Sec. 28-261. Compliance schedule and reporting requirements.
Sobre este texto
- As published by Municode, current through 2026-07-09
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
The following conditions shall apply to the schedules required by section 28-258:
(1) Schedule components. The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment requirements for the industrial user to meet the applicable pretreatment standards (e.g., hiring an engineer, completing the engineering report, completing final plans, executing contracts for major components, commencing construction, completing construction, etc.).
(2) Schedule intervals. No such increment shall exceed 9 months.
(3) Compliance schedule progress report. No later than 14 days following each date in the schedule and the final date for compliance, the industrial user shall submit a progress report to the Authority, at a minimum, whether or not it complied with the increment of progress to be met on such date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and the steps being taken by the industrial user to return construction to the schedule established.
Historia
(Ord. No. O-03-22, Exh. A, 11-10-2022)