Sec. 62-35. General provisions applicable to all placements.

Sobre este texto

  • As published by Municode, current through 2025-12-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Any permit issued under this section shall constitute a license for permissive use only and the placement of facilities or utilities upon a public way pursuant to a permit shall not operate to create a property right in the permittee.

(b) Prior to commencing installation, wire location devices shall be utilized by all persons.

(c) Should the county determine that it is necessary for the construction, repair, improvement, maintenance, safe and effective operation, alteration or relocation of the public way, then it shall be the sole responsibility and the sole expense of the permittee to remove any utility installed pursuant to this section which is so affected by the public way alteration and to thereafter relocate or reset the utility.

(d) Should a permittee fail to remove or relocate its utility pursuant to subsection (b) of this section, upon written notice by the county, the county shall remove such utilities and the permittee shall be liable for any and all costs or damages incurred by the department as a result thereof. It shall be the responsibility of the permittee to schedule and coordinate removal and relocation construction with the county.

(e) As a condition precedent to the issuance of a permit, the permittee shall provide proof of an agreement to indemnify and hold harmless the county, its agents and officers, as to all claims, damages, demands, actions, costs and expenses which may result from any injury or other damage arising from the construction, operation, utility maintenance, highway maintenance, repair, removal or relocation of the utilities hereunder permitted.

(f) During any construction, repair, removal or relocation permitted under this article, the permittee shall at all times maintain necessary safety devices in accordance with the state department of transportation manual on Uniform Traffic Control Devices, including, but not limited to, flagmen, signs, lights, flares and barricades, as may be deemed necessary by the county as safety precautions.

(g) With respect to any limited access highway, the permit issued under this article shall not provide access rights to any areas not specifically provided for within the terms of the permit.

(h) Prior to the installation and construction of the utilities, the permittee shall verify and provide documentation as to the boundaries of the public way and the placement of the utilities thereon to the county for review and approval.

(i) During installation, construction, removal, maintenance, operation and relocation periods, the permittee shall provide and maintain reasonable access to existing private driveways, private roads, easements and public ways and shall restore all areas disturbed to the condition preceding the work.

(j) Permittee must comply with applicable codes and regulations prior to the construction of a utility permitted under this article and shall be responsible for submitting design specifications and plans and for obtaining approval from applicable departments and agencies within both the state and county governments.

(k) The use of explosives in the construction, installation, removal, relocation, maintenance or operation of utilities permitted under this article is prohibited unless the permittee obtains a separate permit for the blasting activity.

(l) The permittee shall provide the county with written notice of the intent to commence work as permitted under this article a minimum of 24 hours prior to the commencement of any work.

(m) All permits issued under this article shall be void unless work authorized thereunder is commenced within 60 days of the permit's issuance.

(n) All work associated with the installation, construction, maintenance, relocation and removal of utilities permitted under this article shall be completed within a reasonable time, not to exceed 120 days from the date of the permit's issuance. Upon completion, the permittee shall submit a written notice to the county confirming completion.

(o) Permits issued under this article are not transferrable. A new owner of a utility must apply for a permit as specified in this article.

(p) The county may revoke a permit upon submitting a 30-day written revocation notice to the permittees.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Code 1987, § 17-5; Res. No. 98-30, § C(3), 12-8-1998)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:paulding-county/code/62-35@2025-12-09-21bcd9d751

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Paulding County Code of Ordinances, Sec. 62-35. General provisions applicable to all placements | Georgia Commons