Part II - CODE OF ORDINANCES / Chapter 62 - ROADS / Article VI - BROADBAND READY COMMUNITY
Sec. 62-159. Approval or denial notification.
Sobre este texto
- As published by Municode, current through 2025-12-09
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) If, on or before the 11th day as described in section 62-157(b), an application is deemed complete, Paulding County shall approve or deny an application within ten calendar days unless a joint meeting between the applicant and Paulding County is deemed as necessary.
(1) If a joint meeting is deemed necessary, the joint meeting must occur within 15 calendars days of notification of completion and the joint meeting shall include:
a. Where the applicant if going to conduct work;
b. When the work will be conducted;
c. What type of work will be done;
d. Who Paulding County can contact for specific details or related questions; and
e. Any permit seeking approval under application.
f. Following a joint meeting between the applicant and Paulding County, Paulding County shall deny or approve the application within ten calendar days.
(2) Upon final approval, any required permit permitted shall be deemed issued.
Historia
(Ord. No. 21-03, § 1 (Exh. A), 4-13-2021)