110.02.02. Design criteria.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. General. The criteria listed herein is not intended to cover all aspects of design, but rather to mention the basic guidelines and those particulars that are required by the City of Canton.

B. Water supply (all water supply systems).

1) Residential water supply for domestic use shall be in accordance with table 110-1 and provide a minimum pressure of 20 psi.

2) Exceptions may be made when deemed necessary by the city. Demand for other than residential to be determined for each specific development.

3) Residential developments that exceed 150 lots shall have an additional water connection to the existing city water system at each additional entrance.

Table 110-1 Instantaneous Water Demands for Residential Areas Total Number of Residences or Units Served GPM Per Residence Total Number of Residences or Units Served GPM Per Residence 5 8.0 90 2.1 10 5.0 100 2.0 20 4.3 150 1.6 30 3.8 200 1.3 40 3.4 300 1.2 50 3.0 400 0.9 60 2.7 500 0.8 70 2.5 750 0.7 Total Number of Residences or Units Served GPM Per Residence Total Number of Residences or Units Served GPM Per Residence 5 8.0 90 2.1 10 5.0 100 2.0 80 2.2 1,000 0.6

C. Water main extension requirements.

1) All specifications required by the city and by the Georgia Department of Natural Resources must be met by the developer.

2) Developers are required to extend all mains along their entire property frontage if the existing main is adjacent to the proposed development. The size of the main will be set in accordance with subsection D below.

3) If an existing main must be extended to serve a particular development, the developer will be required to pay all of the initial costs, including but not limited to contract prices, testing fees, engineering fees, etc.

4) In certain circumstances, the city may require a larger pipe size to be installed than is required by these standards, and the cost of this over sizing may be funded by the city. The developer may be required to pay all of the initial costs. If the purpose of the over sizing is to improve service to existing customers or part of the city's master plan for a network of large mains to transfer water around the city, the city may enter into negotiations with the developer to provide funding for the betterment.

5) Nothing contained in this section shall be construed as requiring the city to make main extensions or to furnish service to any person.

D. Minimum water main sizes.

1) Any system, whether served from an existing city water main or otherwise, shall have a minimum pipe size of eight inches. Actual sizes may be larger depending on the size required to meet the demand of the proposed development and/or the city's master water plan.

2) Where a water main extension from an existing city water main is required along an existing public right-of-way or future supply route, the size of pipe to be used will be either eight inches, or a size equal to the existing city main, if larger than eight inches, or the size required to meet the demand of the development, whichever pipe size is largest. The city may require a larger pipe size to be installed than is required by this standard. The cost of this over sizing may be funded by the city, in accordance with the line extension policy (subsection C above.)

E. Water main sizes.

1) Multi-family. Water mains shall be no less than eight inches in diameter for multi-family developments.

2) Large shopping centers, malls, etc. Water mains shall be no less than eight inches in diameter.

3) Commercial areas with less than 200,000 square feet. Water mains shall be no less than eight inches in diameter.

4) Motels, light industry and schools. Water mains shall be no less than eight inches in diameter.

5) Commercial areas with 200,000 square feet or more, heavy industry, large/tall buildings.

Water mains shall be no less than ten inches in diameter.

6) Single-family. Single-family residential developments shall use a minimum of 8 inch water mains; larger size mains dependent on demand.

F. Fire protection.

1) Minimum flows.

a. Minimum flows shall meet the requirements of Appendix B of the latest edition of the International Fire Code, as adopted by the State of Georgia.

b. Minimum residential flow: Seven hundred fifty GPM for 30 minutes.

c. The city may require these recommended flow/duration quantities prior to development of property.

2) Fire hydrants will be required as set forth in these specifications where a proposed system is to be served from an existing city water main or in any case where the city is to accept a new system for ownership and operation.

3) Fire protection—Hose lay. Hose lay distance is defined as being measured along the route a piece of fire apparatus must travel in laying a fire hose from the fire to the fire hydrant.

4) All plans for development must meet all applicable fire protection codes.

5) All requirements for design criteria and material and construction specifications must be met to secure a permit from the department of natural resources for construction.

6) Spacing of fire hydrants shall meet the requirements of Appendix C of the latest edition of the International Fire Code, as adopted by the State of Georgia.

a. Fire hydrants shall be located at all intersections and at the end of the line on all cul-de-sacs.

b. Water line extensions along existing roads/highways.

i. Fire hydrants shall be spaced not more than 1,000 feet apart.

ii. Installations requiring fire hydrants shall have a maximum spacing of 1,000 feet as measured along the roadway.

iii. Fire hydrants shall be required at the end of all dead-end lines such as those installed in cul-de-sacs.

iv. Fire hydrants shall be located on the back side of the right-of-way.

v. Fire hydrants shall be located at all intersections.

vi. Fire hydrants shall be located at or within 200 feet of the main entrance to the development.

7) Fire lines shall be metered per subsection J below.

8) Any vault that has a fire department connection must have a fire hydrant on the city water main side of the vault.

G. Sprinkler systems.

1) All in-house sprinkler systems shall have a double check detector assembly equipped with a by-pass meter assembly to monitor low flow.

2) All in ground sprinkler systems shall have a double check backflow preventer.

H. Disconnection of wells.

1) All wells in developments which supply water to distribution are to be disconnected.

2) It shall be the developer's responsibility to fill, plug, and seal the wells in such a manner which meets the requirements of the Georgia EPD rules for safe drinking water.

I. Location of water lines and fixtures.

1) Existing roads.

a. On existing roads, water mains shall be located on the south and west side of the road, within five feet of the edge of the right-of-way whenever possible. Water mains shall be installed so that the top of the pipe is a minimum of four feet below final grade, four feet below the edge of the pavement, or four feet below the ditch paralleling the road, whichever is deepest. Permission must be granted by the city to vary from this requirement.

b. Fire hydrants on existing roads shall be located as near to the right-of-way as practical or as required by the City of Canton or the Cherokee County DOT.

c. Fire hydrants shall be located between the water line and the right-of-way.

d. All water mains located within right-of-way shall be polywrapped.

2) Existing state or federal highways and roads.

a. On existing county, state or federal highways and roads, water mains shall be located on the south and west side of the road whenever possible, and within five feet of the edge of the right-of-way.

Water mains shall be installed so that the top of the pipe is a minimum of four feet below final grade, four feet below the edge of the pavement, or four feet below the ditch paralleling the road, whichever is deepest. Permission must be granted by the Georgia DOT and the city to vary from this requirement.

b. Fire hydrants on existing county, state or federal roads shall be located as near to the right-of-way as practical or as required by the Cherokee County DOT or Georgia Department of Transportation.

c. Fire hydrants shall be located between the water line and the right-of-way.

d. All water mains located within county, state or federal highways and roads right-of-way shall be polywrapped.

3) New streets in subdivisions.

a. Water mains on new streets in subdivisions shall be located on the south and west sides of the streets, five feet from the back of the curb. Water mains shall be installed so that the top of the pipe is a minimum of four feet below final grade, four feet below the edge of the pavement, or four feet below the ditch paralleling the road, whichever is deepest. Permission must be granted by the city to vary from this requirement.

b. Fire hydrants on new streets shall be located between the water main and the right-of-way and as near to the right-of-way as practical.

c. The construction of the water main shall not begin until the rough grading is completed and all curbing is installed.

4) Service laterals.

a. Service laterals shall be located with a minimum bury equal to that of the main line within the right-of-way and reducing to a depth of 12 inches at the water meter location.

i. Service line size shall be one inch for single residential service and one inch for double residential service.

ii. All long side services for single-family residential shall be encased in two-inch PVC pipe.

iii. All long side services for developments other than single-family residential shall be encased in four-inch PVC pipe.

iv. All PVC casings for long side services shall be a minimum of two inches in diameter.

v. The contractor shall install the appropriate size service saddle and corporation stop at the main, service laterals and curb stops in meter boxes.

vi. For double residential services, the contractor shall provide a cut-off valve on the service on the water main side of the service tee, the service tee, all necessary bends and the curb stops in the meter boxes. The cut-off valve on the service shall be buried without a valve box.

b. If a three-inch meter is used for the development, the developer must install four-inch DIP from the main to the meter, and then utilize a four-inch by three-inch reducer at the meter. The city will not accept three-inch service material.

c. Any portion of service lateral located under pavement shall be encased in PVC pipe, extending a minimum of three feet beyond the edge of pavement and/or sidewalk on both sides of the road.

Copper tubing shall be used for all services. A "W" shall be sawed into the curb where each service tap is made for permanent location.

d. At all common areas within residential or other developments, the developer shall include in the water plans a water service and meter at the edge of the street right-of-way.

5) Within commercial developments. Water mains within commercial, multi-family, industrial, office/ institutional or school developments shall be installed so that the top of the pipe is a minimum of four feet below final grade, four feet below the edge of the pavement, or four feet below the ditch paralleling the road, whichever is deepest. Permission must be granted by the city to vary from this requirement.

6) Water valves.

a. Valves less than 16-inch shall be gate valves.

i. Valves 16 inches and larger in diameter shall be butterfly valves.

ii. Water valves at intersections shall be located behind the curb or edge of pavement.

iii. As a general rule, at intersections, the number of valves shall equal the number of streets leaving the intersection. (In other words, four valves where two roads cross and three valves where one road tees into another road.) The city may require valves in excess of this requirement if the water system layout warrants additional valves.

b. The maximum spacing of line valves shall be 1,000 feet.

i. The city may require closer spacing in high-density urban areas and subdivisions. Generally, the city will require a main line valve at every fire hydrant as a minimum. The required spacing shall be at the discretion of the city based on individual development circumstances.

ii. Unless at an intersection, line valves shall be located at fire hydrants.

iii. Concrete valve markers are required at all line valves and at the end of every dead-end line.

c. All fire hydrants shall be provided with a six-inch gate valve between the water main and the hydrant.

i. Wherever possible, the gate valve for a hydrant shall be connected to the main by using a locked hydrant tee.

ii. Wherever possible, the developer shall connect the gate valve to the hydrant by using a locked hydrant adapter or anchor coupling.

iii. When connections using locked hydrant fittings are not feasible, the connections shall be rodded together.

d. All valves shall be provided with valve boxes.

i. Each valve box shall have a concrete collar.

ii. These collars must be a minimum of three and one-half inches thick. They shall be square and sized 24 inches by 24 inches.

iii. Pre-cast collars may be used, provided that they are grouted in place to the valve box.

iv. The box is to be flush with or a maximum of one inch above the finished grade.

v. The edge of the valve box is to be one-half inch above the edge of the concrete collar.

7) Gate valves and line plug.

a. A gate valve and a minimum of 36 linear feet of pipe shall be provided at the end of all lines for phased developments, and at locations where the water main may be extended in the future for water system improvements.

b. The end of the line shall be provided with a M.J. plug and a thrust collar. A valve marker will be placed directly above the plug.

8) Air release valves.

a. Air release valves (ARV) shall be located where appropriate as determined by the design professional responsible for the water system design.

b. All ARV locations are subject to the approval of the city. In general, within subdivisions, ARV's are not necessary as long as services are located at the water main high points.

c. Valve markers are required at each A. and V. assembly.

9) Road crossings.

a. At all road crossings, the water main shall be encased in steel casing. The water main inside the casing shall be restrained with "Field Lok" or "Fast-Grip" gaskets. The ends of the casing shall be sealed with brick to secure the position of the main.

b. Steel casings shall be sized as follows in table 110-2:

Table 110-2 Steel Casing Size Water Main Diameter (inches) Steel Casing Diameter (inches) 6" 12" 8" 12" 10" 16" 12" 18" 16" 24" 20" 30" 24" 36"

10) Polyethylene encasement.

a. Ductile iron water mains shall be provided with black polyethylene encasement whenever the water main either crosses or is in close proximity to a steel gas main.

b. Ductile iron water mains shall be provided with black polyethylene encasement whenever the water main is installed along a city, county, state or federal roadway.

c. Ductile iron pipe (DIP) installed in low-lying damp areas and in areas where anode beds are known to exist shall also be provided with polyethylene encasement.

d. The length of the encasement shall be in accordance with DIPRA recommendations.

e. The city engineer shall have final authority over the required length of the encasement during the plan review process.

11) Easements.

a. Water mains that are located off the right-of-way shall have a minimum 20 feet wide permanent easement.

b. The maximum cross-slope of the permanent easement shall be ten percent.

c. See section 110.02.01.G regarding the requirements for water line easements.

12) Acceleration/deceleration lanes. Where applicable, if an acceleration lane or a deceleration lane is to be constructed and will cover or encroach over existing non-DIP water mains, it is the developer's responsibility to relocate the existing main out from under the proposed pavement and replace the existing main with ductile iron pipe. (See detail W720 "Blow-Off Assembly" in chapter 112.)

13) Dams. Water mains shall be a minimum of 20 feet from the toe of a dam.

J. Fire line metering requirements.

1) All double check detector assembly, compact fire line assembly, or factory mutual fire line meters as required will be handled by the developer under the supervision of the city inspectors. The cost of installation will be at a rate established for each individual site.

2) All existing un-metered fire service systems having private fire hydrants, hand hose connections, or sprinkler heads on private property are required to have an underwriter approved double check detector assembly, compact fire line assembly, or factory mutual fire line assembly with the proper backflow device installed as part of the fire service system.

3) Persons making applications for new fire service connections with private fire hydrants, hand hose connections, or sprinkler heads will be required to have an underwriter approved double check detector assembly, compact fire line assembly, or factory mutual fire line assembly with the proper backflow device installed as part of the fire service system.

4) The contractor shall install a curb stop that can be locked in the on or off position on all two-inch and smaller double check detector assembly (DCDA) connections.

5) When unauthorized (i.e., non-fire fighting water and/or water use without prior notification and approval of the city) is used through the detector meter, the customer will be notified and given 60 days to repair the leak or flow problem. If the meter continues to show usage after the next 60-day reading cycle the customer will then be charged an illegal hook-up fee determined by the city. The city will then determine if a compact fire line assembly or factory mutual fire line meter will need to be installed. If the repair is not made within the given time, this will result in notification to the fire district office and possible disconnection of fire protection water service until corrective action is taken and approved by the city.

6) If the normal usage of the development is such that the service meter required to serve the development is larger than two inches, the city shall require that the developer install an eight-inch or larger compact fire line meter assembly and vault to serve both the normal usage and the fire line needs of the development. If the normal usage of the development is such that a two-inch meter or smaller can be used to serve the development, the developer will be allowed to use a two-inch or smaller meter for the normal usage and a detector meter assembly on the fire line.

7) When unauthorized water is used through a detector meter in three or more billing periods in one calendar year, it shall be replaced with a factory mutual fire line meter. Unauthorized use of water is defined as non-fire fighting water and/or water use without prior notification and approval of the city. The regular monthly fire service standby charge shall be continued for fire service installations having a detector or factory mutual fire line meter. The water that is measured by the detector meter will be billed at five times the normal water charge. If the services of legal council are required to collect bills, the cost of council shall be added to the billing.

8) The detector meters on the backflow preventers shall be Neptune T-10 with E-Coder Register compatible with the city's meter reading equipment.

9) All domestic water supplies must be metered with a proper meter.

10) Installation of detector meters or factory mutual fire line meters as required will be the responsibility of the developer under supervision of the city's inspectors.

11) The city shall have the right to cut off water service to buildings whose owners refuse to comply with these provisions upon proper notification of 60 days.

K. Water pump stations. Where pump stations are required to serve a development, the developer's design professional shall prepare and submit detailed plans, specifications and calculations for the city's review.

Design requirements shall be discussed in the preliminary stages of plan review. Each case shall be reviewed individually, and the city shall retain the right to require changes to the pump station design or materials at the city's discretion.

L. Water mains on private roads. The city may accept for ownership water mains installed along roadways that are not dedicated for public use (i.e., are without public right-of-way) if the property owners dedicate a permanent easement to the city.

M. Protection of water supply and other utilities.

1) Cross connection control.

a. The City of Canton has an established cross-connection program to prevent the entry of contaminants or pollutants into any area of the potable water supply through the control of cross connections.

b. It is illegal to introduce any substance into or to have any cross connections with the potable water supply.

c. There shall be no physical connection between a public or private potable water supply system and a sanitary sewer which would permit the passage of any sewage or polluted water into the potable water supply.

d. See also the cross-connection control program section of this chapter.

2) Separation between water main and sanitary sewer mains.

a. Whenever possible, water mains should be laid at least ten feet horizontally from any existing or proposed sanitary sewer main. Should conditions prevent a separation of ten feet, the lines shall be laid in separate trenches. In either case, the elevation of the invert of the water main shall be at least 12 inches above the crown of the sewer. These distances are measured edge to edge.

b. When water mains cross over sewer mains, the water main shall be laid so that the invert of the water main shall be at least 18 inches above the crown of the sewer. The two pipes shall be installed such that a full length of pipe will be centered over the crossing so that all joints will be separated as much as possible. Ductile iron pipe shall be installed for both mains.

c. In the rare circumstance when the 18-inch clearance between the water and sewer mains cannot be maintained, the DIP mains shall be installed as described in the paragraph above with the joints as far apart as possible, plus both mains shall be placed in casing for a distance of ten feet on each side and grout each end of casing.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2014-18, § 2, 8-21-2014; Ord. No. 2017-07, 3-16-2017; Ord. No. 2018-0920-02, 9-20-2018)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:canton/zoning/110.02.02@2026-11-11-b6fd844000

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Canton Zoning Ordinance, 110.02.02. Design criteria | Georgia Commons