Condado: White County
White County Planning Commission: sesión de trabajo, 29 de septiembre de 2026
18 páginas
Estas son las actas tal como las publicó White County Planning Commission, leídas del archivo en su propio sitio web. Georgia Commons es independiente y no está afiliado a White County Planning Commission.
Registros de esta reunión
Cada enlace abre el sitio web o el portal de reuniones del propio órgano.
- ActasPlanning Commission Work Session and Public Hearing Agenda (www.whitecountyga.gov) · se muestra en esta página
Resumen
Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.
Este resumen está en inglés. No se ha escrito un resumen en español de estas actas.
Planning commission held a public hearing on a draft data center ordinance, where residents opposed data centers; no vote on the ordinance was recorded.
The White County Planning Commission held a work session and public hearing on a proposed Data Center Ordinance, a draft amendment to the county land use regulations. The planning director summarized the draft, which would limit data centers to the Industrial District with a Special Use Permit. Several residents spoke against data centers, citing noise, water use, strain on freshwater resources and possible eminent domain, and asked for a complete ban, tougher restrictions and penalties, and a requirement that data centers supply their own electricity. The director said the county cannot legally ban data centers and that an ordinance would ensure a structured review. The public hearing was closed with no vote on the ordinance recorded. The commission approved the September 1 minutes unanimously. The consent agenda included an administrative variance at 30 Taxi Way Ln and a preliminary plat extension for Chimney Lake Subdivision Phase 4; the minutes record no vote on those items.
Temas tratados: draft data center ordinance; public hearing on data centers; administrative variance at 30 Taxi Way Ln; Chimney Lake Subdivision Phase 4 plat extension; data center noise and water concerns; Special Use Permit for data centers.
Puntos del orden del día (40)
Encontrados en las actas por sus encabezados. Cuando se muestra un resultado, se leyó por regla de las propias palabras del punto: es una guía del texto, no parte del registro.
- 1.2 Purpose. The purpose of this Ordinance is to:
- 3.2 Prohibition in Other Districts. Data centers are expressly prohibited in all other zoning districts of White County, including but not limited to…
- 3.3 Floodplain Prohibition. No data center facility or any component thereof, including substations, fuel storage tanks, or generators, shall be located…
- 3.4 Proximity to Sensitive Features. No data center facility shall be located:
- 3.5 Classification. Data center classification shall be based upon the aggregate maximum electrical demand of the entire development at full buildout, without…
- 4.2 Application Requirements. An application for a Special Use Permit for a data center shall include, at minimum, all of the following:
- 4.3 Findings Required for Approval. The Board of Commissioners shall not approve a Special Use Permit for a data center unless it finds, based on the record,…
- 5.1 Legislative Findings. The White County Board of Commissioners adopts the following findings as the basis for the regulation of cryptocurrency mining…
- 5.3 Special Use Permit Standards — Cryptocurrency Mining Facilities. No Special Use Permit for a cryptocurrency mining facility shall be approved unless the…
- 5.5 Definition. The definition of 'Cryptocurrency Mining Facility' in Section 2 of this Ordinance applies to this Section in its entirety. Any ambiguity as to…
- 6.1 Community Meetings. Prior to any public hearing before the White County Planning Commission or Board of Commissioners, the applicant shall conduct two (2)…
- 6.2 Community Benefit Agreement. For any Major Data Center or Data Center Campus, the applicant shall, as a condition of Special Use Permit approval, enter…
- 7.1 Minimum Lot Requirements.
- 7.3 Setbacks.
- 7.4 Buffer Requirements.
- 7.5 Architectural Standards.
- 7.6 Fencing and Perimeter Security.
- 7.7 Buffer Landscaping Maintenance. All buffer plantings required by Section 7.4 shall be maintained by the operator in a healthy growing condition throughout…
- 8.1 Maximum Permissible Sound Levels. All data center operations, equipment, generators, cooling systems, and HVAC systems shall comply with the following…
- 8.2 Generator Testing and Operation.
- 8.3 Noise Monitoring.
- 8.4 Vibration. No data center operation shall generate perceptible vibration at any property line. All vibration-producing equipment shall be mounted on…
- 9.3 Water Conservation Plan. All data centers shall submit and comply with an approved Water Conservation Plan that:
- 9.4 Erosion and Sedimentation Control. All land disturbance activity associated with a data center facility shall comply fully with the Georgia Erosion and…
- 9.6 Air Quality. All diesel generators and other combustion equipment shall comply with applicable EPA emission standards. No open burning of vegetation,…
- 10.1 Infrastructure Cost Responsibility. It is the policy of White County that all public infrastructure costs directly attributable to a proposed data center…
- 10.5 Utility Coordination. Prior to issuance of any land disturbance permit, written will-serve letters and approved engineering plans shall be submitted from…
- 11.3 Maximum mounting height of site lighting: twenty (20) feet above finished grade.
- 11.4 Security lighting shall be motion-activated wherever possible and shall be directed inward toward the facility.
- 12.1 Decommissioning Plan Required. Prior to issuance of any building permit for a data center, the applicant shall submit a Decommissioning Plan for approval…
- 12.2 Financial Assurance. Prior to the issuance of any building permit, the applicant shall provide financial assurance in a form approved by the White County…
- 12.3 Abandonment. A data center shall be deemed abandoned if operations cease for a period of twelve (12) six (6) consecutive months, excluding temporary…
- 12.6 Bond Call Penalty. If White County is required to draw upon the financial assurance to complete decommissioning, the former operator shall be liable for…
- 13.1 All operating data center facilities shall submit an Annual Compliance Report to the White County Community and Economic Development Director by January…
- 13.3 Failure to submit the Annual Compliance Report by the required date shall constitute a violation of the Special Use Permit and subject the operator to…
- 14.1 Any conversion of an existing data center facility to any other high-intensity computing or digital processing use, including but not limited to…
- 14.3 Any transfer of ownership or change of operator of an approved data center shall be reported to White County within sixty (60) days, and the new owner or…
- 15.1 Any violation of this Ordinance, including failure to comply with any term or condition of an approved Special Use Permit, shall be subject to…
- 15.3 Nothing in this Section shall limit White County's right to pursue any other remedy available at law or in equity.
- 16.2 The Board of Commissioners may, at its sole discretion, impose conditions on a Special Use Permit that are more stringent than the minimum standards set…
Las actas
Tal como se publicó en www.whitecountyga.gov, leído el 25 de noviembre de 2026. Nada de lo que sigue lo escribió Georgia Commons. El registro se muestra en inglés, tal como se publicó.
WHITE COUNTY PLANNING COMMISSION MINUTES
WORK SESSION AND PUBLIC HEARING
Page 1 of 1 Tuesday, September 29, 2026 Administration Building 6:30 pm 1235 Helen Hwy, Cleveland, Ga. 30528
I. Call to Order – Chairman Thomas called meeting to order at 6:30 p.m.
II. Invocation- Said by Commissioner Ackerman
III. Review of Agenda
IV. Review and approval of minutes of September 1, 2026
a. Motion to approve made by Commissioner Burke, seconded by Commissioner Dixon, Approved Unanimously
V. Consent Agenda
a. Administrative Variance for Sam Orr
1. Senior Planner Carter presented an Administrative Variance that was granted by Director Owensby to Sam Orr at 30 Taxi Way Ln. Mr. Orr applied for a code variance of Appendix B, Section 804 Setbacks. Mr. Orr was requesting to reduce the side yard setback to 8 feet on the west side of his tract to build a storage building. Mr. Orr’s application met all the requirements necessary for Director Owensby to Approve an Administrative Variance under Appendix C, Section 2012.
b. Preliminary Plat Approval Extension for Chimney Lake Subdivision Phase 4
1. Senior Planner Carter presented London Ventures, Inc.’s request for an extension to the preliminary plat approval of phase 4 of the Chimney Lake Subdivision. The project is making steady progress, but additional time is necessary. This is their first request for an extension.
VI. New Business
a. Data Center Ordinances
1. Director Owensby gave a detailed summary of the proposed Data Center Ordinance that White County is considering implementing. See Appendix A.
2. Chairman Thomas then open the public hearing. Several citizens were present and spoke out against data centers being allowed in White County. Their concerns included issues that other jurisdictions have experienced that allowed data centers to be developed, the negative impacts from the noise that data centers generate, water usage and the strain to our freshwater resources and possible eminent domain. They requested the county ban data centers completely; increase the restrictions and penalties in the proposed ordinance and require data centers provide their own electricity. Director Owensby explained that the county cannot legally ban data centers. The county adopting an ordinance will ensure that any data center development will be extensively evaluated through a structured process with clear restrictions that ensure the community’s environmental, infrastructure, and quality of life are protected. Chairman Thomas then closed the public hearing.
VII. Adjournment Motion made by Commissioner Dixon to adjourn at 7:19 p.m., seconded by Commissioner Burke, Approved Unanimously
VIII. Present: Larry Freeman, Linda Dixon, Dona K. Burke, Charlie Thomas, Brad Ash, R.K. Ackerman, Tammy Carter, Jessie Owensby, Katy Paterson,
Robert House, Erin Lewis, Shelby Nish, Robbin Pearson, Alan Johnson, Jonathan Berry, Al Lunceford and Heath Biggers
IX. Absent: John Yarbrough
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
PREAMBLE
WHEREAS, White County, Georgia is a rural community committed to preserving its natural resources, agricultural heritage, scenic character, and quality of life for its residents; and
WHEREAS, high technology data centers represent an emerging and rapidly expanding industrial land use with unique and substantial demands on electricity, water, transportation infrastructure, and emergency services; and
WHEREAS, White County finds it necessary and appropriate to establish specific, enforceable land use regulations governing the siting, design, construction, operation, and decommissioning of data center facilities to protect the health, safety, and welfare of its citizens; and
WHEREAS, White County is authorized under O.C.G.A. § 36-66-1 et seq. and Appendix C of the White County Code of Ordinances to regulate land use through zoning and special use permits; and
WHEREAS, White County is authorized to require, as a condition of Special Use Permit approval, that applicants enter into Developer Infrastructure Agreements providing for applicant-funded construction of public infrastructure necessary to serve proposed data center development, pursuant to O.C.G.A. § 36-66-1 et seq. and White County's inherent police powers;
NOW THEREFORE, BE IT ORDAINED by the Board of Commissioners of White County, Georgia, that the White County Land Use Regulations are hereby amended to add the following provisions.
APPENDIX A
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
SECTION 1. TITLE AND PURPOSE
1.1 Title. This ordinance shall be known and may be cited as the "White County High Technology Data Center Facilities Ordinance" (hereinafter "Ordinance").
1.2 Purpose. The purpose of this Ordinance is to:
a. Establish clear definitions and classifications for data center uses;
b. Restrict data center development to appropriate zoning districts where adequate infrastructure exists;
c. Protect White County's rural character, natural resources, agricultural lands, scenic corridors, and groundwater supplies from incompatible industrial development;
d. Require data center operators to bear the full cost of impacts on public infrastructure, utilities, roads, and emergency services;
e. Establish enforceable standards for noise, lighting, visual screening, water use, stormwater, hazardous materials, and air quality;
f. Ensure responsible decommissioning and site restoration upon cessation of operations;
g. Provide meaningful community input and transparency in the review process;
and
h. Prevent adverse impacts on adjacent property values and the character of surrounding communities.
SECTION 2. DEFINITIONS
For purposes of this Ordinance, the following definitions apply:
"Data Center” A facility, or portion thereof, primarily designed, constructed, and operated for the purpose of housing computer systems, servers, telecommunications equipment, or related infrastructure used for the processing, storage, management, or transmission of digital data. A data center includes all accessory and supporting infrastructure necessary to its operation, including mechanical cooling systems, backup power generation, electrical substations, water cooling and treatment facilities, security systems, and fire suppression systems. This definition is consistent with O.C.G.A. § 48-8-3(68.1)(G)(ii).
A data center does not include an individual server room, computer room, or similar equipment area that is accessory and subordinate to another principal use, nor does it include a telecommunications center where the principal function of the facility is the transmission, switching, routing, or distribution of telecommunications signals.
Telecommunications Center. A building, portion of a building, structure, or facility whose principal use is to house telecommunications equipment used primarily for the transmission, receipt, switching, routing, amplification, regeneration, or distribution of voice, video, data, or other communications signals through a telecommunications network. Such facilities may include switching equipment, routing equipment, terminal equipment, repeater equipment, transmitter or receiver equipment, fiber-optic equipment, cable vaults, and associated power and mechanical equipment.
A telecommunications center does not include a data center where the principal use is the processing, storage, hosting, management, or computational analysis of digital data or applications.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
"Cryptocurrency Mining Facility” A facility, or portion thereof, primarily devoted to the operation of data processing equipment used to verify cryptocurrency transactions and maintain distributed digital ledgers (blockchain), including the generation or "mining" of cryptocurrency units. Cryptocurrency mining facilities are regulated as a distinct and separate use due to their intensive energy demand profiles, noise generation, and adverse land use impacts.
"Small Data Center” A data center containing less than 20,000 square feet of gross floor area 10 MW of maximum electrical demand devoted to data center operations.
"Medium Data Center” A data center containing 20,000 square feet to less than 100,000 square feet of gross floor area a maximum electrical demand of 10MW or greater but less than 100MW devoted to data center operations.
"Major Data Center” A data center containing 100,000 square feet to less than 500,000 square feet of gross floor area a maximum electrical demand of 100MW or greater devoted to data center operations.
"Data Center Campus” A unified development consisting of two (2) or more data center buildings under common ownership or control, or developed pursuant to a master development plan, with an aggregate of 500,000 or more square feet devoted to data center operations on a site or contiguous parcels.
"Closed-Loop Cooling System” A cooling system that recirculates water within the system without discharging it to the environment, significantly reducing consumptive water use.
"Open-Loop/Evaporative Cooling System” A cooling system that discharges water to the atmosphere through evaporation, consuming significant volumes of potable or raw water.
"Decommissioning” The process of safely closing and dismantling a data center facility, including the removal of all equipment, structures, hazardous materials, and restoration of the site to a safe condition suitable for future permitted use.
"Fiscal Impact Analysis” A study estimating the net fiscal effect of a proposed development on White County's revenues and expenditure obligations, including impacts on roads, utilities, emergency services, and public infrastructure.
"Operator” Any person, corporation, limited liability company, partnership, or other legal entity that owns, operates, or controls a data center facility.
"Property Line” The legally described boundary of the parcel on which a data center is located.
"Sensitive Use” Any residential dwelling, school, daycare facility, place of worship, hospital, medical facility, park, campground, recreational area, or similar use that may be adversely affected by data center operations.
SECTION 3. APPLICABILITY AND ZONING DISTRICT RESTRICTIONS
3.1 Zoning Districts. Data centers, as defined herein, shall only be permitted within the Industrial District (I) of White County, as set forth in Article XV of the White County Land Use Regulations, and only upon the issuance of a Special Use Permit pursuant to Section 4 of this Ordinance and Article XVII of the White County Land Use Regulations.
3.2 Prohibition in Other Districts. Data centers are expressly prohibited in all other zoning districts of White County, including but not limited to Agricultural Forestry (A-1), Residential Single-Family (R-1), Residential Multi-Family (R-2), Residential Seasonal (R-3), Community Commercial (C-1), Highway Business (C-2), and Planned Development (PD) districts.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
3.3 Floodplain Prohibition. No data center facility or any component thereof, including substations, fuel storage tanks, or generators, shall be located within a 100-year floodplain or floodway as designated on FEMA's Flood Insurance Rate Maps (FIRMs) or any applicable local floodplain maps.
Data Center Electrical Demand. The maximum coincident electrical demand, expressed in megawatts (MW), designed, requested, contracted, or otherwise established to serve a data center at full buildout under normal operating conditions, including electrical demand associated with information technology equipment, cooling systems, mechanical equipment, lighting, and other equipment necessary for operation of the facility. Electrical demand shall include power supplied by a utility or by on-site generation intended for normal or continuous operation but shall not include emergency standby generation used solely during a utility outage or emergency.
Aggregation of Data Center Capacity. For purposes of determining data center classification, the electrical demand of all data center buildings, facilities, phases, and associated development located on the same parcel, contiguous parcels, or parcels under common ownership, control, operation, or development shall be considered cumulatively. A development shall not be divided into separate buildings, parcels, phases, utility accounts, ownership entities, or applications for the purpose of avoiding a data center classification or applicable development standard.
3.4 Proximity to Sensitive Features. No data center facility shall be located:
a. Within 1,500 feet, in a straight line, of any property zoned or used for residential purposes;
b. Within 1,500 feet, in a straight line, of any school, daycare facility, hospital, or place of worship;
c. Within 1,500 feet, in a straight line, of any public park, publicly accessible greenway, nature trail, or publicly owned recreational area;
d. Within 1,000 feet, in a straight line, of any state waters;
e. Within 1,500 feet, in a straight line, of the Chattahoochee River or any of its tributaries, or any named stream within White County;
f. On any property containing prime farmland soils as classified by the USDA Natural Resources Conservation Service; or
g. On any property located within or adjacent to a groundwater recharge area as identified by the Georgia Department of Natural Resources or Georgia Environmental Protection Division.
3.5 Classification. Data center classification shall be based upon the aggregate maximum electrical demand of the entire development at full buildout, without regard to the number of buildings, parcels, development phases, utility meters, or ownership entities comprising the development.
SECTION 4. SPECIAL USE PERMIT REQUIRED
4.1 All data centers (Small, Medium, Major, and Data Center Campuses) shall require approval of a Special Use Permit (SUP) by the White County Board of Commissioners prior to the issuance of any land disturbance permit, building permit, or certificate of occupancy. Approval is not guaranteed and shall be subject to the standards and findings required herein.
4.2 Application Requirements. An application for a Special Use Permit for a data center shall include, at minimum, all of the following:
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
(1) Application and Filing Fees: A non-refundable application fee as established in the White County fee schedule, plus reimbursement to the County for the reasonable costs of independent third-party technical review of all required studies, which shall be paid by the applicant prior to scheduling of any public hearing.
(2) Conceptual and Full Site Plan: A detailed site plan prepared and sealed by a licensed Georgia professional engineer or registered land surveyor showing: (i) all proposed structures, setbacks, buffers, driveways, parking, and impervious surfaces;
(ii) location of substations, generators, fuel storage, cooling equipment, and transmission infrastructure; (iii) all natural features including streams, wetlands, floodplains, tree lines, and topographic contours; and (iv) the location of all dwellings, schools, places of worship, and sensitive uses within 2,640 feet of the property boundary.
(3) Building Elevations and Renderings: Architectural elevations and photorealistic renderings of all proposed buildings as viewed from each public right-of-way and from all adjacent properties.
(4) Viewshed Analysis: A viewshed analysis prepared by a qualified professional demonstrating visual impacts from public roads and adjacent properties, including sight-line exhibits.
(5) Noise Impact Assessment: A pre-construction acoustic study prepared by a licensed engineer who specializes in acoustics establishing existing ambient noise baselines and modeling projected noise levels from all facility operations, generators, cooling equipment, and HVAC systems at all property lines and at the nearest sensitive use. The study shall confirm compliance with the noise standards in Section 8.
(6) Water Consumption and Sustainability Plan: A plan demonstrating: (i) total projected daily, peak, and annual water demand; (ii) the proposed cooling technology (open-loop systems are prohibited — see Section 9); (iii) evidence that the proposed water demand will not impair the water supply of White County or surrounding communities; (iv) compliance with Georgia EPD water withdrawal permitting requirements; and (v) strategies for minimizing water consumption and responding to drought conditions.
(7) Groundwater Impact Assessment: An analysis of the potential impacts of data center operations on groundwater resources within White County, including testing of all active wells within one-quarter (1/4) mile of the site boundary by a licensed hydrogeologist, with results provided to the County and to all affected well owners prior to approval.
(8) Energy Consumption and Power Infrastructure Plan: A plan demonstrating: (i) peak and average electricity demand in megawatts; (ii) the proposed power source(s) and service provider(s); (iii) will-serve letters from the electric utility confirming capacity availability; (iv) the location, design, and screening of any on-site substations or transmission infrastructure; and (v) strategies for on-site energy generation, storage, or efficiency that reduce reliance on the regional grid.
(9) Transmission Line Impact Assessment: An assessment identifying all new or upgraded transmission lines required to serve the facility, including environmental impacts, tree removal, and impacts on adjoining properties and public rights-of-way.
(10) Traffic Impact Study: A traffic impact study prepared by a licensed Georgia professional engineer in accordance with GDOT standards, analyzing projected traffic volumes (construction and operational phases), impacts on adjacent roads and intersections, and identifying all road improvements and dedications required
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
to serve the facility. All road improvements identified as required shall be provided at the sole expense of the applicant.
(11) Erosion and Sedimentation Control Plan: An Erosion and Sedimentation Control Plan prepared by a certified design professional and approved by the White County Soil and Water Conservation District prior to any land disturbance, in full compliance with the Georgia Erosion and Sedimentation Act, O.C.G.A. § 12-7-1 et seq. The plan shall demonstrate measures to protect all streams, wetlands, and adjacent properties from sediment and construction runoff during all phases of development.
(12) Developer Infrastructure Agreement: A draft Developer Infrastructure Agreement, reviewed and approved by the County Attorney prior to scheduling of any public hearing, identifying all public infrastructure improvements (roads, drainage improvements, utility extensions, emergency service requirements) necessary to serve the proposed facility, and committing the applicant to fund and construct all such improvements entirely at applicant's expense with no cost to White County or its taxpayers. See Section 10.
(13) Hazardous Materials Management Plan: A plan for the identification, storage, handling, containment, and emergency response for all hazardous materials to be used or stored on-site, including diesel fuel, battery systems, coolants, refrigerants, and transformer oils, in compliance with federal and state law.
(14) Buffer Landscaping Plan: A Buffer Landscaping Plan identifying the location and composition of all required vegetated buffers pursuant to Section 7.4, including species selection, planting sizes, and maintenance commitments. This plan shall be prepared by a qualified landscape professional and shall demonstrate that all required buffers will achieve full screening within five (5) years of planting. White County has no general tree preservation or reforestation ordinance; buffer requirements herein are established solely by this Ordinance as a condition of Special Use Permit approval.
(15) Emergency Action Plan: A comprehensive emergency action plan coordinated with White County Emergency Management Agency, Fire Department, and Sheriff's Office, including procedures for facility emergencies, hazardous material releases, active threat response, and protocols for utility outages.
(16) Security Plan: A plan demonstrating controlled access, perimeter security, 24/7 monitoring, video surveillance of all access points and perimeter areas, and coordination protocols with White County law enforcement.
(17) Decommissioning Plan and Financial Assurance: See Section 12 of this Ordinance.
(18) Community Benefit Agreement (Large Facilities): For any Major Data Center or Data Center Campus, a proposed Community Benefit Agreement as described in Section 6.
4.3 Findings Required for Approval. The Board of Commissioners shall not approve a Special Use Permit for a data center unless it finds, based on the record, that:
a. The proposed use is consistent with the White County Comprehensive Plan;
b. The proposed use meets all standards and requirements of this Ordinance;
c. The proposed use will not adversely impact the health, safety, and welfare of adjacent property owners or the public;
d. The proposed use will not overburden public infrastructure, utilities, emergency services, or the road network;
e. The proposed use is compatible with the rural character of White County and the surrounding area;
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
f. All costs to the County and its taxpayers have been identified and will be borne by the applicant; and
g. The applicant has demonstrated financial capability to operate the facility and complete decommissioning.
SECTION 5. CRYPTOCURRENCY MINING FACILITIES
5.1 Legislative Findings. The White County Board of Commissioners adopts the following findings as the basis for the regulation of cryptocurrency mining facilities:
(a) Energy Intensity Without Proportionate Community Benefit. Cryptocurrency mining operations consume extraordinary quantities of electricity — typically 10 to 100 times more power per square foot than conventional industrial uses — while generating as few as three to five permanent local jobs per facility regardless of size.
This power-to-employment ratio imposes disproportionate costs on public infrastructure relative to the economic benefit returned to the local community.
(b) Persistent Noise Nuisance. Cryptocurrency mining operations generate continuous, uninterrupted mechanical noise from cooling fans and HVAC systems 24 hours per day, 365 days per year, with reported source levels of 80–95 dB(A). This constant noise profile distinguishes crypto mining from conventional industrial uses that have periods of reduced or no activity and renders it fundamentally incompatible with the rural residential and agricultural character of White County.
(c) Distinct Use from General Data Centers. Cryptocurrency mining performs repetitive mathematical computations solely to generate speculative digital currency tokens and provides no computing service, data storage, or communications infrastructure to any identifiable end user. This operational and economic distinction from general data centers justifies distinct and more stringent regulatory treatment.
(d) High Abandonment Risk. Cryptocurrency mining operations are uniquely susceptible to rapid economic obsolescence driven by cryptocurrency market value fluctuations and algorithm changes, resulting in facility abandonment and potential environmental remediation obligations for local governments.
(f) Incompatibility with White County's Rural Character. White County's Comprehensive Plan and Land Use Regulations prioritize preservation of agricultural uses, residential neighborhoods, outdoor recreation, and the tourism economy centered on the Chattahoochee River and North Georgia mountains. The operational profile of cryptocurrency mining is fundamentally incompatible with these goals
5.2 Permitted by Special Use Permit — Industrial District Only. Based on the findings in Section 5.1, and pursuant to White County's zoning authority under O.C.G.A. § 36-66-1 et seq. and Appendix C of the White County Code of Ordinances, cryptocurrency mining facilities shall be classified as a use requiring a Special Use Permit within the Industrial (I) zoning district only. Cryptocurrency mining facilities are expressly prohibited in all other zoning districts. No cryptocurrency mining facility shall be permitted without full compliance with every standard set forth in Section 5.3. Each standard in Section 5.3 constitutes an independent, sufficient basis for denial of a Special Use Permit.
5.3 Special Use Permit Standards — Cryptocurrency Mining Facilities. No Special Use Permit for a cryptocurrency mining facility shall be approved unless the applicant demonstrates full compliance with each of the following standards. Each standard is independently sufficient for denial. All costs of demonstrating compliance, including
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
independent third-party review retained by White County at the applicant's expense, shall be borne entirely by the applicant.
(a) Maximum Noise — 35 dB(A) at All Hours. All operations, including all cooling fans, HVAC systems, and electrical equipment, shall produce a maximum sound level of thirty-five (35) dB(A), measured continuously at every point along the property line, at all hours of the day and night, seven days a week. This standard reflects both the continuous 24/7 noise character of cryptocurrency mining operations and the need to protect White County's rural nighttime ambient environment
(b) Minimum Setback — 5,280 Feet (One Mile in a straight line) from All Sensitive Uses. No cryptocurrency mining facility or any component thereof shall be located within one (1) mile of the nearest residential dwelling, agricultural use, school, daycare facility, place of worship, hospital, park, campground, or publicly accessible recreational area, measured from the facility property line to the nearest point of the sensitive use
(c) Employment Ratio Requirement. The applicant shall demonstrate, by binding written commitment enforceable as a condition of the Special Use Permit, that the proposed facility will employ a minimum of one (1) full-time equivalent White County resident per fifty (50) kilowatts of approved peak electrical demand, maintained throughout the life of the permit. Failure to maintain the required employment ratio in any calendar year shall constitute a violation of the Special Use Permit subject to revocation
(d) Grid Self-Sufficiency Requirement. The applicant shall provide written certification from the serving electric utility, in a form satisfactory to the White County Attorney, that: (i) the proposed facility can be fully served at its peak electrical demand without requiring construction of any new transmission line, substation, distribution infrastructure, or generation capacity; (ii) no cost of any infrastructure upgrade or expansion attributable to the facility will be recoverable from other ratepayers of any class; and (iii) service to existing customers will not be degraded in reliability or cost as a result of the proposed facility. The serving utility's certification shall be irrevocable for the life of the Special Use Permit.
(e) Water — Zero Consumptive Use. The facility shall demonstrate, through independent engineering analysis approved by the County, that it will consume zero
(0) gallons of water per day from any source — including municipal water, wells, surface water, or reclaimed water — for any cooling, humidification, or operational purpose. All cooling shall be accomplished by closed-cycle air-cooled systems only
(f) Decommissioning Bond — 200% of Estimated Costs. Prior to issuance of any building permit, the applicant shall provide financial assurance in the amount of two hundred percent (200%) of the independently estimated cost of full decommissioning and site restoration, reflecting the heightened abandonment risk documented in Section 5.1(d). The financial assurance shall be in a form approved by the White County Attorney and shall be reviewed and adjusted annually
(g) Noise Monitoring — Continuous Real-Time Public Reporting. Prior to commencing operations, the applicant shall install continuous real-time noise monitoring at all property line locations, with data transmitted live and publicly accessible on a County-hosted web portal, updated no less frequently than every fifteen (15) minutes. Any reading exceeding 35 dB(A) at any property line location for any fifteen-minute period shall constitute a self-reported violation subject to immediate enforcement under Section 15
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
(h) Annual Independent Audit. The applicant shall, at its sole expense, retain a licensed independent engineer approved by the County to conduct an annual audit of compliance with each standard in Section 5.3. The audit report shall be submitted to the White County Planning Director by January 31 of each year. White County may, at any time and at the operator's expense, commission its own independent verification of any compliance claim.
(i) Community Benefit Agreement — Enhanced Requirements. For any cryptocurrency mining facility, regardless of size, the applicant shall execute a Community Benefit Agreement with White County prior to approval that includes: (i) all requirements of Section 6.2 applicable to Major Data Centers; (ii) quarterly (not annual) reporting of all compliance metrics; (iii) a dedicated community liaison available 24 hours per day, 7 days per week, reachable by direct telephone, to receive and respond to noise or operational complaints within two (2) hours; and (iv) a $500,000 cash escrow held by White County, separate from and in addition to the decommissioning bond, as a readily accessible fund for immediate remediation of any nuisance condition
5.4 Conversion Prohibition. Any data center or industrial facility operating under any permit issued by White County that converts, repurposes, or operates any portion of its approved floor area, electrical capacity, or equipment for cryptocurrency mining operations shall be deemed in violation of its Special Use Permit and subject to all enforcement remedies under Section 15, including immediate revocation. The operator shall bear all costs of inspection, investigation, and enforcement.
5.5 Definition. The definition of 'Cryptocurrency Mining Facility' in Section 2 of this Ordinance applies to this Section in its entirety. Any ambiguity as to whether a proposed use constitutes a cryptocurrency mining facility shall be resolved by the White County Planning Commission, whose determination shall be final subject to appeal to the Board of Commissioners in accordance with Article XVIII of the White County Land Use Regulations.
SECTION 6. COMMUNITY MEETINGS AND COMMUNITY BENEFIT REQUIREMENTS
6.1 Community Meetings. Prior to any public hearing before the White County Planning Commission or Board of Commissioners, the applicant shall conduct two (2) separate community meetings as follows:
a. Meetings shall be conducted within White County at a publicly accessible location determined in consultation with the Community and Economic Development Director;
b. Meetings shall be held between 5:00 p.m. and 8:00 p.m. on a weekday and shall be at least twenty-one (21) days apart;
c. Written notice of each meeting shall be mailed by certified mail to all property owners within 1,500 feet, in a straight line, of the subject property at least fourteen
(14) days before each meeting;
d. Notice shall be published in a newspaper of general circulation in White County at least seven (7) days before each meeting;
e. The applicant shall post signage on the property along all road frontages at least fourteen (14) days before each meeting, with each sign no less than twenty
(20) square feet and legible from twenty-five (25) feet;
f. A representative of the applicant with full decision-making authority over site design shall attend each meeting in person; and
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
g. The applicant shall submit a written certification of compliance with all community meeting requirements before any public hearing is scheduled.
6.2 Community Benefit Agreement. For any Major Data Center or Data Center Campus, the applicant shall, as a condition of Special Use Permit approval, enter into a Community Benefit Agreement (CBA) with White County that shall include, at minimum:
a. Annual reporting on water usage, energy consumption, noise levels, and employment;
b. Local hiring commitments during construction and operations phases;
c. Funding for emergency services training and equipment directly attributable to the facility;
d. Road maintenance and improvement commitments along all haul routes and access corridors;
e. Environmental monitoring and reporting obligations; and
f. A community liaison designated by the operator and available to respond to resident complaints within twenty-four (24) hours.
SECTION 7. DEVELOPMENT STANDARDS — SITE AND BUILDING
7.1 Minimum Lot Requirements.
a. Minimum lot area: Fifteen (15) acres for any data center.
b. Minimum lot width: Two hundred fifty (250) feet of frontage on a paved public road.
c. Maximum lot coverage (all impervious surfaces): Sixty (60) percent.
7.2 Building Height. Maximum building height: Fifty (50) feet, inclusive of rooftop mechanical equipment. No rooftop equipment shall project above the parapet without full visual screening. Antenna and communication towers shall comply with the White County Wireless Telecommunications Facilities Ordinance.
7.3 Setbacks.
a. Minimum setback from all property lines: Two Hundred Fifty (250) feet.
b. Minimum setback from any public right-of-way: One Hundred (100) feet.
c. Minimum setback from any Sensitive Use: Two thousand six hundred forty (2,640) feet (one-half mile in a straight line), measured from the property line.
d. Minimum setback for all substations, generators, fuel storage, and cooling towers: Five hundred (500) feet from all property lines and one thousand (1,000) feet, in a straight line, from any Sensitive Use.
7.4 Buffer Requirements.
a. Where a data center site abuts any residentially zoned or residentially used property: minimum undisturbed natural forested buffer of five hundred (500) feet, measured from the shared property line.
b. Where a data center site abuts any non-residential property: minimum undisturbed natural forested buffer of one hundred fifty (150) feet, measured from the shared property line.
c. Along all road frontages: minimum opaque vegetated buffer of one hundred
(100) feet consisting of at least three (3) staggered rows of evergreen trees and shrubs of at least four (4) genera, planted at a minimum of six (6) feet in height and designed to achieve full opaqueness to a height of twenty (20) feet within five (5) years.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
d. All required buffers shall remain in perpetuity as a condition of the Special Use Permit. Removal of buffer vegetation shall constitute a violation of the Permit.
7.5 Architectural Standards.
a. All building facades visible from any public right-of-way or from any adjacent property shall be designed to minimize perceived mass and visual impact. Flat, uninterrupted metal or blank concrete wall facades are prohibited.
b. Facades visible from public rights-of-way shall incorporate at least two (2) of the following: brick, stone, or architectural precast concrete panels; architectural metal panels with non-reflective finish; or high-quality fiber cement panels.
c. Facades visible from public rights-of-way shall include fenestration, recesses, projections, or material articulation at intervals not to exceed fifty (50) feet.
d. Exterior building colors shall be limited to earth tones, muted tones, or subdued natural colors. Fluorescent, metallic, or high-contrast colors are prohibited.
e. All loading docks, overhead doors, and service areas shall be oriented to the side or rear of the property, away from public roads.
f. All rooftop mechanical equipment shall be fully screened from view from any public road or adjacent property.
7.6 Fencing and Perimeter Security.
a. Perimeter fencing is required. Decorative metal fencing shall be used along road frontages.
b. Barbed wire, razor wire, concertina wire, and similar anti-climb features are prohibited along any frontage visible from a public road. Such features may only be used on interior perimeter fencing not visible from roads or adjacent properties.
c. Minimum fence height: eight (8) feet.
7.7 Buffer Landscaping Maintenance. All buffer plantings required by Section 7.4 shall be maintained by the operator in a healthy growing condition throughout the life of the Special Use Permit. Dead or damaged plantings shall be replaced within one (1) growing season. Failure to maintain required buffers shall constitute a violation of the Special Use Permit. [Note: White County has no general tree preservation or reforestation ordinance.
Buffer requirements are established solely by this Ordinance as Special Use Permit conditions.]
SECTION 8. NOISE STANDARDS
8.1 Maximum Permissible Sound Levels. All data center operations, equipment, generators, cooling systems, and HVAC systems shall comply with the following maximum sound levels as measured at the property line:
a. Daytime hours (7:00 a.m. to 10:00 p.m.): Fifty-five (55) dB(A) or ten (10) dB(A) above measured ambience, whichever is less restrictive.
b. Nighttime hours (10:00 p.m. to 7:00 a.m.): Forty-five (45) dB(A) or ten (10) dB(A) above measured ambient, whichever is less restrictive.
c. For any data center within 1,500 feet of a Sensitive Use: the maximum sound level at the nearest Sensitive Use property line shall not exceed forty (40) dB(A) at any hour.
8.2 Generator Testing and Operation.
a. Routine generator testing is limited to Monday through Friday, 9:00 a.m. to 4:00 p.m., excluding state and federal holidays.
b. Generator testing shall not exceed eight (8) hours per month total.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
c. All generators shall be fully enclosed within sound-attenuating enclosures and shall comply with EPA Tier 4 emission standards.
d. Generators may operate without hour restrictions during documented bona fide utility outages only.
8.3 Noise Monitoring.
a. Prior to issuance of a Certificate of Occupancy, the applicant shall submit a post-construction noise compliance study prepared by a licensed professional engineer demonstrating compliance with Section 8.1.
b. Continuous noise monitoring shall be installed and operated 24 hours per day, 365 days per year, at all property lines nearest to Sensitive Uses.
c. Noise monitoring data and an annual compliance report shall be submitted to the White County Community and Economic Development Director by January 31 of each year.
d. White County may retain an independent licensed acoustical engineer at the operator's expense to verify noise compliance at any time.
8.4 Vibration. No data center operation shall generate perceptible vibration at any property line. All vibration-producing equipment shall be mounted on vibration-isolating supports.
SECTION 9. WATER USE AND ENVIRONMENTAL STANDARDS
9.1 Cooling System Requirements. Open-loop and evaporative cooling systems that discharge water to the atmosphere are prohibited. All liquid cooling systems shall utilize closed-loop or equivalent water-conserving technologies. Applicants proposing alternative cooling technologies shall demonstrate equivalent or superior water conservation performance through independent engineering analysis approved by the County.
9.2 Potable Water Prohibition. The use of White County's potable water supply for data center cooling purposes is prohibited. Data centers shall not connect to municipal or county potable water systems for cooling unless an alternative supply is upon approval of the White County Water Authority.
9.3 Water Conservation Plan. All data centers shall submit and comply with an approved Water Conservation Plan that:
a. Demonstrates that water usage will not impair county or municipal water supply
b. Establishes binding water use limits expressed in gallons per day;
c. Includes contingency measures to reduce or cease water-intensive operations during drought conditions declared by the Georgia EPD;
d. Requires annual reporting of water usage as specified in Section 13; and
e. Addresses pre-treatment of all wastewater prior to any discharge to a permitted wastewater system.
9.4 Erosion and Sedimentation Control. All land disturbance activity associated with a data center facility shall comply fully with the Georgia Erosion and Sedimentation Act, O.C.G.A. § 12-7-1 et seq., and all applicable regulations of the Georgia Environmental Protection Division. An Erosion and Sedimentation Control Plan shall be approved by the White County Soil and Water Conservation District prior to the issuance of any land disturbance permit. [Note: White County does not maintain a local stormwater management ordinance or program. All erosion and sediment control requirements referenced herein are grounded solely in state law.]
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
9.5 Wetlands, Streams, and Buffers. No data center facility or any accessory structure shall be located within any state-regulated stream buffer as defined under the Georgia Erosion and Sedimentation Act or the Georgia Shoreline Protection Act. All applicable Georgia EPD permits shall be obtained prior to any land disturbance.
9.6 Air Quality. All diesel generators and other combustion equipment shall comply with applicable EPA emission standards. No open burning of vegetation, waste, or demolition debris shall occur on site. Air quality permits required by Georgia EPD shall be obtained and maintained throughout the life of the facility.
SECTION 10. INFRASTRUCTURE AND FISCAL IMPACT REQUIREMENTS
10.1 Infrastructure Cost Responsibility. It is the policy of White County that all public infrastructure costs directly attributable to a proposed data center shall be borne by the applicant and shall not be shifted to White County taxpayers or existing utility ratepayers.
As a condition of Special Use Permit approval, the applicant shall:
a. Fund all off-site road improvements identified in the required Traffic Impact Study, including turn lanes, widening, intersection improvements, signalization, and any necessary bridge upgrades, prior to issuance of any Certificate of Occupancy;
b. Fund all electric utility infrastructure upgrades, substation expansions, and transmission line extensions required to serve the facility, as documented by will-serve letters from the applicable utility;
c. Fund all water, sewer, or drainage infrastructure extensions or upgrades required to serve the facility; and
d. Execute a Developer Infrastructure Agreement with White County, reviewed and approved by the County Attorney, prior to issuance of any building permit.
10.2 Developer Infrastructure Agreement. White County does not currently maintain a Development Impact Fee program. Accordingly, infrastructure cost recovery shall be accomplished exclusively through the Developer Infrastructure Agreement required by Section 10.1(d) and Section 4.2(12). The Developer Infrastructure Agreement shall be a binding contractual obligation running with the land, recorded in the White County deed records, and enforceable by the County against the operator and all successors in interest. No building permit shall be issued until the Developer Infrastructure Agreement has been fully executed and recorded.
10.3 Emergency Services. The applicant shall reimburse White County for all costs of specialized emergency response training, equipment, and planning directly attributable to the proposed facility, as determined by the White County Public Safety Director. Such costs shall be paid annually pursuant to the Community Benefit Agreement required by Section 6.2.
10.4 Road Maintenance. The applicant shall maintain all designated haul routes and access roads to a standard acceptable to the White County Public Works Director during all phases of construction and shall restore all county roads damaged by construction traffic to their pre-construction conditions within thirty (30) days of construction completion.
10.5 Utility Coordination. Prior to issuance of any land disturbance permit, written will-serve letters and approved engineering plans shall be submitted from all applicable utility providers, including electric, water, sewer (if applicable), and telecommunications service providers.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
SECTION 11. LIGHTING STANDARDS
11.1 All exterior lighting shall utilize full-cutoff, fully shielded (zero uplight) fixtures designed to prevent light trespass and preserve the existing rural night sky.
11.2 Light fixtures shall be located at a minimum distance of four (4) times the mounting height from all adjacent property lines.
11.3 Maximum mounting height of site lighting: twenty (20) feet above finished grade.
This is a stricter standard than the forty-five (45) foot maximum applicable to non-residential uses under Appendix C, Section 518; such stricter standard is imposed herein as a Special Use Permit condition to protect adjacent residential and rural uses.
11.4 Security lighting shall be motion-activated wherever possible and shall be directed inward toward the facility.
SECTION 12. DECOMMISSIONING, FINANCIAL ASSURANCE, AND SITE RESTORATION
12.1 Decommissioning Plan Required. Prior to issuance of any building permit for a data center, the applicant shall submit a Decommissioning Plan for approval by White County.
The Decommissioning Plan shall include, at minimum:
a. A detailed timeline for closure, equipment removal, dismantling infrastructure, and site restoration;
b. Procedures for the safe removal and disposal of all data center equipment, backup generators, fuel storage tanks, substations, transformers, battery systems, cooling equipment, and all associated structures;
c. A comprehensive hazardous materials management plan for all materials to be removed, including diesel fuel, batteries, refrigerants, coolants, transformer oils, and all other hazardous or regulated substances;
d. A site remediation plan addressing soil and groundwater testing, identification of any contamination, and remediation procedures;
e. A site restoration plan restoring the property to a safe, stable, and regraded condition suitable for future permitted use, including re-grading, erosion control, and reforestation or revegetation; and
f. An estimate of total decommissioning and restoration costs prepared by a qualified independent professional engineer.
12.2 Financial Assurance. Prior to the issuance of any building permit, the applicant shall provide financial assurance in a form approved by the White County Attorney, in an amount equal to two hundred percent (200%) of the estimated cost of decommissioning and site restoration. Acceptable forms include:
a. A performance bond from a surety company licensed to do business in Georgia;
b. An irrevocable letter of credit from a federally insured financial institution;
c. An escrow account held by a federally insured financial institution; or
d. Such other forms of financial security as approved by the Board of Commissioners.
The financial assurance shall be reviewed and adjusted every five (5) years to reflect current costs. The financial assurance shall remain in effect until White County certifies that all decommissioning, hazardous material removal, and site restoration have been completed in accordance with the approved Decommissioning Plan.
12.3 Abandonment. A data center shall be deemed abandoned if operations cease for a period of twelve (12) six (6) consecutive months, excluding temporary shutdowns for maintenance. Upon a finding of abandonment, the Board of Commissioners may require
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
immediate implementation of the Decommissioning Plan and may draw upon the financial assurance to fund decommissioning activities.
12.4 Notice of Cessation. The operator shall provide written notice to the White County Planning Department at least six (6) months prior to the anticipated permanent cessation of operations.
12.5 Decommissioning Timeline. Upon cessation of operations or a finding of abandonment, decommissioning activities shall commence within six (6) months and shall be completed within twenty-four (24) months. Extensions may be granted by the Board of Commissioners for good cause shown.
12.6 Bond Call Penalty. If White County is required to draw upon the financial assurance to complete decommissioning, the former operator shall be liable for an additional penalty equal to fifteen percent (15%) of the bond amount to cover administrative costs incurred by the County.
SECTION 13. ANNUAL REPORTING AND MONITORING REQUIREMENTS
13.1 All operating data center facilities shall submit an Annual Compliance Report to the White County Community and Economic Development Director by January 31 of each year. The report shall include:
a. The facility name, address, owner, and operator of record;
b. Total gross floor area and any changes from prior year;
c. Total annual and average daily electricity consumption (kWh and peak MW);
d. Percentage of energy derived from renewable sources;
e. Total annual and average daily water consumption (gallons), by source;
f. Total annual wastewater discharged (gallons) and method of treatment;
g. Results of all noise monitoring for the preceding year;
h. Documentation of all generator testing events, including date, duration, and noise levels recorded;
i. Any changes in ownership, operator, or operational use;
j. Total ad valorem taxes paid to White County for the preceding year;
k. Number of full-time equivalent employees employed locally; and
l. A certification, signed under penalty of perjury, that the facility is in compliance with all terms and conditions of the Special Use Permit.
13.2 White County reserves the right to conduct unannounced on-site inspections of any data center facility at reasonable times to verify compliance with the terms and conditions of the Special Use Permit and this Ordinance.
13.3 Failure to submit the Annual Compliance Report by the required date shall constitute a violation of the Special Use Permit and subject the operator to the penalties set forth in Section 15.
SECTION 14. CHANGE OF USE AND CONVERSION
14.1 Any conversion of an existing data center facility to any other high-intensity computing or digital processing use, including but not limited to cryptocurrency mining operations, artificial intelligence computing facilities, large-scale cloud computing, colocation centers, or similar high-density computing operations not included in the original Special Use Permit approval, shall require a new Special Use Permit.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
14.2 Any expansion of a data center that increases gross floor area, increases power demand by more than five (5) percent above the approved level, or increases water consumption by more than five (5) percent above the approved level, shall require an amendment to the Special Use Permit.
14.3 Any transfer of ownership or change of operator of an approved data center shall be reported to White County within sixty (60) days, and the new owner or operator shall assume all obligations under the Special Use Permit, Community Benefit Agreement, and financial assurance instruments.
SECTION 15. VIOLATION AND ENFORCEMENT
15.1 Any violation of this Ordinance, including failure to comply with any term or condition of an approved Special Use Permit, shall be subject to enforcement by White County through any combination of the following:
a. Civil fines of not less than five hundred dollars ($500) and not more than five thousand dollars ($5,000) per day per violation;
b. Revocation or suspension of the Special Use Permit by the Board of Commissioners after notice and opportunity to be heard;
c. Revocation of building permits or Certificate of Occupancy;
d. Injunctive relief sought by the White County Attorney in the Superior Court of White County; and
e. Drawing upon the financial assurance to fund corrective actions.
15.2 Each day a violation continues shall constitute a separate violation.
15.3 Nothing in this Section shall limit White County's right to pursue any other remedy available at law or in equity.
SECTION 16. NON-WAIVER OF REQUIREMENTS
16.1 The Board of Commissioners shall not waive, reduce, or modify the minimum setback, buffer, noise, water, financial assurance, or decommissioning requirements of this Ordinance through the Special Use Permit process or through any condition of approval. These standards are established as minimum requirements for the protection of public health, safety, and welfare and are not subject to administrative waiver.
16.2 The Board of Commissioners may, at its sole discretion, impose conditions on a Special Use Permit that are more stringent than the minimum standards set forth herein, based on findings specific to the proposed project.
SECTION 17. SEVERABILITY
If any section, subsection, sentence, clause, or phrase of this Ordinance is for any reason held to be invalid or unconstitutional by a court of competent jurisdiction, the decision shall not affect the validity of the remaining portions of this Ordinance. The Board of Commissioners hereby declares that it would have adopted this Ordinance and each section, subsection, sentence, clause, or phrase thereof, irrespective of the fact that any one or more sections, subsections, sentences, clauses, or phrases might be declared unconstitutional.
AN AMENDMENT TO THE WHITE COUNTY LAND USE REGULATIONS
DRAFT ORDINANCE ONLY. PUBLIC HEARING REGARDING THIS ORDINANCE TO BE
HELD 9/29/26 AT 1235 HELEN HIGHWAY, CLEVELAND, GA 30528 @ 6:30 P.M.
SECTION 18. EFFECTIVE DATE
This Ordinance shall become effective upon passage and adoption by the White County Board of Commissioners in accordance with applicable legal requirements.