Part II - CODE OF ORDINANCES / Chapter 70 - UTILITIES / Article V - STANDARDS FOR SOLAR FARMS

Sec. 70-82. Application for permit, fee, and revocation of permit.

Sobre este texto

  • As published by Municode, current through 2026-03-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Before commencing operations, all solar farms shall submit an application for a solar farm permit on the form prescribed by the Sumter County Code Enforcement Department and shall provide proof of compliance with all standards for solar farms outlined in this article.

No solar farm shall commence operations until it has been inspected by the Sumter County Code Enforcement Department and obtained the permit required by this section.

(b) An application for a solar farm permit shall be accompanied by a comprehensive site plan for the solar farm, which shall include, but not be limited to:

(1) Drawings prepared by a professional engineer licensed to practice in Georgia that clearly illustrate the design of the solar farm;

(2) A project summary;

(3) General procedures for operation and maintenance of the installation;

(4) Measures for maintaining safe access to the installation;

(5) Electrical schematics,

(6) Soil erosion and sediment control;

(7) Landscape plans;

(8) Temporary or permanent roads or driveways;

(9) Grading;

(10) Vegetation clearing and planting and mitigation or screening with vegetation, structures, or fences;

(11) Exterior lighting and any screening.

The applicant shall provide additional copies of the comprehensive site plan to the Sumter County Sheriff's Office, Fire Department, and Emergency Management Agency. The

comprehensive site plan must be approved in writing by the Sumter County Code Enforcement Department before a solar farm may receive a permit or commence operations.

(c) An application for a solar farm permit shall be accompanied by a decommissioning and restoration plan that describes the anticipated life of the solar project, the parties responsible for the decommissioning and restoration, the estimated decommissioning and restoration costs, the amount by which such costs were reduced due to the recyclable value of any materials, and the method for ensuring that funds will be available for decommissioning and restoration of the real property. The decommissioning and restoration plan must be prepared by a professional engineer duly licensed by the State of Georgia.

(d) An application for a solar farm permit shall be accompanied by a bond ensuring that funds will be available for decommissioning the solar farm and reasonably restoring the site to its natural condition. The bond shall be in the form of cash or surety from a bonding company qualified to transact business in the State of Georgia and acceptable to the Sumter County Code Enforcement Department. The bond shall be payable to Sumter County in an amount determined by the county's code enforcement department to be reasonably sufficient to cover removal of the solar farm in its entirety and reasonable restoration of the site to its natural condition. The bond shall be maintained as long as the solar farm exists, regardless of whether it is actively operating. If the bond is not maintained as provided herein, Sumter County may call the bond and use the proceeds to remove the solar farm in its entirety and to reasonably restore the site to its natural condition. The bond may be released or returned when the county's code enforcement department determines in its reasonable discretion that the decommissioning of the solar farm has been completed in accordance with all applicable ordinances and federal and state laws.

(e) At the time of application, each applicant shall pay a non-refundable permit fee in the amount established by the Sumter County Code Enforcement Department.

(f) A permit may be revoked by the Sumter County Code Enforcement Department for any solar farm which is not in full compliance with this article. Prior to revoking the permit, the Sumter County Code Enforcement Department shall provide three calendar days' written notice of any deficiencies to the solar farm owner or operator via U.S. Mail, overnight delivery, or hand delivery. If the deficiencies are not corrected within those three days, the Sumter County Code Enforcement Department may revoke the solar farm's permit and require the solar farm to submit a new application before recommencing operations. During the time that a solar farm permit is revoked, the solar farm shall post a sign at each entrance to the solar farm no smaller than one foot by two feet stating: "This solar farm's operations have ceased due to noncompliance with the Sumter County Code of Ordinances. For more information, contact the Sumter County Code Enforcement Department.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 4-19-16(2); Ord. of 8-15-17; Ord. of 8-20-19, § 1)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:sumter-county/code/70-82@2026-03-17-757fab5e5f

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.