Sec. 50-76. Application; plan requirements; permit process.

Sobre este texto

  • As published by Municode, current through 2025-11-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) General. The property owner, developer and designated planners and engineers shall design and review before submittal the general development plans.

Cobb County shall review the tract to be developed and the area surrounding it. They shall consult the zoning ordinance, storm water management ordinance, subdivision ordinance, flood damage prevention

ordinance, this article, and any other ordinances, rules, regulations or permits, which regulate the development of land within the jurisdictional boundaries of Cobb County. However, the owner and/or operator are the only parties who may obtain a permit.

(b) Application requirements.

(1) No person shall conduct any land disturbing activity within the confines of the

unincorporated areas of Cobb County without first obtaining a permit, where required, from the Cobb County Community Development Agency to perform such activity and providing a copy of the notice of intent submitted to the Georgia EPD, if applicable. A land

disturbance permit for clearing and grading projects may only be obtained if such projects are part of a complete site/project plan review and approval (allowing for clearing and grading only phases, including a time table for final completion). Any clearing and grading

activities permitted under this section shall comply with the provisions found in article III, section 50-75 of this chapter. In no event shall any portion of this article be interpreted in any manner to reduce or diminish the use

or density of any project where the county board of commissioners has approved such use or density.

(2) The application for a land disturbance permit shall be submitted to the Cobb County Community Development Agency and must include the applicant's erosion, sedimentation and

pollution control plan with supporting data, as necessary. Said plans shall include, as a minimum, the data specified in subsection (c) of this section. Erosion, sedimentation and pollution control plans, together with supporting data, must demonstrate affirmatively that the land disturbing activity proposed will be

carried out in such a manner that the provisions of section 50-75 of this article will be met. Applications for a permit will not be

accepted unless accompanied by a copy of the applicant's erosion, sedimentation and pollution control plans and by such supportive data as will affirmatively demonstrate that

the land-disturbing activity proposed will be carried out in such a manner that the minimum requirements shall be met. Maps, drawings and supportive computations shall bear the signature and seal of the certified design professional. All applications shall contain a certification stating that the plan preparer or the designee thereof visited the site prior to

creation of the plan in accordance with EPD Rule 391-3-7-.10.

(3) In addition to the local permitting fees, fees will also be assessed pursuant to paragraph

(5) subsection (a) of O.C.G.A. 12-5-23, provided that such fees shall not exceed $80.00 per

acre of land-disturbing activity, and these fees shall be calculated and paid by the primary permittee as defined in the state general permit for each acre of land-disturbing activity included in the planned development or each phase of development. All applicable fees shall be paid prior to issuance of the land disturbance permit. Per subsection (a) of O.C.G.A. 12-7-8 half of such fees levied shall be submitted to the Division;

except that any and all fees due from an entity which is required to give notice pursuant to paragraph (9) or (10) of O.C.G.A.

12-7-17 shall be submitted in full to the Division, regardless of the existence of a local issuing authority in the jurisdiction.

(4) If a permit applicant has had two or more violations of previous permits, this section, or the Erosion and Sedimentation Act, as

amended, within three years prior to the date of filing the application under consideration, Cobb County may deny the permit application.

(5) Cobb County may require the permit applicant to post a bond in the form of government

security, cash, irrevocable letter of credit, or any combination thereof up to, but not exceeding, $3,000.00 per acre or fraction thereof of the proposed land-disturbing activity, prior to issuing the permit. If the applicant does not

comply with this section or with the conditions of the permit after issuance, Cobb County may call the bond or any part thereof to be

forfeited and may use the proceeds to hire a contractor to stabilize the site.

(c) Plan requirement.

(1) Standards and specifications. Plans for land disturbing activities shall contain soil erosion and sedimentation control measures and

practices which conform to the publication entitled Manual for Erosion Control in Georgia or through the use of more stringent, alternate design criteria which conform to sound

conservation and engineering practices which is on file in the office of the issuing authority.

The publication is hereby incorporated by reference in this article. The plan for the land disturbing activity shall consider the interrelationship of the soil types, geological, and hydrological characteristics, topography,

watershed, vegetation, proposed permanent structures including roadways, constructed waterways, sediment control and stormwater management facilities, local ordinances, and state laws.

(2) Data Required for Site Plan shall include all the information required from the appropriate Erosion, Sedimentation and Pollution Control Plan Review Checklist established by

the Commission as of January 1 of the year in which the applicable land-disturbing activity was permitted.

(3) Maintenance.

a. Maintenance of all soil erosion and sedimentation control practices, whether temporary or permanent, shall be at all times the responsibility of the owner. It shall be the responsibility of the owner or his/her designee to post a maintenance log on site at all times. Said log will be posted on site with the land disturbance permit from the issuing authority. Said log must also be initialed on a weekly basis by the owner or his/her designee to indicate compliance with best management practices and the approved maintenance schedule.

b. All plans must contain the following maintenance statement: "Erosion control measures will be maintained at all times.

If full implementation of the approved plan does not provide for effective erosion and sediment control, additional erosion and sedimentation control

measures will be installed if deemed necessary by on-site inspection. On-site inspectors may add items to plans as necessary. On-site inspectors may delete items from plans subject to approval by the director of Cobb County Community Development or his/her designee."

(4) Permits.

a. Permits issuance or denial. A permit is issued after Cobb County has determined that the plan for erosion and sedimentation control complies with the requirements of section 50-75, and after Cobb County has affirmatively determined

that the plan complies with all other development ordinances, rules and regulations in effect within the unincorporated areas of the county.

Permits will be issued or denied as soon as practical after the permit is filed with Cobb County, but in any event not later than 45 days after receipt by Cobb County of a completed application;

providing variances and bonding are obtained, where necessary and all applicable fees have been paid prior to permit issuance. The permit shall include conditions under which the activity may be undertaken. If the permit is denied, the reasons for the denial shall be furnished to the applicant.

b. No permit shall be issued unless Cobb County has affirmatively determined that the plan is in compliance with this ordinance, any variances required by section 50-75(c)(15), (16) and (17) are obtained, bonding requirements, if necessary, as per 50-76(b)(6) are met and all ordinances and rules and regulations in

effect within the jurisdictional boundaries of Cobb County are met.

c. Any land-disturbing activities by a local issuing authority shall be subject to the same requirements of this ordinance, and any other ordinances relating to land development, as are applied to private persons and the division shall enforce such requirements upon the local issuing authority.

d. Staged developments. If the tract is to be developed in stages, then a separate permit shall be required for each phase.

e. Responsibility. Neither the issuance of the permit nor compliance with the conditions thereof, nor with the provisions of this article, shall relieve any person of any responsibility otherwise

imposed by law for damage of persons or property; nor shall the issuance of any permit pursuant to this article serve to impose any liability upon the county, its officers, board members or employees, for injury or damage to persons or property. The permit issued pursuant to this article does not relieve the applicant of the responsibility of complying with any other county ordinance or state law.

f. Special conditions. A permit issued by Cobb County shall specify any special conditions under which the land disturbing permit may be undertaken.

g. The permit may be suspended, revoked, or modified by the Local Issuing Authority ("LIA"), as to all or any portion of the land affected by the plan, upon finding

that the holder or his successor in the title is not in compliance with the approved erosion and sedimentation control plan or that the holder or his successor in title is in violation of this ordinance. A holder of a permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the permit.

h. The LIA may reject a permit application if the applicant has had two or more violations of previous permits or the Erosion and Sedimentation Act permit requirements within three years prior to the date of the application, pursuant to O.C.G.A. § 12-7-7(f)(1).

(Ord. of 3-27-90; Code 1977, § 3-6-111; Ord. of 11-14- 95; Ord. of 7-27-99 (eff. 10-1-99); Ord. of 1-25-00; Ord.

of 1-23-01; Ord. of 4-13-04; Ord. of 2-27-07; Amd. of 2-23-10; Amd. of 2-9-21; Amd. of 2-8-22; Amd. of 10-24-23; Amd. of 11-21-24)

Reuniones que se refieren a esta sección

Encontradas: 1. Son reuniones de este gobierno cuyas actas o transcripciones automáticas nombran esta sección, o una ordenanza de su línea de historia, de la más reciente a la más antigua. Halladas por regla a partir de las propias palabras de esos registros. Una referencia es un enlace a otro registro, no una afirmación de que la sección se aplica o se cambió.

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:cobb-county/code/50-76@2025-11-20-9975804e87

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.