Part II - CODE / Chapter 34 - OFFENSES AND MISCELLANEOUS PROVISIONS / Article VI - BROADBAND NETWORK PROJECTS
Sec. 34-105. Approval or denial notification.
Sobre este texto
- As published by Municode, current through 2024-09-05
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
If, on or before the 11th day as described in subsection 34-103(b), an application is deemed complete, the county shall approve or deny an application within ten (10) calendar days unless a joint meeting between the applicant and the county is deemed as necessary.
(1) If a joint meeting is deemed necessary, the joint meeting must occur within fifteen (15) calendars days of notification of completion and the joint meeting shall include:
a. Where applicant is going to conduct work;
b. When the work will be conducted;
c. What type of work will be done;
d. Who the county can contact for specific details or related questions; and
e. Any permit seeking approval under application.
f. Following the joint meeting, the county shall deny or approve the application within ten (10) calendar days.
(2) Upon final approval, any required permit permitted shall be deemed issued.
Historia
(Ord. No. 04-04-19, § II, 4-4-2019)