Sec. 18-73. Permit fees.

Sobre este texto

  • As published by Municode, current through 2026-02-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Permits not valid. No building, construction, electrical, mechanical, miscellaneous or other permit issued by the planning and development department shall be valid until fees prescribed by this section shall have been paid.

(b) Permit fees for work commenced prior to obtaining permits. In all cases where building, construction, electrical, plumbing, mechanical or other work for which a permit is required is commenced before such permit is obtained, any permit fee due to the county for a permit for such work shall be twice the amount of the regular permit fee specified in this article which would have been due had such permit been obtained prior to commencing work. In no event shall such fee be less than an amount listed in the schedule of fees in addition to the regular permit fee. Payment of such increased fee shall not be a defense in any prosecution for any such work, for which a permit is required. Any work performed prior to the issuance of a building permit that has not been inspected by the county, and that is not easily inspected, or has been covered up, shall be inspected by an independent engineer that can certify that such work complies with the building code.

(c) Reinspection fees. When extra inspection trips are made for a permit holder due to any of the following reasons, an addition fee in an amount listed in the schedule of fees shall be charged for each such additional inspection:

(1) Wrong address given on call for inspection;

(2) Work not ready for inspection at time specified;

(3) Required corrections not made within time specified;

(4) Failure to request required inspections; and

(5) Additional work done after inspection has been made.

(d) Refund of fees. Where no work has been done under a valid permit for which fees have been paid and a written request for refund of fees is made by holder thereof within six months of the date of original issuance, the of the planning and development department may authorize the refund of 85 percent of such fee upon surrender of the permit and cancellation of the permit, providing no refund shall be made of a plan review fee.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 7-2-2021(1))

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:putnam-county/code/18-73@2026-02-17-ecb6082f37

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.