Burke County · Ordenanza de zonificación
Part II - CODE OF ORDINANCES / Chapter 26 - LAND DEVELOPMENT CODE / Article III - PROTECTION OF NATURAL FEATURES AND RESOURCES
26-3.02.14. Permit procedures.
Sobre este texto
- As published by Municode, current through 2025-10-14
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Application for a development permit shall be made to the flood plain administrator on forms furnished by the community prior to any development activities, and may include, but not be limited to the following: Plans in duplicate drawn to scale showing the elevations of the area in question and the nature, location, dimensions, of existing or proposed structures, earthen fill placement, storage of materials or equipment, and drainage facilities. Specifically, the following information is required:
(a) Application stage.
(1) Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures;
(2) Elevation in relation to mean sea level to which any non-residential structure will be flood-proofed;
(3) Design certification from a registered professional engineer or architect that any proposed non-residential flood-proofed structure will meet the floodproofing criteria in section 26-3.02.18(b) below;
(4) Description of the extent to which any watercourse will be altered or relocated as a result of the proposed development.
(b) Construction stage.
(1) For all new construction and substantial improvements, the permit holder shall provide to the flood plain administrator an as-built certification of the regulatory flood elevation or flood-proofing level immediately after the lowest floor or flood proofing is completed.
(2) The permit holder shall provide the flood plain administrator sealed supplemental construction documents including, but not limited to foundation and structure anchoring details prepared by a licensed professional engineer and/or registered architect. Any lowest floor certification made relative to mean sea level shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same.
(3) When flood proofing is utilized for non-residential structures, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same.
(4) Any work undertaken prior to submission of these certifications shall be at the permit holder's risk.
(5) The flood plain administrator shall review the above referenced certification data submitted.
(6) Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further progressive work being allowed to proceed.
(7) Failure to submit certification or failure to make said corrections required hereby, shall be cause to issue a stop-work order for the project.
Historia
(Ord. No. 18-01, §§ 1, 2, 9-11-2018; Ord. No. 19-05, § 2, 8-13-2019)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.