existing conditions. The report shall include a detailed summary statement of the increase or decrease in flow or runoff on adjacent properties and downstream drainageways. It shall contain drainage area delineation maps and other exhibits at satisfactory scale and sufficient in quantity and slope to define the boundaries of the site relative to watercourses, drainage divides, drainage structures, and other pertinent features.

(3) The analysis of downstream conditions in the report shall address each and every point or area along the project site's boundaries at which runoff will exit the property. The analysis shall focus on the portion of the drainageway "immediately" downstream from the project. This area shall generally extend a flow distance of about one-half mile from the project's boundary line, but shall be longer for projects contributing relatively large amounts of runoff to the study area, and shorter for small runoff contributions. In all cases, the most critical downstream area investigation shall be conducted relative to existing and anticipated land use on tracts that adjoin the project site.

(b) Stormwater detention required.

(1) If the stormwater management report indicates that adverse stormwater runoff is expected to result from the development of a property, that project shall be required to provide stormwater detention facilities. These detention facilities shall be designed so that their peak release rates, when combined with those of all detention bypass areas in the same basin, produce peak flow rates and flow velocities at the site's boundary line no greater than those which occurred at the same location for pre-developed conditions.

(2) The following criteria shall be evaluated by the engineer preparing the stormwater management report, and in determining whether or not detention should be required for any portion of any site:

a. Existing land uses downstream.

b. Anticipated future land uses downstream.

c. Magnitude of increase in peak flows due to development.

d. Presence of existing drainage problems.

e. Capacity of existing and anticipated drainage systems.

f. Creation of concentrated flows where none had occurred previously.

g. Availability of feasible locations for detention facilities.

h. Existing flows generated off-site that pass through the project site.

i. Anticipated future flows generated off-site that pass through the project site.

j. The nature of the receiving watercourse.

(3) Stormwater detention facilities shall be required for any portion of any site for which development activities will result in increased flows, unless the registered professional engineer currently registered in the state certifies and provides documentation supporting the conclusion to the engineer that the following is true and correct as applicable:

a. The nondetained, postdevelopment runoff will leave the project site as sheet flow, and will not have an adverse impact upon downstream properties.

b. The effect of detention would be to concentrate flows where sheet flow had occurred under pre-developed conditions, and any impact of increase sheet flows upon downstream properties would be less adverse than that which would result from the concentrated flows from a detention facility even if energy dissipation devices were employed.

c. The runoff will flow directly into a floodplain without crossing off-site properties, and the runoff will constitute less than five percent of the total runoff in the watercourse at the point where the watercourse crosses the project site's downstream property line.

d. The undetained flow will pass through downstream properties, in drainage easements obtained by the developer, to an existing detention facility that has been designed to manage the additional upstream property's runoff.

(c) Detention design criteria—General.

(1) All stormwater detention design calculations shall be certified by a professional engineer currently registered in the state.

(2) All stormwater detention facilities shall be designed to control the peak flow rates associated with storms having two-, ten-, 25-, 50- and 100-year return frequencies.

(3) A variety of methods of achieving stormwater management goals shall be acceptable in providing detention facilities. The type of facility provided shall be based on the following criteria:

a. The type of development for which the detention facility is being provided.

b. The type of development which the detention facility is intended to protect.

c. Volume of stormwater to be stored.

d. Origin and magnitude of the flows to be managed.

e. Topographic opportunities and limitations.

f. Safety considerations.

g. Maintenance requirements.

h. Aesthetic considerations.

i. Likelihood of facility operation interfering with access to public or private facilities.

j. Proximity of facility to property lines, utilities, buffers, etc.

k. Similar site-specific constraints.

(4) Detention facilities may be of any of the following types, and two or more types may be used in combination with one another:

a. Normally-dry basins, whether excavated or created by damming a natural drainage feature, or a combination of both methods.

b. Lakes and ponds, whether excavated or created by damming a natural drainage feature, or a combination of both methods.

c. Other types of facilities shall be approved by the community development department.

(5) Reservoir routing methods shall be used for all detention facility design.

(6) The detention methodology required for any given project shall conform to standard engineering practices. It shall be the responsibility of the design engineer to use the correct coefficients and applications that will result in compliance with the requirements of this article and the intent of these regulations.

(7) Runoff coefficients used for pre-and post-development conditions for the rational methods shall be consistent with standard engineering practices. For the SCS method the runoff curve numbers found in the "Manual for Erosion and Sediment Control in Georgia" shall be used. For any stormwater analysis, the composite "C" (rational method) or CN (SCS method) used for predeveloped conditions shall not exceed 0.3 or 66, respectively, unless prior approval has been obtained through the department.

(8) If either the rational method or the SCS method is used for detention design, calculations shall be provided showing how all times of concentration or lag times were computed, both for pre- and postdevelopment conditions. Likewise, adequate support must be provided for all composite runoff coefficients or curve numbers used.

(9) If a computer program is used for detention design, including generation and routing hydrographs, the output from the program shall be summarized in the stormwater management report, and the name and version of the program shall be indicated.

Computer output sheets may be attached to the report if desired by the design engineer or if requested by the development department.

(10) The design of every detention facility of any type shall consider the effects both of inflows in excess of those the facility is designed to accommodate and of malfunctioning of the primary outlet system. A safe path for overflow condition flows shall be provided.

(d) Detention facility location criteria.

(1) Residential detention facilities shall be located outside the boundaries of a permitted building lot. Access shall be provided via a graded and grassed roadway not less than 12 feet wide and minimum grade practical within a 25-foot wide deeded property strip.

Access shall not occur on any permittable building lot.

(2) For purposes of these regulations, a detention facility shall be deemed to consist of the area within the maximum design ponding limits, the dam (if one) including all embankment slopes and wall footings (if applicable), primary and emergency outlet works, any drainage and access easements, and any energy dissipation devices.

(3) Detention facilities, to the greatest extent feasible, shall be located so as to minimize the amount of flow generated on-site that bypasses the facility.

(4) No portion of any detention facility shall disturb any required buffer, landscape strip, or tree protection area.

(5) The 100-year ponding limits of a detention facility shall not encroach upon a neighboring lot.

(6) Detention facilities may encroach upon utility easements or rights-of-way, upon receipt by the engineer of written permission from both the property and utility owners.

(e) Residential detention facility access requirements. Deeded property at least 25 feet in width shall be required to provide access to all residential detention facilities from a public street. This access shall be cleared, grubbed and/or graded so that it can be utilized by rubber-tired construction vehicles. Its location shall be as to minimize the amount of grading required.

(f) Residential detention facility maintenance.

(1) The detention storage capacity or function of any detention basin, pond or other impoundment, whether natural or man-made, shall not be removed or diminished without the express approval of the board of commissioners.

(2) A homeowner's association is required to be established prior to final plat approval. All residential detention facilities shall become the responsibility of the homeowner's association or the owner/developer for maintenance upon the county's approval of the final plat and the detention facility engineers certification and record (as-built) drawings.

(3) In his discretion, the director may consider another entity other than a home owner's association to be responsible for maintenance of the detention facility.

(g) Detention facility construction standards.

(1) Stormwater detention facilities shall be constructed in accordance with plans reviewed and approved by the engineer, and shall be in place and inspected prior to the initiation of other improvements. If the detention facility is planned to be a lake, temporary detention facilities shall be provided and shall remain in place until such time as the lake has become effective in providing stormwater management.

(2) Within a detention basin, all stumps are to be cut flush with the ground or removed and all debris is to be removed below the ten-year ponding elevation. Trees or shrubs may be allowed to remain below the ten-year ponding elevation only upon certification of the survivability of the vegetation.

(3) Detention slopes that are disturbed are to be grassed and the ground cover within the basin shall be well established with all exposed areas covered prior to the end of the maintenance period. All sloped shall be 3:1 maximum.

(4) If the developer desires to place a fence around a detention facility, it shall be a minimum six-foot high fence of durable material, with a 12-foot wide access gate.

Fencing may be required by the development department for hazardous detention ponds.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 10-16-01, § 1; Ord. of 1-6-15, § 1)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:carroll-county/code/86-172@2025-05-06-ffbc4a1233

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Carroll County Code of Ordinances, Sec. 86-172. Stormwater detention | Georgia Commons