Polk County · Código de ordenanzas
Chapter 32 - BROADBAND
Sec. 32-6. Approval or denial notification.
Sobre este texto
- As published by Municode, current through 2026-06-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
If, on or before the 11th day as described in section 32-5 an application is deemed complete, Polk County government shall approve or deny an application within ten calendar days unless a joint meeting between the applicant and Polk County Board of Commissioners is deemed as necessary.
(1) If a joint meeting is deemed necessary, the joint meeting must occur within 15 calendar days of notification of completion and the joint meeting shall include:
a. Where applicant is going to conduct work,
b. When the work will be conducted,
c. What type of work will be done,
d. Who Polk County government can contact for specific details or related questions, and
e. Any permit seeking approval under application.
f. Following a joint meeting between the applicant and the Polk County Board of Commissioners, the application shall be approved or denied within ten calendar days.
(2) Upon final approval, any required permit permitted shall be deemed issued.
Historia
(Ord. No. 2021-22, § 1, 6-8-2021)
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.