Lilburn Downtown Development Authority: reunión ordinaria, 21 de octubre de 2026

7 páginas

Estas son las actas tal como las publicó Lilburn Downtown Development Authority, leídas del archivo en su propio sitio web. Georgia Commons es independiente y no está afiliado a Lilburn Downtown Development Authority.

Copiar para un LLM, Ver en Markdown y Enviar a una IA usan la versión en Markdown, en inglés: el resumen que escribió Georgia Commons, bajo un encabezado que lo indica, y luego el registro tal como se publicó. Ver texto sin formato es solo el registro.

Registros de esta reunión

Cada enlace abre el sitio web o el portal de reuniones del propio órgano.

Resumen

Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.

Este resumen está en inglés. No se ha escrito un resumen en español de estas actas.

Authority approves three Gwinnett County water and sewer agreements 7-0 and agrees to closer communication with the city on downtown projects.

The authority held a work session followed by a regular meeting. In the regular meeting it approved Resolution No. 2026-14 by a 7-0 vote, covering three agreements with Gwinnett County Department of Water Resources for sanitary sewer, water main and metering devices at the assemblage; the agreements carry no cost to the authority. It also approved the agenda and the September 8, 2026 minutes. In the work session, staff reported that the parking deck has its certificate of occupancy, a ribbon cutting is planned for December 2, 2026, and the stormwater vault cost share was set at 81/19. Staff also covered Main Street design plans and a structural analysis of 57 Railroad Avenue, with an estimated cost of at least $150,000. Board members raised concerns about communication, and the board agreed to have a rotating member attend the city's weekly staff meeting and to receive the city's weekly update. The board met in closed session on real estate.

Temas tratados: Resolution 2026-14 water and sewer agreements; parking deck certificate of occupancy; The Porchline apartments; stormwater vault cost sharing; Main Street flush street design; 57 Railroad Avenue structural analysis; DDA and city communication; economic developer position; Main Street and US 29 development; bond for title and PILOT.

Decisiones que constan en las actas (3)

Después de cada decisión va la oración de las actas que la registra, copiada palabra por palabra, en inglés.

  1. Resolution 2026-14 approving three Gwinnett County water resources agreements for sewer, water main and metering at the assemblage

    Aprobado7-0

    Las actas: “Elmer Nash made a motion to approve Resolution No. 2026-14 and to authorize Chairman DeArmon a to sign each of the three agreements.”

    Leer este punto en las actas

  2. Communication steps: rotating board member at city weekly staff meeting and inclusion on weekly council update

    Aprobado

    Las actas: “The Board agreed to move forward with both of these communication improvements.”

    Leer este punto en las actas

  3. Minutes of the September 8, 2026 special called meeting

    Aprobado5-0

    Las actas: “Scott Mecredy made a motion to approve the minutes.”

    Leer este punto en las actas

Puntos del orden del día (4)

Encontrados en las actas por sus encabezados. Cuando se muestra un resultado, se leyó por regla de las propias palabras del punto: es una guía del texto, no parte del registro.

  1. 1. Financial Report – September 30, 2026Una presentación
  2. 2. Update – DDA PropertyUna presentación
  3. 3. Update – Lilburn Community Improvement District and Lilburn Community PartnershipUna presentación
  4. 4. Update – Development ActivitiesUna votación

Las respuestas las escribe la IA a partir de este documento, que está en inglés, y cada cita se verifica con él. No es asesoría legal.

Las actas

Tal como se publicó en cityoflilburn.com, leído el 12 de noviembre de 2026. Nada de lo que sigue lo escribió Georgia Commons. El registro se muestra en inglés, tal como se publicó.

Lilburn Downtown Development Authority Regularly Scheduled Meeting DRAFT Minutes October 21, 2026 6:30 PM Work Session Room – Lilburn City Hall Work Session Agenda 6:30 P.M.

Call to Order Chairman Mark DeArmon called the October 21st Work Session to order at 6:33 pm.

Board members present: Mark DeArmon, Joe Nocera, Elmer Nash, Hugh Wilkerson, Tom Mills, Scott Mecredy, and Amy Valdez Barker. No members were absent.

Old Business

1. Financial Report – September 30, 2026

Tom Mills provided the financial report for September 30, 2026. The starting balance was $435,445.42. Revenues included a lease payment of $3,500.00 from CRC Restaurant Group for the Agavero Parkside. Tom noted that the CRC rent follows a seasonal schedule and will decrease toward December, with the lowest payments occurring in that month. Expenses included a payment of $45.55 to Georgia Power. The ending balance was $438,899.87. The bank statement was available for Board review.

2. Update – DDA Property

Andrew Thompson, Assistant City Manager, provided updates on the parking deck and The Porchline apartments, the Main Street design, and 57 Railroad Avenue.

Parking Deck and The Porchline Apartments: The DDA has received its Certificate of Occupancy (CO) for the parking deck. The deck is currently in a soft opening phase, with temporary wayfinding signage to be installed to direct the

public to its location. A ribbon cutting ceremony with RangeWater is planned for December 2, 2026. RangeWater is proceeding with a three-phase temporary CO process for The Porchline apartments. A remaining issue with the Gwinnett County Fire Marshal related to parking has been resolved, clearing the way for RangeWater to obtain its final CO upon completion of the phased process. The CDC (Certificate of Development Completion) package with the City is on its sixth submittal; City staff has been actively working with RangeWater to guide them through the process, which involves maintenance bonds, right-of-way work, and related items. Leasing interest is active. The Board requested that a RangeWater representative be invited to a future meeting to provide a leasing update, including occupancy projections and anticipated timeline to full capacity.

The previously discussed stormwater vault cost-sharing arrangement has been finalized at an 81/19 split, with RangeWater responsible for 81% and the DDA responsible for 19%, an improvement from the original 57/43 arrangement.

Main Street Design: Toole Design delivered 10% plans for the Main Street flush street design on September 21, 2026. The design covers the 0.77-acre parcel at 100 Main Street and the properties across the street, encompassing approximately 27 parcels with 25–35 foot storefronts fitting within the area. The next steps include utility coordination and progression to 30% plans. As part of utility coordination, the City is working to deconflict existing utilities with the proposed infrastructure and determine how to locate utility connections (such as water meters) to the rear of future buildings, potentially running new water lines along secondary streets. The Board was advised that an upcoming call with Toole Design will clarify which parcels can be built with a shared slab, which has implications for how vertical development is phased and financed. The DDA’s first action related to this design will likely be a property trade with the City, in which the DDA exchanges a portion of its 0.77-acre parcel for street right-of-way in order to properly align the 100-foot flush street corridor.

57 Railroad Avenue: The structural analysis of 57 Railroad Avenue has been received. Andrew Thompson indicated he is in the process of reviewing the full report. Initial estimates from the structural engineer indicate that bringing the building up to current standards would cost at least $150,000, though this figure requires further review to ensure all items are captured. The analysis was conducted under the assumption that half of the metal exterior cladding will be removed, and the structural improvements would address foundational and wind-load requirements for a building of this age. The analysis was funded through 2023 SPLOST funds, as the project has a potential transportation use (providing a roadway connection from First Avenue through the site to Railroad Avenue, consistent with the Toole Design master concept). The Board noted that the cost of eventual developer improvements would be separate from and in addition to the structural remediation cost, and that those costs would fall to a future developer or tenant. The construction fencing and staging equipment from the RangeWater project have been removed from the front of 57 Railroad Avenue.

The Board engaged in a substantive discussion about the DDA’s role in the planning process and transparency of communication. Several Board members expressed concern that decisions and studies related to DDA-owned properties

— including the funding and framing of the 57 Railroad structural analysis and the concept of running a road through the building as part of the Toole Design master concept — had not been sufficiently communicated to the Board in advance. Board members noted that while they support the collaborative vision for downtown Lilburn, they want to be genuine partners in the process rather than receive information after decisions have effectively been made.

Mayor Crist and City Manager Simpkins acknowledged the feedback, affirmed the importance of the partnership, and proposed a concrete step to improve communication: that a rotating DDA Board member be invited to attend the City’s weekly Tuesday morning staff meeting to stay informed on active projects and concepts being discussed. Chairman DeArmon accepted responsibility on behalf of the Board to establish a rotation schedule and ensure the information is shared with the full Board. City Manager Simpkins also offered to include the DDA on the weekly update that is currently sent to the City Council. The Board agreed to move forward with both of these communication improvements.

3. Update – Lilburn Community Improvement District and Lilburn Community Partnership

Mark DeArmon reported on his first in-person LCID Board meeting, which took place in October. He noted the following items from the meeting:

Economic Development Position: The City has posted a new Economic Developer position, a job description developed jointly by Andrew Thompson and Jenny Simpkins to fit Lilburn’s specific needs, combining the responsibilities of a department manager and project manager in a single role. Several applications have already been received. The Economic Developer will become a regular attendee at DDA meetings.

Retention Pond Landscaping: The LCID, in coordination with the City and TAD, has obtained an approved quote for two-phase landscaping of the stormwater retention pond in front of Bryson Park. Phase 1 will vegetatively stabilize and landscape the rim of the pond so that it is not visible from the road. The bottom of the pond cannot be disturbed until after the mandatory state inspection in August.

Work on Phase 1 is expected to begin within the next couple of weeks.

Rebecca, Communications Director, reported for the Lilburn Community Partnership (LCP):

LCP is preparing for holiday activities. LCP has been nominated for Best of Gwinnett in the nonprofit category. Voting is available on the Historic Wynne Russell House Facebook page and the City’s Facebook page.

4. Update – Development Activities

Jenny Simpkins, City Manager, provided the following update on development activity:

Commercial Development at Main and US 29: City staff met with Gwinnett County plan reviewers to assist private developers in moving their land disturbance permit (LDP) application toward approval. The developers are very close to receiving the LDP, with only a couple of remaining items outstanding.

Upon LDP approval, the developers will purchase the property from the current

owners. The proposed development, valued at approximately $7.5–8 million, includes approximately nine tenant spaces consisting of two to three sit-down restaurants, two to three walk-up restaurant spaces, and a hardscape with a water feature at the corner. The project is subject to the City’s design guidelines.

City staff also met with financial advisor Ed Wall to discuss the possibility of a bond for title and payment in lieu of taxes (PILOT) arrangement for the project. If the developers agree to fund the approximately $100,000 in legal fees required to structure the bond for title deal, staff anticipates bringing the matter to the DDA Board for consideration by the end of the year. The developers stand to save an estimated $1.5 to $2 million in property taxes over the life of the arrangement.

Updates from Mayor Crist Mayor Crist noted that the items on his update list had already been covered during the work session discussion. No additional updates were provided.

New Business

1. Approval of Resolution No. 2026-14, a Resolution approving three agreements between the Lilburn Downtown Development Authority and Gwinnett County Department of Water Resources for sanitary sewer installation, water main installation, and metering devices located at the assemblage. Approval authorizes the Chairman to sign each agreement.

Andrew Thompson explained that as part of the final approval process with Gwinnett County Water Resources, the DDA is required to execute three separate owner-developer agreements — one for the sanitary sewer installation, one for the water main installation, and one for the metering devices — covering the assemblage site. Each agreement includes a one-year warranty period and a dedication of the easement areas in which the respective facilities are located.

There is no cost to the DDA associated with these agreements; they are part of the county’s standard process for accepting the completed infrastructure facilities.

Public Comment A member of the public asked whether the DDA had paid for the structural analysis of 57 Railroad Avenue. Jenny Simpkins clarified that the analysis was funded through 2023 SPLOST funds because of the building’s potential use as a transportation corridor, and that the analysis was a conditional assessment of the building based on the assumption of removing half of the metal exterior and constructing a roadway through the site.

A member of the public asked for a brief explanation of the purpose and scope of an executive session. Chairman DeArmon explained that under Georgia law, a public body may close a meeting to the public only to discuss legal matters, personnel matters, or real estate transactions. All other business must be conducted in open session.

Executive Session At 7:24 pm, Chairman DeArmon asked for a motion to enter executive session. Amy Valdez Barker made a motion to enter executive session to discuss matters related to real estate. Tom Mills seconded. Motion passed. The Board entered executive session at 7:24 pm. Amy Valdez Barker made a motion to close the executive session. Tom Mills seconded. Motion passed. The executive session concluded at 8:13 pm.

Adjournment Chairman DeArmon adjourned the work session at 8:13 pm.

Meeting Agenda Immediately following work session Call to Order Chairman Mark DeArmon called the October 21, 2026 Regular Meeting of the Lilburn Downtown Development Authority to order at 8:13 pm. Board members present: Mark DeArmon, Joe Nocera, Elmer Nash, Hugh Wilkerson, Tom Mills, Scott Mecredy, and Amy Valdez Barker. No members were absent.

Approval of Agenda Chairman DeArmon asked for a motion to approve the agenda. Elmer Nash made a motion to approve the agenda. Joe Nocera seconded.

Motion passed 7-0.

Approval of Minutes

1. Approval of Minutes from the September 8, 2026, Special Called Meeting Chairman DeArmon presented the minutes from the September 8, 2026, Special Called Meeting for approval.

Scott Mecredy made a motion to approve the minutes. Amy Valdez Barker seconded. Chairman DeArmon called the vote. Members Mark DeArmon, Elmer Nash, Hugh Wilkerson, Tom Mills, and Amy Valdez Barker voted Aye. Scott Mecredy and Joe Nocera were absent from the September 8, 2026, meeting and therefore did not vote on the approval of those minutes.

Motion passed 5-0.

Old Business Chairman DeArmon summarized the Old Business items discussed during the Work Session, including updates on DDA property (parking deck, The Porchline apartments, Main Street design, and 57 Railroad Avenue), the Lilburn Community Improvement District, the Lilburn Community Partnership, and development activities at Main Street and US 29. There were no questions from Board members on Old Business.

New Business

1. Approval of Resolution No. 2026-14, a Resolution approving three agreements between the Lilburn Downtown Development Authority and Gwinnett County Department of Water Resources for sanitary sewer installation, water main installation, and metering devices located at the assemblage. Approval authorizes the Chairman to sign each agreement.

Chairman DeArmon asked for a motion. Elmer Nash made a motion to approve Resolution No. 2026-14 and to authorize Chairman DeArmon a to sign each of the three agreements. Joe Nocera seconded.

Motion passed 7-0.

Adjournment Elmer Nash made a motion to adjourn the meeting. Tom Mills seconded. All in favor.

The Regular Meeting of the Lilburn Downtown Development Authority was adjourned at 8:16 pm.

Approved this ______ day of _____________, 2026.

________________________________ Mark DeArmon, DDA Chair ________________________________ Anja Peay, DDA Secretary

As set forth in the Americans with Disabilities Act of 1990, the City of Lilburn does not discriminate based on disability in the admission or access to, or treatment or employment, in its programs or activities. The City Clerk has been designated to coordinate compliance with the non-discrimination requirements contained in section 35.107 of the Department of Justice regulations, information concerning the provisions of the Americans with Disabilities Act, and the rights provided thereunder.

The City of Lilburn will assist citizens with special needs given proper notice. Any requests for reasonable accommodations required by individuals to fully participate in any open meeting, program, or activity of the City of Lilburn should be directed to the City Clerk, 340 Main Street, Lilburn, GA 30047, telephone number 770-921-2210.

Legible por máquinas https://georgiacommons.org/meetings/2026-10-21/lilburn-downtown-development-authority.md · https://georgiacommons.org/meetings/local/index.md · MCP https://mcp.georgiacommons.org/mcp