The entire surface of the in-place subgrade shall be plowed, harrowed and mixed to a depth of at least six inches. After the material has been thoroughly mixed, the top 12 inches of subgrade shall be brought to grade and compacted to 100 percent of the maximum laboratory dry density as tested for both cut and fill sections at a frequency of one test for every 1,000 lineal feet of roadway for a two-lane road with a minimum of one test per street and at all low points and storm drain crossings.
A. Compaction of the subgrade will be accomplished by the use of a sheep's foot roller. In all places that are not accessible by a roller, the required compaction shall be secured by the means of approved mechanical tampers. The same density requirements as stated above shall apply.
B. Prior to placing any subsequent layers of base and paving materials, the subgrade shall have sufficient stability to support construction equipment without excessive movement regardless of compaction.
The city inspector may direct the contractor to proof roll the subgrade with a loaded dump truck.
C. If any sections of subgrade are composed of unsuitable or unstable material, such material shall be removed to a depth directed by the city inspector or the approved geotech engineer, replaced with suitable dry material and compacted to 100 percent of maximum laboratory dry density.
D. The surface of the completed subgrade shall be bladed to a smooth and uniform texture. The centerline profile shall conform to the established elevations with an acceptable tolerance as established by this
UDC.
E. No graded aggregate materials shall be placed on a muddy or frozen subgrade.
F. Test results shall be reported immediately after results are obtained to the city inspector.
G. No graded aggregate material shall be placed on the subgrade until passing compaction results are reported to the city inspector.
H. When a street will be used for construction traffic before paving work is completed, a layer of #3 stone shall be laid as a traffic surface at the entrance of the subdivision for a distance of 50 feet. The developer shall maintain at all times a construction entrance until the graded aggregate base has been approved. This material shall not be used as part of the base material. It may be worked into the subgrade, or it shall be removed before the base course is set up for paving. An alternative method of protecting the base material and the existing street may be used if approved by the city engineer.