Sec. 110-447. Design and installation; decommissioning.
Sobre este texto
- As published by Municode, current through 2015-12-01
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Utility scale solar farms and commercial scale solar farms, which are considered to be the principal use for property ranges in size from three acres and up, shall be considered the same for the purpose of this division.
(1) Design and installation.
a. All on-site utility and transmission lines shall, to the extent feasible, be placed underground.
b. All large solar energy production facilities shall be designed and located in order to prevent reflective glare toward any inhabited buildings on adjacent properties, as well as adjacent street rights-of-way.
c. A clearly visible warning sign concerning voltage must be placed at the base of all pad-mounted transformers and substations.
d. Use of public roads or state roads has been secured and approved for access points for project roads and parking areas for the site.
e. Liability insurance shall be maintained covering bodily injury and property damage with limits of at least $1,000,000.00 per occurrence and $1,000,000.00 in the aggregate.
(2) Decommissioning. The applicant agrees to the following conditions for a land use permit:
a. If the applicant ceases operation of the energy project or begins operations, but does not complete operations, the applicant shall restore the site according to a plan approved by the planning and zoning board;
b. The owner is required to notify the county immediately upon cessation or abandonment of the operation. The owner shall be responsible for the removal of the facility within six months from the date the applicant ceases use of the facility or the facility becomes obsolete. The owner will then have 12 months to dismantle/ remove all other components of the energy production facility.
c. Permit. At the time of issuance of a permit, the owner shall provide financial security in the form of a letter of credit in accordance with section 118-236 to secure the expense of dismantling and removing the structure.
d. Fees. No fees shall apply to an accessory structure; however, see fee schedule for large scale solar farms/arrays, commercial and/or utility scale and electrical inspection fees.
Historia
(Ord. of 2-3-2015, § 14.9)
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.