Section 7.12.7. Maintenance of Ponds and Facilities.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. Facilities to be Accepted by the City. If a proposed residential facility or pond is intended for acceptance by the City, then it must be located on a separate lot and deeded to the City along with an access way that is at least 20 feet in width containing the 10-foot wide access road. The access way shall either be a portion of the lot having frontage on a street, or an access easement connecting the lot to a street. The access road shall be constructed to standard specifications of the Engineering Department. The lot need not meet zoning requirements as a buildable lot.

B. Variance. A variance from side yard setbacks may be requested from the Planning Division if the 20-foot access prohibits the builders from complying with zoning requirements.

C. Petition for Acceptance. The developer should petition the City for acceptance upon completion of construction.

D. Bond. A continuous two year maintenance bond to cover the maintenance and construction shall be provided. The bond will remain in effect until released by the Department of Engineering at which time the City will assume maintenance of the facility.

E. Perimeter Buffering. The perimeter of the parcel deeded to the City for detention ponds and access shall be planted with good living 4 foot high Burford Holly, Ligustrum Japonicum (wax leaf privet), Leland Cypress, or approved equal and set 4-foot on centers.

1. Minimum Maintenance Period. All plants shall be in good living condition at the end of the two year maintenance period and shall have been planted a minimum of one year.

2. Extended Warranty for Planting. If the 1 year planting cannot be met then an extended warranty shall be required.

F. Maintenance of Private Stormwater Management Facilities.

1. The owner/operator of a private stormwater management facility (i.e., a facility not accepted by the City that serves any development) shall perpetually be responsible for the proper operation and maintenance of said facility. Failure to operate or maintain a stormwater management facility in accordance with this chapter shall be a violation of this Chapter. Should it become necessary for the City to perform work (or have a private contractor perform work on behalf of the City) in order to maintain a private facility, then the City may place a lien against the property until full reimbursement for the work performed by City forces, or work paid for by the City, is recovered.

2. The owner of a private stormwater management facility shall submit an annual maintenance report to the City. The annual report will document all maintenance and inspection activities conducted by the owner on his/her stormwater management facility(ies) for each calendar year.

Blank maintenance and inspection reports, provided by the City, shall be completed by the owner or his/her designee for each facility and returned to the City no later than January 31 of the following year. This requirement applies to all existing and future stormwater management facilities; both inside and outside the Combined Sewer Area and shall go into effect January 1, 2016. The first reports under the requirement will be due by January 31, 2017.

Failure to provide the City with an adequate Annual Report by the deadline shall be a violation of this Chapter.

3. Maintenance and Inspection standards and schedules expected by the City mirror those found in the most recently published Georgia Stormwater Management Manual (GSMM). Should prescribed maintenance and inspection activities and recommended schedules not be included in the GSMM, those activities and schedules recommended by the device's manufacturer, at a minimum, will be required.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 09-52, § 1, 11-10-09; Ord. No. 15-53, § 4, 10-27-15)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:columbus-muscogee/zoning/7.12.7@2026-11-11-9579b7d81b