Sec. 62-86. Predevelopment review.

Sobre este texto

  • As published by Municode, current through 2023-08-08
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Prior to the filing of an application for preliminary plat approval, the developer, the engineer, or agent is encouraged to consult with the county building inspector, health department, public works director and other appropriate county departments as well as the Flint River District of the Natural Resource Conservation Service and the state department of transportation should the property require ingress and egress from a state highway for the purpose of facilitating the review process.

(1) Sketch plan. It is also recommended that a sketch plan of the proposed development be submitted by the subdivider for review at this time. The sketch plan should contain the following official's data which may be obtained from base maps available at the county building/ administration office, the county tax assessor's office, natural resource conservation service office, or the Southwest Georgia Regional Development Center.

a. Type of development (i.e., residential, manufactured home, or commercial);

b. Approximate tract boundaries and total acreage;

c. Approximate location with respect to land lot lines;

d. Streets on and adjacent to the tract;

e. Proposed general street layout;

f. Significant topographic, physical and historic features;

g. Generalized existing vegetation;

h. Proposed general lot layout and total number of lots; and

i. Location of any existing wells if applicable.

(2) Sketch plan review. As far as may be practicable on the basis of a sketch, the planning commission or designated staff will, without prejudice to the county, advise the subdivider within 20 working days of the extent to which the proposed subdivision conforms to the standards of these regulations and other applicable ordinances or statutes, and will advise what additional documents, possible plan modifications, etc., must be submitted and what review procedures must be undergone in order to obtain final plat approval.

(3) Soil and sedimentation review process.

a. The applicant is encouraged to meet with the Soil Conservation Service Office (SCS), Flint River District with a rough draft or sketch plan of the proposed subdivision prior to submitting an application and preliminary plat. Although this step is not a requirement, it is helpful to aid these officials in advising the developer if a soil and sedimentation control plan is necessary.

b. If a proposed new subdivision will have new roads or drainage improvements or entails a significant amount of land disturbing activity entailing greater than 1.1 acres, the developer must submit a soil erosion and sedimentation control plan prior to plat approval.

Five copies of the soil erosion and sedimentation plan as well a land disturbing permit application will need to be delivered to the county building department to be dispensed to the health official, road superintendent, the natural resource and conservation service (formerly the soil conservation service) and department of natural resources for review.

The review process may take up to 45 days from the date the plan is submitted. No land disturbing (i.e., road building, land clearing, drainage installation, etc.) shall be performed until the preliminary plat has been approved, signed and land disturbing permits issued.

(4) Department of transportation review process.

a. If the subdivision is located on a state highway, driveway and ingress/egress approval is required by the state department of transportation (DOT). The subdivider shall submit three copies of the preliminary plat to the state DOT for review.

b. The DOT recommendation is required prior to submittal of the preliminary plat to the planning commission for review.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Code 2004, § 66-91; Ord. of 9-12-2000, § 400.0)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:mitchell-county/code/62-86@2023-08-08-0b41f2a52a

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Mitchell County Code of Ordinances, Sec. 62-86. Predevelopment review | Georgia Commons