Sec. 22-83. Permitting, inspection, certificate of occupancy and fees.

Sobre este texto

  • As published by Municode, current through 2022-11-07
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A permit shall be required to locate a pre-owned manufactured home in the jurisdiction. All permits shall be issued within three days of receipt of all items listed in subsection (1)a through d of this section.

(1) Permit. To obtain a permit, applicants shall provide to the building inspector:

a. An affidavit signed by the applicant that the pre-owned manufactured home meets health and safety standards required by the Act;

b. Photographs of the interior and exterior of the pre-owned manufactured home providing evidence that home meets the minimum health and safety standards of section 22-84;

c. A $300.00 refundable cash deposit;

d. The permit and inspection fee required by subsection (4) of this section;

e. A copy of the bill of sale or title evidencing title in the applicant.

(2) Inspection. Upon receipt of a permit, the applicant may relocate the manufactured home on a residential site for the purposes of inspection. The applicant shall arrange for an inspection to be held once the installation of the manufactured home is complete.

(3) Certificate of occupancy. A certificate of occupancy shall be issued to the applicant at such time that the building inspector certifies that the requirements of this article have been met.

(4) Fee. A permit and inspection fee in an amount provided and on file in the county clerk's office shall be charged to the applicant to cover the cost to the county to process the permit application and inspect the pre-owned manufactured home. Such fee shall cover the initial inspection and one follow-up inspection. The applicant shall be charged a fee in an amount provided and on file in the county clerk's office for each additional follow-up inspection that may be necessary.

(5) Alternative inspection. At the request of the applicant, the building inspector may, at his discretion, inspect a pre-owned manufactured home prior to its being relocated if the home is then located at another site within the county.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Code 1996, § 36-27; Ord. of 10-6-1997, § 2-2; Res. of 3-7-2005; Res. of 10-1-2007, § 1; Res. of 11-1-2010, § 3)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:early-county/code/22-83@2022-11-07-85b33f530e

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Early County Code of Ordinances, Sec. 22-83. Permitting, inspection, certificate of occupancy and fees | Georgia Commons