Las actas
Tal como se publicó en burkecounty-ga.gov, leído el 26 de noviembre de 2026. Nada de lo que sigue lo escribió Georgia Commons. El registro se muestra en inglés, tal como se publicó.
BURKE COUNTY BOARD OF COMMISSIONERS
FINANCE COMMITTEE
JULY 2, 2024
The Finance Committee of the Burke County Board of Commissioners met on Tuesday, July 2, 2024, at 4:00 pm in the Training Room. The meeting was called to order at 4:00 pm by Committee Chair Lucious Abrams, Jr. Commissioners Art Lively, Tommy Nix, County Manager Merv Waldrop, Assistant County Manager Adam Flakes, and CFO Michael Wiseman were in attendance.
Bids for the Splash Pad at Citizens Park were received from:
BIDDER BID PRICE
Playground Creations $ 199,410.79 Dominica Recreation (A) $ 194,865.35 (B) 239,302.45 Water Splash $ 199,555.45 Bids for the Concession Stand at Citizens Park were received from:
BIDDER BID PRICE
Arentz Contracting $ 483,000.00
C. Merrill Construction $ 549,000.00 Stewart Construction $ 486,000.00 The Committee viewed the project’s designed layout and discussion ensued on the project’s $350,000.00 budget. Manager Waldrop stated there is currently $350,000.00 in the General Fund for the project and additional funding is available in SPLOST IV. Recreation Director Stephen Waskey stated approximately $360,000.00 to $380,000.00 is currently allocated in their budget for the project.
Assistant Manager Flakes reminded the Committee of a CDBG grant in process for the Gymnasium project and Manager Waldrop stated SPLOST V will have recreation funding. Both Assistant Manager Flakes and Waskey stated the Gymnasium project is the priority. Continued discussion of the parking lot, restrooms, and new playground area budgeting concerns occurred with Facilities Director Josh Dailey stating that $1,000,000.00 should cover costs for the splash pad, concession building, and parking lot area. Waskey stated the price of the Splash Pad may increase if the Concession Stand is not included since the pump room for the Splash Pad was in the Concession Stand. Waskey will review the submissions and bring a recommendation back to the Board on Tuesday, July 9, 2024.
The Committee reviewed and approved the check runs for June 2024.
Assistant Manager Flakes stated ACH of all payroll was successful.
Commissioner Abrams requested an update on the Cobb Road paving project. Discussion on the current hold-up of the project ensued and whether crush and run is a better option.
Mr. Waskey stated the Recreation Department successfully held a twenty-team tournament and provided details on the July 4th festivities.
Being no further business to come before the Committee, the meeting was adjourned at 4:36 pm.
_________________________________ ______________________________ Lucious Abrams, Committee Chair Tommy Nix, Commissioner _________________________________ ______________________________