Chapter 14 - SITE DESIGN / Article II - PERMITS AND PROCEDURES
Sec. 14-27. Duration of permit.
Sobre este texto
- As published by Municode, current through 2026-05-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(1) Construction work authorized by an approved permit shall be completed within 12 months following approval of the
permit. Permitted work not completed within 12 months may be officially extended for additional six-month increments.
(2) If construction has not commenced within one year of the issuance of a permit, such permit shall expire, unless extended in
writing by the Whitfield County Engineer.
If such approval expires, then new construction plans must be submitted in accordance with then-current regulations.