Pulaski County · Código de ordenanzas
Appendix A - SUBDIVISION ORDINANCE / Chapter 5 - CONFORMANCE WITH COMPREHENSIVE PLAN, IMPROVEMENTS REQUIRED, DESIGN AND CONSTRUCTION STANDARDS FOR ALL SUBDIVISIONS / 5.0 - Conformance With Comprehensive Plan and Other Regulations.
Section 5.7. Standards for Storm Water Management.
Sobre este texto
- As published by Municode, current through 2023-06-05
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
A combination of storage and controlled release of storm water runoff and on-site retention shall be required when the proposed development shall increase the peak rate of runoff by more than one cubic feet per second (1.0 cfs) for a ten (10)-year frequency storm. The Rational Method or the Soil Conservation Method shall be used to determine the runoff rate in accordance with sound engineering practice and shall be acceptable to the Enforcement Officer. Developments may be exempt from this provision if the design professional of record can demonstrate that the runoff can be adequately transmitted through existing downstream storm drain structures and will not result in increased flood heights or additional threats to public safety, will not adversely affect downstream properties, and compliance with Section 5.2.1 is demonstrated.
Should on-site retention be required, the outlet device(s) of the retention facility shall be designed to limit post-development runoff rates to less than or equal to the pre-development rates for the two (2), five (5), ten (10), twenty-five (25), and fifty (50)-year storm event.
The retention storage volume to be provided shall be calculated on the basis of the appropriate return frequency rainfall, as published by the National Weather Service or other acceptable service for the affected site. The retention volume required shall be calculated based on the appropriate hydrograph for inflow and standard reservoir routing at the approved release rates as specified above. However, the design calculations shall include the routing of the one hundred (100) year frequency storm event through the retention facility. Said calculations shall indicate that the one hundred (100) year frequency storm event can be safely routed through the facility.
The storm drainage system shall be designed in accordance with Section 5.3.9 of this Ordinance. At a minimum, the storm drainage system shall be sized to adequately convey the runoff from the fifty (50) year frequency storm event to the retention facility.
Any required retention areas shall not be developed. Appropriate vegetation shall be planted in all retention areas. Any required retention areas shall be incorporated into the common areas of the residential development or incorporated into individual lots. The local government maintains the right, but not the responsibility, to access retention areas for purposes of maintenance and inspection.
Fences a minimum of four feet (4') in height with a minimum eight-foot (8')-wide gate will be required on all retention ponds where:
1. The sides of the pond have a slope greater than three horizontal to one vertical (3:1); or
2. The depth of water in the pond is greater than three feet (3') at one hour after the duration of the storm event.
Drainage easement requirements:
The minimum easement width for open ditch where pipe is feeding into the ditch will be determined as follows:
Pipe Size Easement 15" to 30" 10 feet 36" to 66" 20 feet Pipe Size Easement 72" and greater 25 feet Where a subdivision is traversed by a watercourse, drainage way or stream, there shall be a drainage and access easement conforming substantially with the lines of such watercourse, and such further width as will be adequate for the purpose of drainage and maintenance, taking into account possible future development of higher land in the same drainage area. Such drainage way shall be piped when the Enforcement Officer shall find that it is a hazard or that a continual maintenance problem might exist. If the drainage way is totally piped, the easement width shall be based on the associated pipe size above.