(a) The design of the solar energy system shall conform to applicable local, state and national codes, regulations, and standards. A building permit, reviewed by department staff, shall be obtained for a solar energy system. All design and installation work shall comply with all applicable provisions in the versions of the National Electric Code (NEC), the International Residential Code (IRC), International Commercial Building Code, International or Fire Code including any state or local amendments that are enforced at the time of permit review, and any additional requirements set forth by the local utility.

(b) Emergency access. Roof-mounted solar energy systems shall be located in such a manner as to ensure emergency access to the roof, provide pathways to specific areas of the roof, provide for smoke ventilation opportunities, and provide emergency egress from the roof.

(c) The solar energy system shall comply with all applicable Putnam County Code of Ordinances so as to ensure the structural integrity of such solar energy system. The existing roof structure and the weight of the solar energy system shall be taken into consideration when applying for a solar energy system permit.

(d) Prior to operation, electrical connections must be inspected by an appropriate electrical inspection person or agency, as determined by the planning director.

(e) Any connection to the public utility grid must be approved by the appropriate public utility.

(f) If batteries are included as part of the solar collector system, they must be installed according to all requirements set forth in the versions of the National Electric Code and State Fire Code in force at the time of permit. When no longer in operation, the batteries shall be disposed of in accordance with the laws and regulations of the Putnam County and any other applicable laws and regulations relating to hazardous waste disposal.

(g) The owners and operators of a solar farm and the owners of any real property on which it is located shall be jointly responsible for the maintenance and removal of the solar energy system, its equipment and panels, and any appurtenant structures The names of the manufacturers, installers, facility owners, and facility operators, and their addresses and phone numbers shall be posted on the required fencing at each entrance of a solar farm.

(h) The director of planning and development or designee shall have the right to inspect any solar farm in the unincorporated areas of the county without notice if there is a risk of immediate harm or injury to person or property. If there is no risk of immediate harm or injury to person or property, the director or designee shall have the right to inspect any solar farm upon making reasonable efforts to notify the owners or operators 24 hours in advance of the inspection.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 7-10-2020(1))

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:putnam-county/code/53-7@2026-02-17-6d63e84527

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Putnam County Code of Ordinances, Sec. 53-7. Safety and inspections | Georgia Commons