Ciudad: Brooklet
Brooklet City Council: reunión ordinaria, 12 de diciembre de 2024
4 páginas
Estas son las actas tal como las publicó Brooklet City Council, leídas del archivo en su propio sitio web. Georgia Commons es independiente y no está afiliado a Brooklet City Council.
Este registro se publicó como imágenes escaneadas, leídas aquí con OCR: una letra o un número puede estar mal leído. El archivo que publicó el órgano está enlazado abajo.
Registros de esta reunión
Cada enlace abre el sitio web o el portal de reuniones del propio órgano.
- ActasDecember 12, 2024 Lane Street Residents Meeting Minutes (cityofbrooklet.org) · se muestra en esta página
Resumen
Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.
Este resumen está en inglés. No se ha escrito un resumen en español de estas actas.
Officials briefed Lane Street residents on a sewer pipeline project set to begin in January 2025; no votes were recorded.
These minutes record a pre-construction meeting for Lane Street residents, not a vote-taking session. City officials and the city engineer described the Brooklet to Statesboro sewer project, which includes a new pump station near the scout hut and a 12-inch pipe running along Church Street, across Lee Street and parallel to Lane Street to the city limits. Construction is set to start in January 2025, with the contractor expected to be out of city limits by the end of March. The engineer said driveways that are cut will be replaced, and residents were asked to mark sprinklers with paint or flags. The minutes record no motions or votes.
Temas tratados: Lane Street sewer project; pump station near scout hut; 12-inch force main route; driveway restoration; marking residents' irrigation systems; construction schedule January 2025.
Puntos del orden del día (2)
Encontrados en las actas por sus encabezados. Cuando se muestra un resultado, se leyó por regla de las propias palabras del punto: es una guía del texto, no parte del registro.
Las actas
Tal como se publicó en cityofbrooklet.org, leído el 12 de noviembre de 2026. Nada de lo que sigue lo escribió Georgia Commons. El registro se muestra en inglés, tal como se publicó.
CITY OF BROOKLET
104 CHURCH ST. BROOKLET, GA 30415 PHONE (912) 842-2137 FAX (912)842-5877
L.W. (Nicky) Gwinnett, Jr. Mayor Carter Crawford, City Manager Rebecca Kelly, Mayor Pro-Tem Lori Phillips, City Clerk Bradley Anderson, Councilman Melissa Pevey, Assistant Clerk Hubert Keith Roughton, Councilman Ben Perkins, City Attorney
James Harrison, Councilman Sheila Wentz, Councilwoman
Lane Street Residents Pre-Construction Meeting December 12, 2024 6:30 PM Minutes
1. Welcome: Mayor Gwinnett
2. Project Overview: City Engineer Wesley Parker, Parker Engineering, LLC.
City of Brooklet officials and Lane Street residents gathered to discuss the upcoming redevelopment of Lane Street. The project, part of a broader infrastructure improvement initiative, will provide sewer services to the City of Brooklet. The initiative aims to enhance sewer services by installing a new pump station near the scout hut and laying a main
pipeline through Church Street, across Lee Street, and down Lane Street to the city's existing system.
Construction is set to start in January 2025, A 12-inch pipe, 4 feet deep, will run from the Scout Hut to Church Street, across Lee Street, and parallel Lane Street to the city limits.
Project manager Wesley Parker assured Lane Street residents that fiber optic cables, power lines, and irrigation systems would not be disturbed underground.
“We will avoid hitting cables, and we should be able to go under everything: we can't afford to be careful," said Parker.
The diligence required to avoid existing infrastructure underground could potentially slow
the construction. Parker would rather be slow and steady, avoiding unnecessary destruction and frustration.
1|Page
Parker also mentioned that existing irrigation systems will not be marked with flags as private companies install them, and they do not know where they are underground,
Because of this, he urged residents to mark where their sprinklers are with spray paint or flags and notify the construction workers.
Lindsey Thomas, the project's engineer from Parker Engineering, provided an overview of the construction plans. She noted that the trench for the force main would be approximately four feet deep and three to four feet wide. Thomas assured residents that any driveways
impacted during the excavation would be restored, stating, "If we have to cut through your driveway, we will be replacing it.”
Parker acknowledged the inconvenience but emphasized the project's long-term benefits, remarking, “We understand this will be a disruption, but once completed, it should resolve existing issues.” Parker also expressed appreciation for the community's cooperation,
adding, "Thank you to all the residents; we're going to get to know each other well during this process.”
The City of Brooklet encourages Lane Street residents to stay engaged throughout the
construction process and to report any concerns promptly to ensure a smooth and efficient
project. Updates will be provided as construction progresses, keeping the community informed every step of the way.
Discussions at the work session earlier on Thursday highlighted the city's broader plans for growth and development, including utility management services and zoning improvements.
3. Conclusion: Mayor Gwinnett
“
a ever
4 Pl gpa’) Approved this IW? day oc Jinuay ans % *, ” :
SEB NA
L.W. (Nicky) Gwinnett, Jr., Mayor ori Phillips, City Clerk
[e) eaanet® ie <<“ ony Uy, OK at o SS
“AAW
2|Page
Residents’ Meeting for the Brooklet to Statesboro Sewer Project
The purpose of the project is to provide sewer services to the City of Brooklet.
A pump station is planned at the Scout Hut to pump wastewater to the City of Statesboro.
A 12” pipe will run from the Scout Hut, to Church Street, across Lee Street, and will parallel Lane Street to the City limits.
A separate 3” pipe will also be installed for homeowners wishing to connect to the sewer system with a pump.
The project will start in January 2025.
The contractor should be out of the City limits by the end of March.
The pipe will be 4 feet deep.
The excavated trench will be approximately 3 to 4 feet wide.
The disturbed area will be approximately 15-20 feet wide.
The area over the excavated trench will be sodded after construction.
The contractor will bore under most paved driveways instead of cutting the concrete.
Driveways that must be cut will be patched temporarily with rock (crusher run) until concrete can be poured.
A resident would be without a driveway for a few hours at the most.
The pipe will be drilled underneath the wetlands.
*
Example of a pipeline project.