Jones County · Código de ordenanzas
Part II - CODE OF ORDINANCES / Chapter 87 - SOLAR ENERGY SYSTEMS
Sec. 87-6. General requirements for all ground mounted solar energy systems.
Sobre este texto
- As published by Municode, current through 2026-01-16
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) The following requirements apply to all Ground Mounted SESs, in addition to the specific requirements in this chapter that apply to Intermediate and Large Scale SESs respectively.
(1) Solar access. Consistent with O.C.G.A. § 44-9-20 et seq., a property owner may obtain a solar easement from another property owner for the purpose of ensuring a Ground Mounted SES adequate exposure to sunlight.
(2) Impervious surface. Ground mounted structures and components of the Ground Mounted SES, including transformers and foundations, shall be considered impervious. However, for purposes of compliance with the Jones County Comprehensive Land Development Resolution's impervious surface coverage requirements, the panels of a Ground Mounted SES shall be considered pervious if they maintain sheet flow and allow for water to infiltrate under and around them through a pervious surface and into the subsoil.
(3) Lighting. To reduce light pollution, lighting of a Ground Mounted SES shall: a) be limited to the minimum reasonably necessary for its safe operation; b) be directed downward where reasonably feasible; c) incorporate full cut-off fixtures; and d) reasonably utilize motion sensors.
(4) Tree removal. The removal of trees or natural vegetation for a Ground Mounted SES shall be avoided to the extent reasonably practicable and shall comply with the requirements of the Jones County Comprehensive Land Development Resolution.
(5) Decommissioning. Unless otherwise approved by the Board of Commissioners, decommissioning shall begin no later than 12 months after a Ground Mounted SES has ceased to generate electricity or thermal energy:
a. For a Ground Mounted SES allowed without a permit, within six months of the beginning of decommissioning, the SES and all structures associated with it shall be removed, all materials shall be recycled or otherwise reused to the extent reasonably practicable, and the property shall be returned to its condition prior to the installation of the SES or to some other condition reasonably appropriate for the designated land use; and
b. For a Ground Mounted SES allowed with a permit, the SES shall be decommissioned in accordance with the most recent decommissioning plan approved by the Board of Commissioners, and as further described in the Conditional Use Permit provision of this Resolution.
Historia
(Ord. of 10-6-2020)
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.