Each and every lot in the
subdivision shall be connected to the county water system at time of first sale, and there shall be a tap-on fee to the water system as stated on the fee schedule adopted by the county.
Dry lines. In the event that any subdivision is approved within one (1) mile by nearest public road of either existing water distribution lines of the county water system, or any water distribution line under contract to be installed as of the date of approval, said subdivision shall have dry water lines and valves and other required items installed by the developer in accordance with the above standards, the same to be connected to the county water system when water distribution lines are accessible.
Phone lines. Phone lines shall be installed thirteen (13) feet from the edge of pavement or nine (9) feet from back of curb.
Cable lines. Cable lines shall be installed two
(2) feet from the edge of pavement or one (1) foot from back of curb or six (6) inches if sidewalk is against curb.
Power lines. Power lines shall be installed two
(2) feet off the right-of-way or nineteen (19) feet from back of curb.