Section 123. Procedure for preliminary plat approval.

Sobre este texto

  • As published by Municode, current through 2026-01-16
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Prior to the cutting or grading of any street or the making of any street improvements or the installation of utilities, the subdivider shall submit to the commission a preliminary plat of the proposed subdivision in accordance with the following procedures:

123.1. Application for preliminary plat approval. Following the pre-application review of a proposed subdivision, the subdivider shall submit to the zoning enforcement officer a complete application for review and approval of a preliminary plat.

123.11. If the property being subdivided does not abut any part of the state highway system, the subdivider shall submit to the zoning enforcement officer an application for approval of preliminary plat, and four copies of the preliminary plat and other documents, as specified in section 124 herein. The planning and zoning commission shall act on the preliminary plat at its next regular meeting no less than ten calendar days from the date of receipt of a complete application by the zoning enforcement officer.

123.12. If the property being subdivided abuts any part of the state highway system, the subdivider shall submit to the zoning enforcement officer an application for approval of preliminary plat and seven copies of the preliminary plat and other documents, as specified in section 124 herein. The zoning enforcement officer shall forward three copies of the preliminary plat and other documents to the Georgia Department of Transportation District Office for review and approval, or disapproval, in accordance with the O.C.G.A. § 32-6-151. The commission shall act on the preliminary plat at its next regular meeting no less than ten calendar days from the date of receipt of a complete application by the zoning enforcement officer, or at the next regular meeting of the planning and zoning commission no less than ten calendar days from the date of receipt of the decision of the Georgia Department of Transportation by the zoning enforcement officer, whichever is later. Applications for preliminary plat approval for subdivisions of property abutting the state highway system that do not include all of the above items shall not be considered complete. Approval of a subdivision plat does not relieve the subdivider of the requirement to obtain a commercial driveway permit from the Georgia Department of Transportation.

123.2. Georgia Department of Transportation recommendation. In accordance with O.C.G.A.

§ 32-6-151, the zoning enforcement officer shall submit three copies of the preliminary plat to the Georgia Department of Transportation if the proposed subdivision includes or abuts on any part of the state highway system. The Department of Transportation, within 30 days of receipt of the plat, shall recommend approval or disapproval and note its recommendation on the copy to be returned to the zoning enforcement officer.

Failure of the department of transportation to act within this 30-day period shall constitute a recommendation for approval. If the plat is recommended for disapproval, the reasons for disapproval and requirements for approval shall be given to the zoning enforcement officer in writing; but such recommendations shall be advisory only and shall not be binding on the planning and zoning commission. Approval of a subdivision plat does not relieve the subdivider of the requirement to obtain a commercial driveway permit from the Georgia Department of Transportation.

123.3. Notice of hearing. Notice of the time and place of hearing shall be sent via certified mail to the address of the subdivider not less than five days before the date fixed therefore. It shall be the responsibility of the zoning enforcement officer to send said notice.

123.4. Review of preliminary plat. The zoning enforcement officer shall check the plat for conformance to the rules and regulations of this resolution and report his findings and recommendations to the planning and zoning commission, which shall afford a hearing on the preliminary plat.

123.41. Preliminary approval. Following the hearing of the preliminary plat and other related material, the planning and zoning commission may express preliminary approval, noting the conditions of such approval on four copies of the preliminary plat, with one copy being returned to the subdivider, one copy to the Jones County Health Department, and one copy to the zoning enforcement officer for the board of commissioners, and one copy to be added to the records of the planning and zoning commission. Approval of a preliminary plat does not constitute approval of a final plat. It indicates only approval of the layout as a guide to the preparation of the final plat.

123.42. Expiration. Preliminary approval shall expire and be of no further effect 12 months from the date of the preliminary approval, unless the time is extended by the planning and zoning commission.

123.43. Disapproval. Following the hearing of the preliminary plat and other related material, the planning and zoning commission may find conditions detrimental to the public safety, health and general welfare, or in conflict with adopted plans of the planning and zoning commission which require the disapproval of the preliminary plat. A statement of the reasons for disapproval shall be made on two copies of the preliminary plat with one copy being returned to the subdivider and one copy being added to the records of the planning and zoning commission. The applicant may reapply for preliminary plat approval in accordance with section

123.1 herein.

123.44. Automatic approval. Failure of the commission to act on the preliminary plat within the time frame specified in section 123.1, without due cause, shall be deemed to be approval of the plat and a certificate of preliminary approval shall be issued by the planning and zoning commission on demand, provided, however, that the subdivider may waive this requirement and consent to an extension of time.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 201203-2o, 3-20-2012)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:jones-county/code/123@2026-01-16-aafb9b704b

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Jones County Code of Ordinances, Section 123. Procedure for preliminary plat approval | Georgia Commons