Lee County · Código de ordenanzas

Part II - CODE OF ORDINANCES / Chapter 28 - COMMUNICATIONS / Article II - STANDARDS FOR WIRELESS COMMUNICATION FACILITIES

Sec. 28-30. Development requirements for towers.

Sobre este texto

  • As published by Municode, current through 2026-06-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Towers may be located only in the following zoning districts subject to the restrictions and standards contained herein:

AG-1 Active Agricultural District C-1 Neighborhood Business District C-2 General Business District I-1 Light Industrial District I-2 Heavy Industrial District Wireless transmission facilities in any other zoning districts shall be accessory uses or alternative tower structures only; provided however, towers may be allowed on publicly owned property regardless of zoning district.

(b) Separation. Except in cases of co-location on the same tower or accessory structure, no wireless transmission facilities shall be located within 2,500 feet of any preexisting tower or preexisting antenna within the county unless such facility or preexisting tower or antenna is concealed through use of alternative tower structures or otherwise camouflaged in such a way that the presence of telecommunications equipment is virtually undetectable from any adjoining property.

(c) All applicants seeking to erect a tower must demonstrate that no existing tower or structure can accommodate the proposed antenna(s). Evidence of an engineering nature shall be documented by the submission of a certification by an engineer. Such evidence may consist of the following:

(1) No existing towers or structures are located within the geographic area required to meet applicant's engineering requirements.

(2) No existing structure is of sufficient height to meet the applicant's engineering requirements.

(3) No existing tower or structure has sufficient structural strength to support applicant's proposed antenna(s) and related equipment.

(4) Applicant's proposed antenna(s) would cause electromagnetic interference with the antenna(s) on the existing tower or structure.

(5) That the cost or contractual provisions required by the tower owner to share an existing tower or structure or to adapt an existing tower or structure for sharing are unreasonable. Costs exceeding new tower development are presumed to be unreasonable.

(6) Such other limiting factor(s) as may be demonstrated by the applicant.

All evidence submitted shall be signed and sealed by appropriate licensed professionals or qualified industry experts. Such evidence shall be subject to independent verification by an engineer of the county's choosing.

(d) Setbacks. Setbacks for towers and above-ground transmission facilities shall be as follows:

(1) All transmission facilities, except buried portions, shall be set back from all adjoining properties zoned non-residential the distance required for that zoning district.

(2) When a tower is adjacent to a residential use, the tower and entire transmission facility must be set back from the nearest residential lot line a distance equal to the height of the tower.

(3) Setbacks may be reduced, at the discretion of the planning and zoning department, to the fall radius of the tower as identified in a fall zone letter prepared by an engineer certified by the State of Georgia.

(e) Unless otherwise specified by the planning director or his/her designee, towers shall be enclosed by vinyl chain link security fencing or other approved alternative not less than six feet in height and shall be equipped with an appropriate anti-climbing device.

(f) All new towers in excess of 100 feet which do not incorporate alternative design features must be designed and built in a manner that allows other entities to co-locate on the structures using the following guidelines:

Maximum Telecommunications Tower Heights Zoning District Two Users Three Users Four Users AG-1 120' 200' 300' C-1, C-2 120' 150' 150' I-1, I-2 120' 150' 180'

(g) All towers and their related structures shall maximize the use of building materials, colors, textures, screening and landscaping that, in the opinion of the planning director or his/her designee, effectively blend the tower facilities within the surrounding natural setting and built environment. Where appropriate, towers shall be painted so as to reduce their visual obtrusiveness, subject to any applicable standards of the Federal Aviation Administration (FAA).

(h) If upon receipt of an application for the erection of any tower or alternative tower structure governed by this article, the planning director or his/her designee deems that the proposed structure may interfere with the use of the airways of the county by the public or interfere with the operation of existing or proposed airport facilities, a copy of the application shall be submitted by the planning and zoning department to the airport division of the department of transportation for review and recommendation.

(i) No application shall be approved unless written evidence is provided by the applicant that the Federal Aviation Administration (FAA) has made or issued a "Determination of No Hazard" with respect to the proposed tower.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 2-5-2001(2); Ord. of 9-15-2003(1); Ord. of 1-12-2021)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:lee-county/code/28-30@2026-06-23-3c32be3613

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.