Sec. 310-104. Exemptions.

Sobre este texto

  • As published by Municode, current through 2026-01-27
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Pre-existing conditions. This article shall not apply to the following pre-existing conditions:

(1) Work consisting of the repair or maintenance of any lawful use of land that is zoned and approved for such use on or

before the effective date of this article.

(2) Existing development and on-going land development activities including but not limited to existing silviculture, landscaping, gardening and lawn maintenance, except that new development or land development activities on such properties will be subject to all applicable buffer

requirements.

(3) Any land development activity that is under construction, fully approved for development, scheduled for permit approval or has been submitted for approval as of

the effective date of this article.

( 4) Land development activity that has not been submitted for approval, but that is part of a larger master development plan, such as for an office park or other phased development that has been previously approved within two years of the effective date of this article.

(b) Exempted activities. This article shall not apply to the following:

(1) Activities for the purpose of building one or more of the following:

a. A stream crossing by a driveway, transportation route or utility line.

b. Public water supply intake or public wastewater outfall structures.

C. Intrusions necessary to provide access to a property.

d. Public access facilities that must be on the water including boat ramps, docks, foot trails leading directly to the river, fishing platforms and overlooks.

e. Unpaved foot trails and paths.

f. Activities to restore and enhance stream bank stability, vegetation, waSupp. No. 6 CD310:21 ter quality and/or aquatic habitat, so long as native vegetation and bioengineering techniques are used.

(2) Public sewer line easements paralleling the stream, except that all easements (permanent and construction) and land development activities should be at least 25 feet from the top of the bank. This includes such impervious cover as is necessary for the operation and maintenance of the utility, including but not limited to

manholes, vents and valve structures. This exemption shall not be construed as allowing the construction of roads, bike paths or other transportation routes in such

easements, regardless of paving material, except for access for the uses specifically cited in subsection (b)(l), above.

(3) Permitted land development activities within a right-of-way existing at the time this article takes effect or approved under the terms of this article.

( 4) Within an easement of any utility existing at the time this article takes effect or approved under the terms of this article, land development activities and such impervious cover as is necessary for the operation and maintenance of the utility,

(5) (6) including but not limited to manholes, vents and valve structures.

Emergency work necessary to preserve life or property. However, when emergency work is performed under this section, the person performing it shall report such work to the director on the next

business day after commencement of the work. Within ten days thereafter, the person shall apply for a permit and perform such work within such time period as may

be determined by the director to be reasonably necessary to correct any impairment such emergency work may have caused to the water conveyance capacity,

stability or water quality of the protection area.

Forestry and silviculture activities on land that is zoned for forestry, silvicultural or agricultural uses and are not incidental to other land development activity. If such activity results in land development in the buffer that would otherwise be prohibited, then no other land development activity other than normal forest management practices will be allowed on the entire property for three years after the

end of the activities that intruded on the buffer.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 0-2006-32, §§ 1-3, 11-28-2006)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:rockdale-county/code/310-104@2026-01-27-ec4a4de00d

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Rockdale County Code of Ordinances, Sec. 310-104. Exemptions | Georgia Commons