Sec. 14-425. Required inspections.

Sobre este texto

  • As published by Municode, current through 2023-09-05
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

The building official, upon notification from the permit holder or his or her agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or notify the permit holder or his or her agent of any violations which must be corrected in order to comply with the technical code:

(1) Building.

a. Foundation inspection. The foundation inspection is to be made after trenches are excavated and forms erected.

b. Frame inspection. The frame inspection is to be made after the roof, all framing, fireblocking and bracing are in place, and all concealing wiring, pipes, chimneys, ducts and vents are complete.

c. Final inspection. The final inspection is to be made after the building is completed and ready for occupancy.

(2) Electrical.

a. Underground inspection. The underground inspection is to be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.

b. Rough-in inspection. The rough-in inspection is to be made after the roof, framing, fireblocking and bracing is in place and prior to the installation of wall or ceiling membranes.

c. Final inspection. The final inspection is to be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.

(3) Plumbing.

a. Underground inspection. The underground inspection is to be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place.

b. Rough-in inspection. The rough-in inspection is to be made after the roof, framing, fireblocking and bracing is in place and all soil, waste and vent piping is complete, and prior to the installation of wall or ceiling membranes.

c. Final inspection. The final inspection is to be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.

(4) Mechanical.

a. Underground inspection. The underground inspection is to be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.

b. Rough-in inspection. The rough-in inspection is to be made after the roof, framing, fireblocking and bracing are in place and all ducting and other concealed components are complete, and prior to the installation of wall or ceiling membranes.

c. Final inspection. The final inspection is to be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy.

(5) Gas.

a. Rough piping inspection. The rough piping inspection is to be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.

b. Final piping inspection. The final piping inspection is to be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.

c. Final inspection. The final inspection is to be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to ensure compliance with all the requirements of this Code and to ensure that the installation and construction of the gas system is in accordance with permitted plans.

(6) Energy.

a. Foundation inspection. The foundation inspection is to be made before slab concrete is poured in place. To verify that perimeter insulation has been installed correctly on any slab on grade foundations, if required.

b. Frame inspection. The frame inspection is to be made before exterior wall insulation is concealed by wall board to check installation of exterior wall insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner to restrict air passage.

c. Final inspection. The final inspection is to be made after the building is completed and ready for occupancy. The final inspection shall verify installation and R-value of ceiling and floor insulation and verify correct Seasonal Energy Efficiency Ratio (SEER) ratings on appliances.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Code 2000, § 36-108(3.8.6))

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:morgan-county/code/14-425@2023-09-05-a4c3c3933e

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Morgan County Code of Ordinances, Sec. 14-425. Required inspections | Georgia Commons