(a) Submittal of plans and documents.
(1) Constructions plans and documents, special inspection and structural observation programs, and other data shall be submitted in one or more sets with each application for a permit. The construction plans and documents shall be prepared by the applicant or a registered design professional as deemed necessary by the building official or required otherwise by any section of this Code. When the building official is unable to make a determination as to the grant or denial of a permit based upon the plans submitted with a permit application, the building official is authorized to require additional construction plans and documents to be prepared by the applicant or a registered design professional.
(2) The building official is authorized to waive in writing the submission of construction plans and documents and other data required to be prepared by a registered design professional if it is found that the nature of the work applied for is such that reviewing of construction plans and documents is not necessary to obtain compliance with this chapter. In addition, construction plans and documents for single-family residential construction do not have to be prepared by a registered design professional unless required by the building official in writing.
(b) Information on construction plans and documents. Construction plans and documents shall be dimensioned and drawn upon suitable material. Electronic media construction plans and documents are permitted to be submitted when approved by the building official. Construction plans and documents shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of this Code and all other applicable laws and regulations.
(c) Fire protection system shop drawings. Shop drawings for the fire protection system shall be submitted to indicate conformance with this chapter and the construction plans and documents and shall be approved by both the building official and the appropriate fire marshal prior to the start of system installation.
(d) Manufacturer's installation instructions for residential installation. Manufacturer's installation instructions, as required by the international residential codes, shall be available on the residential job site at the time of inspection.
(e) Exterior wall envelope. Construction plans and documents for all buildings shall describe the exterior wall envelope in sufficient detail to determine compliance with this chapter. The construction plans and documents shall provide details of the exterior wall envelope as required, including flashing, intersections with dissimilar materials, corners, end details, control joints, intersections at roof, eaves, or parapets, means of drainage, water resistive membrane, and details around openings.
(f) Manufacturing installation instructions. The construction plans and documents shall include manufacturing installation instructions that provide supporting documentation that the proposed penetration and opening details described in the construction plans and documents maintain the weather resistance of the exterior wall envelope. The supporting documentation shall fully describe the exterior wall system that was tested, where applicable, as well as the test procedure used.
(g) Site plan. The construction plans and documents submitted with the application for a building permit shall be accompanied by a site plan approved by the planning and development services department in accordance with the guidelines set out in the zoning ordinance in appendix A to this Code. For example, the site plan shall be shown to scale the size and location of new construction and existing structures on the site, distances from lot lines, the established street grades and the proposed finished grades. Additionally the site plan shall be drawn in accordance with an accurate boundary line survey. In the case of demolition, the site plan shall show the construction to be demolished and the location and size of existing structures and construction that are to remain on the site or lot. The building official is authorized to waive or modify in writing the requirement for a site plan.
(h) Examination of construction plans and documents. The building official shall examine or cause to be examined the accompanying construction plans and documents and shall ascertain by such examination whether the proposed construction indicated and described is in compliance with the requirements of this chapter and other pertinent provisions of the International Building Code, 2006 edition, with Georgia Amendments 2007; International Residential Code, 2006 edition, with Georgia Amendments 2007 and 2008; International Fire Code, 2006 edition, with Georgia Amendments 2008; International Plumbing Code, 2006 edition, with Georgia Amendments 2007 and 2008; International Mechanical Code, 2006 edition, with Georgia Amendments 2007 and 2008; International Fuel Gas Code, 2006 edition, with Georgia Amendments 2007 and 2008; National Electrical Code, 2005 edition, with Georgia Amendments 2006; and International Energy Conservation Code, 2009 edition, with Georgia Supplements and Amendments 2008. The reference to the Codes will include any and all subsequent and future amendment to these codes. This also includes all updates and required International Building Codes from the date of the ordinance from which this section is derived and all future ordinances and codes as required by the state will be enforced.
(i) Approval of construction plans and documents. When the building official issues a permit, the construction plans and documents shall be approved, in writing or by stamp, as being in compliance with this chapter. However, the approval of construction plans and documents and other data shall not prevent the building official from requiring the correction of errors in the construction plans and documents and other data. One set of construction plans and documents so reviewed shall be retained by the building official. The other set shall be returned to the applicant, shall be kept at the site of work and shall be open to inspection by the building official.
(j) Previous approvals. The enactment of this chapter shall not require changes in the construction plans and documents, construction or designated occupancy of a structure for which a lawful permit has been issued prior to enactment of this chapter and the construction of which has been pursued and not abandoned within 180 days after the effective date of the ordinance from which this chapter is derived.
(k) Phased approval. The building official is authorized to issue a permit for the construction of foundations or any other part of a building or structure before the construction plans and documents for the whole building or structure have been submitted, provided that construction plans and documents and adequate information and detailed statements have been filed complying with pertinent requirements of this chapter. The holder of such permit for the foundation or other parts of a building or structure shall proceed at the holder's own risk with the approved part of the building construction operation and without any assurance that a permit for the entire structure will be granted by the building official.
(l) Design professional in responsible charge.
(1) When it is required and requested by the building official that construction plans and documents be prepared by a registered design professional (a professional engineer or architect licensed by the state), the design professional shall be registered in the state and shall affix such seal on all documents. The building official shall be authorized to require the owner to engage and designate on the building permit application a registered design professional who shall act as the registered design professional in responsible charge. If the circumstances require, the owner shall designate a substitute registered design professional in responsible charge who shall perform the duties required of the original registered design professional in responsible charge. The owner shall notify the building official in writing if the registered design professional in responsible charge is changed or is unable to continue to perform the duties required by this Code.
(2) The registered design professional in responsible charge shall be responsible for reviewing and coordinating submittal plans and documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building.
(m) Deferred submittals. For the purposes of this section, deferred submittals are defined as those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period.
(1) Deferral of any submittal items shall require prior approval by the building official. The registered design professional in responsible charge shall list the deferred submittals on the construction plans and documents for review by the building official.
(2) Submittal construction plans and documents for deferred submittal items shall be submitted to the registered design professional in responsible charge who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and that they have been found to be in general conformance with the design of the building. The deferred submittal items shall not be installed until their design and submittal plans and documents have been approved by the building official in writing.
(n) Amended construction plans and documents. Work shall be installed in accordance with the reviewed construction plans and documents, and any changes made during construction that are not in compliance with the approved construction plans and documents shall be resubmitted by the holder of the building permit for approval as an amended set of construction plans and documents before work is conducted.
(o) Retention of construction plans and documents. One set of approved construction plans and documents shall be retained by the building official for a period of not less than 180 days from date of completion of the permitted work or as required by state or local laws.